DEPARTMENT OF DEFENSE / RECOVERY ACT<br />
FACILITIES SUSTAINMENT, RESTORATION, & MODERNIZATION PLAN – ATTACHMENT A<br />
Installation/Location State Cat.<br />
254 Vandenberg AFB CA E<br />
255 Vandenberg AFB CA O<br />
256 Vandenberg AFB CA E<br />
257 Vandenberg AFB CA E<br />
258 Vandenberg AFB CA P<br />
259 Vandenberg AFB CA P<br />
260 Vandenberg AFB CA E<br />
261 Vandenberg AFB CA E<br />
262 Vandenberg AFB CA P<br />
263 Vandenberg AFB CA P<br />
264 Vandenberg AFB CA R<br />
265 Vandenberg AFB CA O<br />
266 Vandenberg AFB CA R<br />
267 Vandenberg AFB CA E<br />
268 Vandenberg AFB CA P<br />
269 Vandenberg AFB CA E<br />
270 Vandenberg AFB CA P<br />
Cost Contract<br />
Construction<br />
Project<br />
Estimate Award Construction Completion<br />
Number Project Title<br />
($000) Date Start Date Date<br />
XUMU081157<br />
B<br />
Replace HVAC Unit, Civil Engineer Maint Shop 223 May-09 Aug-09 Nov-09<br />
XUMU061136<br />
B<br />
Renovate Training Facility at Civil Engineer Horizontal Shop,<br />
Bldg 10719<br />
241 Jun-09 Jul-09 Dec-09<br />
XUMU091138<br />
B<br />
Repair Chillers for Electronics Lab at Missile Maint Fac 262 Jun-09 Aug-09 Nov-09<br />
XUMU101065<br />
B<br />
Maintain Backflow Prevention Devices Basewide, Fy09 269 Sep-09 Sep-09 Sep-10<br />
XUMU111004<br />
A<br />
Repair North Edge of Road West of Bldg 441 281 Apr-09 May-09 Jun-09<br />
XUMU991022<br />
B9<br />
Repair 8th Street 348 May-09 Jun-09 Oct-09<br />
XUMU061191<br />
E<br />
Energy Audit, Validate Short Circuit Analysis 377 Jul-09 Aug-09 Aug-10<br />
XUMU101090<br />
A<br />
Replace Electrical Switchgear at Ct-3 377 Jul-09 Oct-09 Dec-10<br />
XUMU101070<br />
C<br />
Construct Parking Lot Extension for Bldg 8314 444 Apr-09 May-09 Aug-09<br />
XUMU021010<br />
A<br />
Repair 35th Street 445 Apr-09 Jun-09 Jun-09<br />
XUMU071067<br />
B<br />
Repair Roof at Delta IV Solid Rocket Motor Facility 509 Apr-09 May-09 Mar-10<br />
XUMU091375<br />
A<br />
Base-Wide Facility Painting Contract 538 Apr-09 Apr-09 Oct-09<br />
XUMU081025<br />
B<br />
Repair Roof at Launch Vehicle Fab Shop, Bldg 8305 552 Apr-09 Jun-09 Dec-09<br />
XUMU081459<br />
B<br />
Repair CRAC Units In Admin Bldg 7025 597 May-09 Oct-09 Oct-10<br />
XUMU061155<br />
B1<br />
Repair 30 Mission Support Group HQ Overflow Parking Lot 614 Apr-09 May-09 Jul-09<br />
XUMU061075<br />
B5<br />
Replace HVAC, Phase 3, Launch Control Center 738 Jul-09 Oct-09 Apr-10<br />
XUMU051091<br />
B<br />
Repair 13th Street From Iceland Ave to California Blvd 856 Jun-09 Jul-09 Nov-09<br />
(1) Gap in project numbers results from project cancellations<br />
(2) Estimated construction dates are in plain text, actual construction dates are in italics<br />
(3) The projects listed represent those in the program as of 31 March 2010<br />
(4) As this annual update was done in May, any actual dates between 01 April 2010 and May 2010 are identified as actual dates<br />
Construction<br />
Attachment A – Page 140 of 225