Create successful ePaper yourself
Turn your PDF publications into a flip-book with our unique Google optimized e-Paper software.
i<br />
iculars on 1 December 1938 at an estimat€d<br />
cost of f400,000 per vessel. On<br />
the 3fth, approval was given to orderten<br />
vessels. However, the order for the second<br />
group of ten vessels was to be delayed<br />
pending the evaluation ofthe alternative<br />
design armed with torpedoes.<br />
The functions of the vessels were listed<br />
under the staff requirement for the 1939<br />
fast escort vessel (ADM I/9<strong>44</strong>0):<br />
o<br />
r<br />
o<br />
e<br />
To supplement existing vessels on<br />
A/S and A,/A escort duties.<br />
To provide A/S and A,zA escort for<br />
fast transports and detached units<br />
of the fleet.<br />
For use at home and abroad.<br />
The vessels could be used fortraining<br />
in peacefime.<br />
The Initial Building<br />
Programme and Problems<br />
Tenders, to be received by 20 January<br />
1939, were invited on 20 December 1938.<br />
However, all the firms asked to tender<br />
said that the Engineer-inchiefs estimate<br />
of 270 tons for machinery was 30 tons too<br />
low. It was agteed to use 285 tons. Second,<br />
the legend hull weight was stated as 450<br />
tons (despite the detailed calculation of<br />
495 tons). The shipbuilders suggested 475<br />
tons and finally a figure of 460 tons with a<br />
margin of ten tons was agteed. By using<br />
D quality steel, the shipbuilders saved 13<br />
tons ofhull weight, leaving the design 14<br />
tons overweight compared with the<br />
revised estimate of 460 tons.<br />
A second problem arose when the<br />
stability of the vessels was checked and<br />
found to be 0.8 feet lower than originally<br />
calculated. After discussions with the<br />
builders, the beam of the vessels was<br />
increased by 9in to 29 feet on 14 February<br />
1939. The extra beam increased the hull<br />
weight by five tons and the full load by 7<br />
tons as the tanks got bigger. The speed of<br />
the vessels was reduced by 0.1 hrots.<br />
On 14 March 1939. the First Sea Lord<br />
{irected that in order to speed production,<br />
the second batch of ten vessels were to be<br />
repeats ofthe first ten. A week later, the<br />
first ten were ordered, to be followed<br />
quickly by the ordering of the second<br />
batch of ten vessels on 11 April 1939. the<br />
first units of the class were laid down on 8<br />
June 1939 on the expiry of TYeaty<br />
obligations. Progress was rapid with 18<br />
vessels being laid down before the<br />
declaration of war and, Atherstone,<br />
Hambledon and Eglintonbeing launched<br />
before 1939 had closed.<br />
Athe r s to ne's St ab ility<br />
Problems<br />
Atherstone was nearing completion and<br />
as usual an inclining experiment was<br />
undertaken to check the weight and the<br />
It would seem that the detailed calculations<br />
of her stability had been repeated<br />
and a serious error found. Goodall noted<br />
in his diary: "Cole came in with<br />
Atherstone's inclining results. GM 1 foot<br />
'tion, less than calculated. bad errorin calculashall<br />
have to do something drastic."<br />
After an investigation, the reasons for<br />
this error were discussed. First there was<br />
an original error in the preliminary calculation<br />
for the KG ofthe hull structure and<br />
fittings (it appears that the upper deck<br />
was taken as 7 feet above the keel instead<br />
of 17 feet). This was responsible for twothirds<br />
of the loss of stability. Second, the<br />
vessels turned out to be 60 to 70 tons<br />
heavier than estimated. This should have<br />
been expected, especially in light of the<br />
problems raised by the builders the<br />
previous year. This increase in weight<br />
