Haryana State Agricultural Marketing Board
13.Panchkula - Haryana Marketing Board
13.Panchkula - Haryana Marketing Board
Create successful ePaper yourself
Turn your PDF publications into a flip-book with our unique Google optimized e-Paper software.
44616 09-Apr-13<br />
39983 16-Jan-13<br />
31771 23-Aug-12<br />
10879 14-Oct-11<br />
10881 30-Jul-11<br />
Tender received on 04.02.13 for balance work in 5th priority.<br />
Tender in approval process. CC Road in 410 m is in good condition.<br />
Brick on edge on berms is pending.<br />
Tender to be received on 04.02.2013 at risk and cost of Inderpal<br />
and co.<br />
Good condition, C.C. laid , berms pending.<br />
75mm WBM + Cement concrete in entire length was sanctioned on<br />
14/1/2008 (5th priority), allotted on 11/4/2008 (Inder Pal). Work<br />
done except brick on edge on the side. Tenders for brick on edge on<br />
31/10/2011.<br />
Constructed 1/1997. Path 4 karam. Crust 150mm. PC done in 2001.<br />
10) H - 1715 Symtoo To Kanauli Panchkula<br />
1.35 km.<br />
60442 31-Dec-13<br />
60273 21-Dec-13<br />
47803 30-May-13<br />
44926 10-Apr-13<br />
44617 09-Apr-13<br />
40870 13-Feb-13<br />
39984 16-Jan-13<br />
37887 27-Nov-12<br />
31770 23-Aug-12<br />
18364 17-Feb-12<br />
10899 30-Jul-11<br />
D/E sanctioned for Rs. 84,54,164/-. (5th priority)<br />
D/E tech. sanctioned for Rs. 8454164/- for a group of 1724, 1712,<br />
1725, 1726, 1714, 1727, 1715, 1716, 1717, 1718, 1719, 1720, 1721,<br />
1722 & 1723.<br />
AR tender on 29.05.2013 received and work allotted on 29.05.2013.<br />
No need of brick on edge. AR be done. Work be closed.<br />
Tender received on 04.02.13 for balance work in 5th priority.<br />
Tender in approval process. Brick on edge on berms is pending.<br />
Taken in A/R 2012-13.<br />
Tender to be received on 04.02.2013 on risk and cost.<br />
The history of memos shows that officers are misrepresenting<br />
about progress. SE to visit site on 30th Nov. give correct picture<br />
and settle issues regarding need of remains works.<br />
Good condition, C.C. in some portion and berms pending.<br />
In 465m CC (RD885-1350m in vill. Kanauli) and rest PC sanctioned<br />
on 14.01.2008 allotted on 11.04.2008(Inder Pal).<br />
Constructed 3/1989. Path 5 karam. Crust 150mm. PC done in 2002.<br />
11) H - 1717 Tibbi To Shiv Mandir Panchkula<br />
0.46 km.<br />
60444 31-Dec-13<br />
60275 21-Dec-13<br />
50956 03-Jul-13<br />
44583 09-Apr-13<br />
40845 13-Feb-13<br />
31776 23-Aug-12<br />
10987 14-Oct-11<br />
D/E sanctioned for Rs. 84,54,164/-. (5th priority)<br />
D/E tech. sanctioned for Rs. 8454164/- for a group of 1724, 1712,<br />
1725, 1726, 1714, 1727, 1715, 1716, 1717, 1718, 1719, 1720, 1721,<br />
1722 & 1723.<br />
193.42 Sqm patch done from 24/5/2013 to 26/5/2013 (Exp 79 k).<br />
Road is in good condition except 30 mtr stretch is where there are<br />
skin patches and village drain water flows over the road.<br />
Taken in A/R 2012-13. A/R will be done 2013-14.<br />
Repair required in half portion due to street reach , last S/R done in<br />
04, 2010.<br />
Constructed 2001. Path 4 karam. Crust 150mm. Patch + PC in<br />
8/2009. Patches (45 sqm) done in 14/8/2011 to 20/9/2011 (9.8K).<br />
12) H - 1719 Kalka Bargodam Road To Paploha Kalka<br />
0.16 km.<br />
60446 31-Dec-13<br />
60277 21-Dec-13<br />
D/E sanctioned for Rs. 84,54,164/-. (5th priority)<br />
D/E tech. sanctioned for Rs. 8454164/- for a group of 1724, 1712,<br />
1725, 1726, 1714, 1727, 1715, 1716, 1717, 1718, 1719, 1720, 1721,<br />
1722 & 1723.<br />
Monday, January 20, 2014 Page 4 of 24