ENKA TEKNİK<br />

Genel Müteahhitlik Bakım İşletme Sevk ve İdare A.Ş.<br />

assured by employee implementation of health and<br />

safety precautions.<br />

Established in 1981, ENKA Teknik has become a partner<br />

of preference for turnkey projects involving plant<br />

engineering, fabrication, procurement, construction<br />

and assembly works and the commissioning and<br />

operation of industrial projects. It regularly completes<br />

all tasks to the full satisfaction of its clients. Its project<br />

management system software, developed entirely<br />

in-house, ensures the security and traceability of<br />

documents, information and data, and is the main tool<br />

used for rapid and accurate decision-making in the<br />

projects which ENKA Teknik undertakes.<br />

ENKA Teknik serves clients in Turkey, North Africa, the<br />

Middle East and Central Asia, either as main contractor<br />

or as a consortium partner, in its main areas of business<br />

– namely: energy plants, oil and gas systems, water<br />

treatment plants and environmental systems, cement<br />

plants, materials handling, processing and storage<br />

systems, balance of plant (BoP), and electrical and<br />

control systems.<br />

The primary objective of ENKA Teknik is, and has always<br />

been, customer satisfaction. This is achieved through<br />

effective implementation of the ISO 9001 Quality<br />

Management System, and through the “Zero Accident”<br />

target which has been set by the management and is<br />

ENKA Teknik makes its services available through its<br />

head office in Istanbul, its offices in Libya (Tripoli) and<br />

Iraq (Basra), and its offices at project sites. The head<br />

office continued its business development activities<br />

in 2016 by tracking projects in the company’s areas of<br />

business and preparing various proposals, which are<br />

currently under evaluation by customers.<br />

The Awbari 4x160 MW Gas Turbine Power Plant Project<br />

has been carried out under a contract worth 378 million<br />

EUR which was signed prior to the Libyan uprising<br />

of 2011. The signatories were the General Electricity<br />

Company of Libya (GECOL) on the one hand and a<br />

consortium of GESCO (a GECOL subsidiary that provides<br />

GTG equipment) and ENKA Teknik on the other.<br />

ENKA Teknik’s share in the consortium was valued at 170<br />

million EUR. Work on the site had to be suspended in 2011<br />

and 2014, at the stages of start-up and commissioning<br />

respectively, due to political and civil unrest. Since the<br />

end of 2014, the remaining engineering works have<br />

been performed and the remaining supplies have been<br />

provided. ENKA Teknik has held a series of high-level<br />

meetings with GECOL and the Government of Libya<br />

in order to establish a road map for the resolution<br />

of outstanding issues. A protocol addressing ENKA<br />

Teknik’s concerns about the project was signed on 30<br />

October 2016.<br />

A STRONG PARTNER FOR ENGINEERED<br />

SOLUTIONS<br />

The primary objective of ENKA Teknik is, and has always been to meet customer satisfaction<br />

achieved by effective implementation of the ISO 9001 Quality Management System.<br />

70 | ENKA Annual Report 2016<br />

1981<br />

35 YEARS OF EXPERIENCE<br />

2016<br />

ENKA Annual Report 2016 | 71