29.09.2015 Views

SMALL DAMS

SMALL DAMS - Comité Français des Barrages et Réservoirs

SMALL DAMS - Comité Français des Barrages et Réservoirs

SHOW MORE
SHOW LESS
  • No tags were found...

You also want an ePaper? Increase the reach of your titles

YUMPU automatically turns print PDFs into web optimized ePapers that Google loves.

Chapter IV<br />

CONSTRUCTION PRINCIPLES TO BE STIPULATED IN THE PARTICULAR TECHNICAL<br />

CLAUSES<br />

Protection of the construction site from water<br />

This addresses the following problems:<br />

!" collecting springs and infiltration, and release outside the various excavations;<br />

temporary or permanent structures may be required;<br />

!" protection of the fill and the borrow areas from runoff;<br />

!"the particular technical clauses should stipulate up to what flow the construction site<br />

should be protected, for example the 10-year flood calculated over the period of<br />

construction, but for practical reasons, this flow will be translated into an elevation in<br />

the tender documents and contract. That elevation will be referenced to a fixed point<br />

downstream from the construction site. The contractor bears the sole liability for protection<br />

of the construction site and his equipment as long as that elevation is not<br />

exceeded.<br />

Conditions for quarrying in borrow areas<br />

The preliminary studies will have defined the various types of materials encountered<br />

in the borrow areas and, according to their intrinsic and in situ characteristics, will<br />

have assigned them a function and a place in the structure, or for some of them, will<br />

have decided to eliminate them.<br />

Additional site investigations and tests must be done to detail the results of the study<br />

as soon as the test section is begun.<br />

After stripping to eliminate and store topsoil and plant debris, a plan for operation of<br />

the borrow area defining what part of the structure the various materials are destined<br />

for should be set up.<br />

Materials are extracted either in horizontal layers, which would permit some drying<br />

by the sun and the wind, or in vertical layers, which would permit mixing of the<br />

various layers.<br />

The extracted materials can only be placed directly if their water content is within the<br />

prescribed range. If not, drainage of the borrow areas or temporary storage for<br />

drying or wetting can be necessary, and a cost for this work should be given in the<br />

price schedule.<br />

101<br />

Preparation of excavations<br />

After examination of the base of the embankment and the cut-off, it may prove<br />

necessary to excavate deeper.<br />

Before placing any fill or concrete:<br />

!" the surface of the excavation bottom must be cleaned and strengthened;<br />

!" a detailed survey must be done;<br />

!" the excavations must be formally accepted (see Chapter III, p. 62).

Hooray! Your file is uploaded and ready to be published.

Saved successfully!

Ooh no, something went wrong!