Connecting Europe Facility<br />

ENERGY<br />

Member States involved:<br />

Czech Republic<br />

Implementation schedule<br />

Start date: August 2014<br />

End date: May 2016<br />

ay<br />

Budget:<br />

Estimated total cost of the action:<br />

€2,026,048<br />

Documentation for zoning permit of the line<br />

400 kV Vernerov-Vitkov, substation 400 kV<br />

Vitkov and Project study for substation 400<br />

kV Vernerov<br />

3.11.1-0036-CZ-S-M-14<br />

Part of Project of Common Interest 3.11.1<br />

Maximum EU contribution:<br />

€1,013,024<br />

Percentage of EU support: 50%<br />

Beneficiary:<br />

ČEPS, a.s.<br />

www.ceps.cz<br />

Affiliated entity(ies):<br />

ČEPS Invest, a.s.<br />

Additional information:<br />

European Commission<br />

http://ec.europa.eu/energy/infrastructu<br />

re/index_en.htm<br />

Innovation and Networks Executive<br />

Agency (INEA)<br />

http://inea.ec.europa.eu<br />

Agency for the Cooperation of <strong>Energy</strong><br />

Regulators (ACER)<br />

www.acer.europa.eu<br />

European Network of Transmission<br />

System Operators for Electricity<br />

(ENTSO-E)<br />

https://www.entsoe.eu<br />

The Action is a part of the 3.11.1 PCI Internal line between Vernerov<br />

and Vitkov (CZ), which is a 400 kV AC double circuit overhead<br />

line of approximately 75 km and with a capacity of 2x1730 MVA.<br />

The Action consists of the preparation and approval of the<br />

documentation for the zoning permit for the construction of the 400 kV<br />

AC double circuit overhead transmission line between Vernerov and Vítkov<br />

(onshore) and the documentation for the zoning and building permi ts for<br />

the construction of the 400 kV substation Vitkov. The documents to be<br />

prepared are obligatory under the Building Act of the Czech Republic<br />

(No. 183/2006 Coll.). The zoning and building permit is among the<br />

grant permits which need to be ensured and obtained before the<br />

construction of the PCI starts.<br />

The Action will be completed with the submission of the application for<br />

the zoning and building permit to the competent authorities.<br />

The Action is ongoing.<br />