Center16. Remove large plug from sealing fitting. Pull heating cable back through component hardware,centering end of outer jacket in sealing fitting opening. Be sure no yellow/green tubing extendsinto seal fitting.17. Position grommet in cavity. Install screws in compression gland and tighten firmly. Be careful notto change position of heating cable in sealing fitting. Screw corrugated tubing onto end ofcompression gland. Install tubing clamp.33