13.07.2015 Views

Domestic Wastewater Treatment Mobilization Construction - AskTOP

Domestic Wastewater Treatment Mobilization Construction - AskTOP

Domestic Wastewater Treatment Mobilization Construction - AskTOP

SHOW MORE
SHOW LESS

You also want an ePaper? Increase the reach of your titles

YUMPU automatically turns print PDFs into web optimized ePapers that Google loves.

EM 1110-3-17211 May 84excavated drain will be provided at the toe of the exterior slope toconvey seepage water, over-topping loss, or spillage due to dikefailure to the receiving watercourse for the waste stabilization ponddischarge . Protection from wind and water erosion will be provided asneeded .d . Bottom . The bottom will be as level as practicable withvariations not exceeding 6 inches from the designed bottom elevation .This does not apply to the dished area around the inlet, covered byparagraph 9-3 .a . The bottom will be cleared, grubbed, and sealed toprevent loss of liquid through excess seepage . If ground waterprotection is a requirement or desirable, then a liner would benecessary depending on soil permeability . If the soil permeability is10-7 cm/second or better, a liner would not be required . For lesserpermeabilities, a water barrier of some kind should be provided . Someacceptable lining materials are various synthetics, bentonite, clay, orpavement materials such as concrete or asphalt .e . Surface runoff control . Surface runoff will be excluded,fromwastewater treatment ponds . Intercepting drains, diversion ditches,and/or dikes will be constructed as required to comply with thisrequirement . When surface drainage must be rerouted to meet therequirement, rerouted drainage will be routed to the original drainagecourse to the maximum extent possible .f . Fencing and access . The entire wastewater treatment ponds areawill be provided with a locked security fence that will have a doublewide gate for vehicular access . A gravel road not less than 10 feetwide will be provided through this gate and around the new dike .g . Flow operation modes . In no case will a raw wastewatertreatment pond have less than two cells . Operation will normally be inseries, with piping flexibility permitting parallel or seriesoperation, recirculation if desired, and isolation and removal fromservice of any unit without interference in operation of any otherunit . The maximum design BOD loading rate to each pond cannot beexceeded for any mode of operation .9-7

Hooray! Your file is uploaded and ready to be published.

Saved successfully!

Ooh no, something went wrong!