Easterly Tunnel Dewatering Pump Station

Easterly Tunnel Dewatering Pump Station

Easterly Tunnel Dewatering Pump Station

SHOW MORE
SHOW LESS

You also want an ePaper? Increase the reach of your titles

YUMPU automatically turns print PDFs into web optimized ePapers that Google loves.

ETDPS Programmed to be CompleteShortly After ECT is Activated and Readyto Accept Flows.Project2011 2012 2013 2014 2015 2016 2017Euclid Creek Storage <strong>Tunnel</strong>Apr 2011 4 years duration Apr 2015SHORT PERIOD TO FINALIZE WORK<strong>Tunnel</strong> <strong>Dewatering</strong> <strong>Pump</strong> <strong>Station</strong>Jan 2012 3 years 6 months duration Jun 2015Dugway Storage <strong>Tunnel</strong>Sep 20154 years durationETDPS must coordinate w/ ECT for final connections:• Install Roller Gate• Final Adit Connection• <strong>Pump</strong> Testing and Commissioning13