Connecting Europe Facility<br />
ENERGY<br />
Member States involved:<br />
Czech Republic<br />
Implementation schedule<br />
Start date: July 2015<br />
End date: September 2016<br />
Final project documentation for substation<br />
Vítkov<br />
3.11.1-0007-CZ-S-M-15<br />
Part of Project of Common Interest 3.11.1<br />
Budget:<br />
Estimated total cost of the action:<br />
€572,000<br />
Maximum EU contribution:<br />
€286,000<br />
Percentage of EU support: 50%<br />
Beneficiary:<br />
ČEPS, a.s.<br />
www.ceps.cz<br />
Affiliated entity(ies):<br />
ČEPS Invest, a.s.<br />
Additional information:<br />
European Commission<br />
http://ec.europa.eu/energy/infrastructu<br />
re/index_en.htm<br />
Innovation and Networks Executive<br />
Agency (INEA)<br />
http://inea.ec.europa.eu<br />
Agency for the Cooperation of <strong>Energy</strong><br />
Regulators (ACER)<br />
www.acer.europa.eu<br />
European Network of Transmission<br />
System Operators for Electricity<br />
(ENTSO-E)<br />
www.entsoe.eu<br />
The Action is a part of the 3.11.1 PCI Internal line between Vernéřov and<br />
Vítkov (Czech Republic), which concerns the construction of a 400 kV AC<br />
double circuit overhead line of approximately 75 km and with a capacity of<br />
2x1730 MVA. For the purpose of the line the new 400 kV substation Vítkov<br />
will be constructed using a special Gas-Insulated Substation (GIS)<br />
technology.<br />
The Action aims to complete the preparatory work for the construction of<br />
the substation Vítkov and consists of the preparation and approval of the<br />
final project documentation, including the tendering documentation, as well<br />
as of the tendering procedure of the GIS based technology substation.<br />
The Action is ongoing.<br />
33