Installation/Location State Cat.<br />
Project<br />
Number Project Title<br />
Cost<br />
Estimate<br />
($000)<br />
Contract<br />
Award<br />
Date<br />
Construction<br />
Construction<br />
Start Date<br />
Construction<br />
Completion<br />
Date<br />
1809 Aberdeen Proving Ground MD O 34249 Provide Concrete Berm, 507 50 Oct-09 Nov-09 Feb-10<br />
1810 Aberdeen Proving Ground MD E 34258 Repair HVAC In Bldg 331 175 Dec-09 Jan-10 Aug-11<br />
1811 Aberdeen Proving Ground MD E 34388 Repair Environmental Control Systems, E3100 350 Jul-09 Jan-10 Feb-11<br />
1812 Aberdeen Proving Ground MD R 34397 Repair Roof Leak, Building 4600 100 Jun-09 Jan-10 Feb-11<br />
1813 Aberdeen Proving Ground MD R 34404 Repair Roof, Building 642 195 Jul-09 Sep-09 Jan-10<br />
1814 Aberdeen Proving Ground MD E 34405 Repair A/C and Heat Units, Admin Bldgs E4586/88 150 Sep-09 Mar-10 May-11<br />
1815 Aberdeen Proving Ground MD E 34407 Repair A/C, Bldg 4401 50 Dec-09 Mar-10 Aug-11<br />
1816 Aberdeen Proving Ground MD E 34415 Repair Boiler, Maintenance Bldg E1464 150 Dec-09 Jan-10 Aug-11<br />
1817 Aberdeen Proving Ground MD R 34423 Repair Roof, E5102 50 Jul-09 Jul-09 Nov-09<br />
1818 Aberdeen Proving Ground MD O 34425 Repair Restroom Facilities Bldg E2188 50 Aug-09 Aug-09 Mar-11<br />
1819 Aberdeen Proving Ground MD R 34455 Repair Roof, E5141 60 Aug-09 Aug-09 Oct-09<br />
1820 Aberdeen Proving Ground MD E 35590 Replace exterior steam lines serving several bldgs 500 Dec-09 Jan-10 Oct-11<br />
1821 Aberdeen Proving Ground MD R 35601 Repair Roof, E5101 100 Oct-09 Nov-09 Dec-09<br />
1822 Aberdeen Proving Ground MD E 35687 Replace Main Electric Switch Gear and Motor Control Center 50 Jun-09 Jan-10 Feb-11<br />
1823 Aberdeen Proving Ground MD R 36217<br />
Repair Child Development Center Facility, 2485-Repair Roof,<br />
Sprinkler, Floor, Mechanical Systems<br />
1,800 Sep-09 May-10 Apr-11<br />
1824 Aberdeen Proving Ground MD Q 36218<br />
Repair Family Support bldg 2522- Kitchen, Floors, Walls,<br />
Windows, Doors, Mechanical<br />
750 Feb-10 May-10 Oct-11<br />
1825 Aberdeen Proving Ground MD R 36219<br />
Repair Fitness Facility, Bldg 3300- Roof, Interior Floors,<br />
Doors, and Finishes<br />
900 Feb-10 Jul-10 Sep-11<br />
1826 Aberdeen Proving Ground MD E 36221<br />
Repair Fitness Center, Bldg E4210--floors, HVAC, cardiac<br />
area<br />
346 Sep-09 Jan-10 May-11<br />
1827 Aberdeen Proving Ground MD R 37568<br />
Repairs to Operations Building E2433-Repair Roof, Doors,<br />
Parking<br />
100 Jul-09 Jul-09 Nov-09<br />
1828 Aberdeen Proving Ground MD O 37587 Repair Modified Record Fire Range 700 Mar-10 Jul-10 Aug-11<br />
1829 Aberdeen Proving Ground MD E 37594 Repair Barracks Building 2503, Repair Finishes, Elect, 1,500 Jul-09 Jul-09 Feb-11<br />
(1) Gap in project numbers results from project cancellations<br />
(2) Estimated construction dates are in plain text, actual construction dates are in italics<br />
(3) The projects listed represent those in the program as of 31 March 2010<br />
(4) As this annual update was done in May, any actual dates between 01 April 2010 and May 2010 are identified as actual dates<br />