DATE: JANUARY 9, 2012<br />
<strong>City</strong> <strong>of</strong> <strong>Alexandria</strong>, Virginia<br />
__________________<br />
MEMORANDUM<br />
TO: PARK & RECREATION COMMISSION MEMBERS<br />
FROM: RASHAD K. FRIDAY, MBA, MS, CIVIL ENGINEER III;<br />
LISA JAATINEN, P.E., CIVIL ENGINEER IV<br />
SUBJECT: WASHINGTON STREET STREETSCAPE PROJECT-ITEM III<br />
ITEM:<br />
As a part <strong>of</strong> the Woodrow Wilson Bridge (WWB/Federal Highway Administration<br />
settlement agreement, The <strong>City</strong> <strong>of</strong> <strong>Alexandria</strong> is planning to make improvements to the<br />
South Washington Street Right-Of-Way between Church Street and Gibbon Street. The<br />
proposed improvements are intended as infrastructure improvements that will<br />
aesthetically improve and enhance the existing streetscape. The scope <strong>of</strong> the project<br />
includes enhancements to the lighting, sidewalk and streetscape improvements, traffic<br />
safety improvements, landscape improvements, and drainage improvements. On January<br />
25, 2012 at 6:00 p.m., T&ES has scheduled a public meeting at <strong>City</strong> Hall, Sister Cities<br />
Conference Room 1101, to discuss the proposed project improvements, project schedule,<br />
potential impacts, mitigation efforts, and answer questions. The project is scheduled to<br />
begin construction in the summer <strong>of</strong> 2012. If you have any questions, please feel free to<br />
contact rashad.friday@alexandriava.gov.<br />
ANTICIPATED PROJECT TIMELINE:<br />
March 1, 1999 Project part <strong>of</strong> WWB/FHWA Settlement Agreement<br />
August 2011 Project Kick<strong>of</strong>f with VDOT/FHWA<br />
Septemeber 2011 Project Design Begins<br />
December 2011 30% Plans complete<br />
January 6, 2012 Memo to Council Update<br />
January 11, 2012 Citizen Information Meetings<br />
January 18, 2012 BAR Informational Meeting<br />
January 19, 2012 Update to Park and Recreation Commission<br />
January 25, 2012 Public Hearing<br />
February 17, 2012 90% Plans complete<br />
February 28, 2012 Council Design Approval & Resolution<br />
March 15, 2012 VDOT Design Approval<br />
April 16, 2012 Advertisement<br />
June 15, 2102 Construction Award<br />
July 2, 2012 Begin Construction<br />
# # #