was responsible for the other third of the<br />
loss of stability.<br />
The vessels were altered in the following<br />
ways to restore stability:<br />
o No 2 4in twin mounting was<br />
landed.<br />
o The funnel and bridge were cut<br />
down to reduce top weight.<br />
e 52 tons of permanent ballast was<br />
fitted.<br />
In fact, 23 vessels had to be altered this<br />
way, as three vessels of the second group<br />
(ordered in September and December<br />
1939), Blencathra, Brochlesby and Liddesdale,<br />
were already too far advanced<br />
to be widened and received modifications<br />
similar to those affected to the first<br />
group.<br />
It would seem that the stability<br />
problems that arose in Atherstone werc a<br />
result of the pressure being placed on<br />
naval constructors during 1938 and 1939.<br />
Supervision was inadequate and the<br />
head of section must be to blame for not<br />
checking the design of the new class<br />
against the Blqck Swan cfass, also armed<br />
with-three twin 4in guns on a beam of 37<br />
feet. Second, there were inadequate<br />
checks on the weights to be used in the<br />
design.<br />
The Deuelopment of the<br />
Type 2 Vessels<br />
To speed up production, these 36 vessels<br />
had originally been ordered as repeats of<br />
the original group. These vessels, except<br />
for those mentioned earlier, incorporated<br />
the following alterations to improve<br />
stability:<br />
r<br />
The beam of the vessels was<br />
increased by 2 feet 6in to 31 feet 6in.<br />
It is believed that some vessels<br />
were<br />
'kippered'<br />
on the slip to<br />
incorporate the required beam, by<br />
widening shell strakes.<br />
o<br />
further aft.<br />
The funnel was lowered'<br />
As a result of these modifications no<br />
permanent ballast was shipped. Further<br />
changes were made to these vessels to<br />
enhance their anti-aircraft provision, by<br />
fitting a quadruple 2-pounder and two<br />
single 20mm Oerlikon. The specifications<br />
of the Tlpe 2s were as follows:<br />
kngth: 280 feet (oa) 264 feet &etween pp)<br />
Beam: 31[ feet<br />
Displacement: 1050 tons (standard), 1430<br />
tons (deep)<br />
Armament: Six 4in (3x2), One 2-pounder<br />
quadruple pom pom, two 20mm and 50<br />
depth charges with one rail and two<br />
throwers.<br />
Max Speed: 25 knots (deep load) with<br />
19,000sHP<br />
Endurance: 2560 miles at 20 knots<br />
Complement: Nine officers, 155 ratings<br />
Ttre revised gxoup weights were:<br />
Hull:<br />
595 tons<br />
Machinery: 295 tons<br />
Armament: 136 tons<br />
Equipment: 111tons<br />
Oil Fuel:<br />
277 tons<br />
RFW:<br />
16 tons<br />
Deep displacement: 1430 tons<br />
The Type 3 Vessels<br />
By the spring of 1940, it had become clear<br />
that the Hunts would be undertaking<br />
fleet duties and would require a torpedo<br />
armamerit, albeit at the expense of<br />
suppressing part of the gun armament.<br />
This proposal was, in effect, a revival of<br />
the idea to arm the second batch of ten<br />
vessels of the 1939 Programme with<br />
torpedoes.<br />
At a meeting held on 26 March l.940the<br />
following parameters of the design were<br />
accepted:<br />
The ships were to have a beam of<br />
3lL/2 feet and it was hoped that a<br />
speed of 27 knots in deep condition<br />
could be achieved.<br />
The quarter deck 4in mounting<br />
was suppressed.<br />
It.was hoped to ship 100 depth<br />
charges, with four depth charge<br />
chutes'and four depth charge<br />
throwers being provided, butitwas<br />
accepted that two throwers only<br />
might have to be tolerated.<br />
Better protection ofthe bridge and<br />
wheelhouse, as well as depth<br />
charge personnel was to be<br />
provided.<br />
TWo designs were produced in April 1940:<br />
A: Four 4in guns, one set of twin tubes on<br />
2t9