DEPARTMENT OF DEFENSE / RECOVERY ACT<br />

FACILITIES SUSTAINMENT, RESTORATION, & MODERNIZATION PLAN – ATTACHMENT A<br />

(1) Gap in project numbers results from project cancellations<br />

(2) Estimated construction dates are in plain text, actual construction dates are in italics<br />

(3) The projects listed represent those in the program as of 31 March 2010<br />

(4) As this annual update was done in May, any actual dates between 01 April 2010 and May 2010 are identified as actual dates<br />

Construction<br />

Cost Contract Construction<br />

Project<br />

Estimate Award Construction Completion<br />

Installation/Location State Cat. Number Project Title<br />

($000) Date Start Date Date<br />

135 Yuma Proving Ground AZ P 20285 Repair Parking Lots - LAAF 1,148 Sep-09 Dec-09 Apr-11<br />

136 Yuma Proving Ground AZ E 35354 Repair Substation Transformers 1,100 Dec-09 May-10 Oct-11<br />

137 Yuma Proving Ground AZ E 34848 Retrofit Light Switches W/ Occupancy Sensors/ Timers 800 Sep-09 Jan-10 Apr-11<br />

138 Yuma Proving Ground AZ E 34847 Replace Exterior Door Weather Stripping 125 Sep-09 Jan-10 Apr-11<br />

139 Yuma Proving Ground AZ E 34846 Repair Baseball Court Lighting W/ Energy Efficient System 20 Sep-09 Jan-10 Apr-11<br />

140 Fort Irwin CA B 10398<br />

Repair Barracks Building 264-Repair Walls, Floors, Ceilings,<br />

Latrines, Electric.<br />

3,100 Aug-09 Dec-09 Mar-11<br />

141 Fort Irwin CA B 20160<br />

Repair Barracks Building 98-Repair Walls, Floors, Ceilings,<br />

Latrines, Electric.<br />

1,800 Jul-09 Nov-09 Mar-11<br />

142 Fort Irwin CA E 20130 Repair Chilled/Hot Loop Feed System Ph 3 1,200 Aug-09 Sep-09 Feb-10<br />

143 Fort Irwin CA Q 37198<br />

Repair Athletic Center Buildings 324, 327, 328, 337, 338-<br />

Repairs to Finishes, HVAC, Walls, Floors, Etc.<br />

880 Dec-09 May-10 Aug-11<br />

144 Fort Irwin CA E 20159 Construct Additional Perimeter Lights Asp - Phase 3 676 Mar-10 May-10 Sep-11<br />

145 Fort Irwin CA E 34632<br />

Repair Street Lights & Install Solar Street Lights for<br />

Cantonment Area<br />

650 Mar-10 May-10 Sep-11<br />

146 Fort Irwin CA R 36265 Repair Roof, Building 361, Recreation Center 350 May-10 Jun-10 Oct-11<br />

147 Fort Irwin CA E 39041<br />

Repair Street Lights & Install Solar Street Lights for<br />

Cantonment Area - Phase 2<br />

350 Mar-10 May-10 Sep-11<br />

148 Fort Irwin CA E 36266 Repair HVAC, Building 361, Recreation Center 300 May-10 Jun-10 Oct-11<br />

149 Fort Irwin CA E 37574 Construct Parking Lot Lights Building 940 250 Mar-10 May-10 Sep-11<br />

150 Fort Irwin CA Q 37217 Repair Kitchen Ventilation System Building 1317 125 Apr-10 Jun-10 Aug-11<br />

151 Fort Irwin CA Q 38778 Repair Infant Playground Area 50 Mar-10 May-10 Aug-11<br />

152 Fort Irwin CA Q 38765 Repair Pre-School Playground Area 50 Mar-10 May-10 Aug-11<br />

153 Presidio of Monterey CA O 38519 Remove Inactive Communication Lines, base-wide 590 Aug-09 Jan-10 Mar-11<br />

154 Presidio of Monterey CA E 29645<br />

Replace Barracks Failing HVAC Systems, Barracks Buildings<br />

647, 650, 651,<br />

484 Aug-09 Mar-10 Apr-11<br />

Attachment A – Page 8 of 225