ETDPS Programmed to be CompleteShortly After ECT is Activated and Readyto Accept Flows.Project2011 2012 2013 2014 2015 2016 2017Euclid Creek Storage <strong>Tunnel</strong>Apr 2011 4 years duration Apr 2015SHORT PERIOD TO FINALIZE WORK<strong>Tunnel</strong> <strong>Dewatering</strong> <strong>Pump</strong> <strong>Station</strong>Jan 2012 3 years 6 months duration Jun 2015Dugway Storage <strong>Tunnel</strong>Sep 20154 years durationETDPS must coordinate w/ ECT for final connections:• Install Roller Gate• Final Adit Connection• <strong>Pump</strong> Testing and Commissioning13