Connecting Europe Facility<br />
ENERGY<br />
Member States involved:<br />
Bulgaria<br />
Implementation schedule<br />
Start date: January 2015<br />
End date: April 2018<br />
Studies and pre-investment works for the<br />
project Internal line between<br />
Dobrudja and Burgas<br />
3.8.1-0030-BG-S-M-14<br />
Part of Project of Common Interest 3.8.1<br />
Budget:<br />
Estimated total cost of the action:<br />
€630,000<br />
Maximum EU contribution:<br />
€315,000<br />
Percentage of EU support: 50%<br />
Beneficiary:<br />
Elektroenergien Sistemen Operator<br />
EAD<br />
www.tso.bg<br />
Additional information:<br />
European Commission<br />
http://ec.europa.eu/energy/infrastruct<br />
ure/index_en.htm<br />
Innovation and Networks Executive<br />
Agency (INEA)<br />
http://inea.ec.europa.eu<br />
Agency for the Cooperation of <strong>Energy</strong><br />
Regulators (ACER)<br />
www.acer.europa.eu<br />
European Network of Transmission<br />
System Operators for Electricity<br />
(ENTSO-E)<br />
www.entsoe.eu<br />
The Action is a part of the Project of Common Interest (PCI) 3.8.1 which<br />
involves the construction of a new, AC 400 kV single-circuit interconnector<br />
with a length of approximately 110 km and a capacity of 1500 MW between<br />
the Dobrudja and Burgas substations in Bulgaria.<br />
The aim of this specific Action is to prepare a comprehensive package<br />
necessary for a final investment decision. This includes the preparation of a<br />
final detailed development plan, approval of all the necessary permits for<br />
the implementation of the investment project, preparation of a detailed<br />
design and the tender documentation for the selection of a contractor to<br />
carry out the construction.<br />
The Action is ongoing.<br />