170 Sample issue The Journal of Pipeline Engineering Fig.2. General layout of the Nord Stream pipeline’s German landfall.
3rd Quarter, 2009 171 barrier of ships, known as ‘Schiffssperre’, is a designated historic monument. One of the shipwrecks, identified simply as No 67, has recently been successfully recovered from the sea bed and placed in wet storage to allow access for the laybarge and dredging vessels. The unusual S-shape of the route within the Greifswalder Bodden has been designed so that the pipelines can be installed within a defined planning corridor designated as a marine priority area within the planning policy of the regional development of Mecklenburg-Western Pomerania. The environmental and ecological restrictions within the protected areas have essentially determined the construction schedule and have had such a significant and direct effect on the project’s technical aspects that numerous installation methods have had to be designed, proposed, modified, and ultimately accepted to minimize the environmental impact and maintain the construction operations within the available time period. Onshore, several environmental-mitigation measures will have to be undertaken prior to the start of construction at Lubmin. These include the construction of habitats for lizards, amphibian pathways, solid partition fencing/ screening, and transplantation of small trees and bushes. Additional permit restrictions, including dredging and cofferdam installations, are not allowed to commence before 15 May, 2010, due to the herring-spawning season in the Greifswalder Bodden, and all offshore construction work must be completed in one construction season, i.e. by 31 December, 2010, within the FFH areas in the area of the German landfall. Noise-restriction guidelines have been set, at the nearest residential towns adjacent to the pipeline route, where the levels shall not exceed 50dB(A) during the daytime and 35dB(A) at night-time; additionally noise levels at the adjacent marina shall be monitored and shall not exceed 65dB(A) during the daytime and 50dB(A) during nighttime. Geological formation The offshore area crossed by the Nord Stream pipeline within the German sector can be divided into four different geological sectors: the Greifswalder Bodden, the Boddenrandschwelle, the Oder subsea valley, and the Oder Bank. Each area was formed by the glacial processes in the last ice age and the subsequent marine progression of the Baltic Sea and can generally be distinguished by their different water depths. The Greifswalder Bodden is almost a land-enclosed basin with a water depth up to 10m. The seabed of this basin is characterized by the variation of a large number of soil types, such as sand and gravel, peat, clay, or alluvial mud, which is typical for lagoon-like areas. At its eastern edge the basin is restricted towards the Baltic Sea by a submarine barrier with water depth of less than 5m. This barrier is called the Boddenrandschwelle, and is formed of glacial till (a cohesive mixture of clay, sand, and gravel) with loose residual sediments (sand, gravel, cobbles) generally at the uppermost (surface) layers. The Oder valley formation, an ancient course of the river Oder during the end of the last ice age, runs parallel to the Boddenrandschwelle. The water depth in this subsea valley ranges to 20m and above. The sea bottom is composed of coarse-grained fluvial sediments which have been covered by recent alluvial mud deposits. The major part of the pipeline route within the German sector crosses the Pomeranian Bay east of the Oder valley along the northern foothill of the Oder Bank. The sea bottom is characterized by marine sediments (largely sand), with water depths varying from 15m to more than 20m. German landfall At the German landfall the Nord Stream pipeline is divided into three separate sections: the offshore section, the ‘pullin’ section, and the dry section. The German landfall offshore section commences approximately 1km seaward of the highly-protected Greifswalder Boddenrandschwelle and Parts of the Pomeranian Bight (DE 1749-302) FFH-area, and extends in a south-westerly direction for 26km to approximately 1,100m from the shoreline at Lubmin. The pull-in section then commences and ends approximately 220m landward of the shoreline. The remaining 300m consists of the dry section up to the pig receivers. Sample issue Dry section The dry section generally comprises an ‘Omega’-shaped spool arrangement and a combination of valves (emergency shutdown and gate) together with isolation joints and pig receivers. The 48-in pipework is connected to the Greifswald receiving terminal (GRT) by way of twin 38-in diameter pipelines and supplementary 16-in by-pass lines. The dry section works were originally designed with a ‘dogleg’ arrangement; however, subsequent to a periodic environmental survey, it was discovered that the Grey Dune vegetation had migrated onto the pipeline route, thereby necessitating a realignment of the pipeline route and a redesign of the onshore pipework The dry-section pipework and permanent-work items will be supported by over 100 reinforced concrete bases of varying sizes.
- Page 1 and 2: September, 2009 Vol.8, No.3 Scienti
- Page 3 and 4: 3rd Quarter, 2009 145 The Journal o
- Page 5 and 6: 3rd Quarter, 2009 147 Editorial Pip
- Page 7 and 8: 3rd Quarter, 2009 149 Approaches fo
- Page 9 and 10: 3rd Quarter, 2009 151 L r s y is th
- Page 11 and 12: 3rd Quarter, 2009 153 Fig.4. Ideali
- Page 13 and 14: 3rd Quarter, 2009 155 Approach adop
- Page 15 and 16: 3rd Quarter, 2009 157 The above res
- Page 17 and 18: 3rd Quarter, 2009 159 Comments on g
- Page 19 and 20: 3rd Quarter, 2009 161 J e based on
- Page 21 and 22: 3rd Quarter, 2009 163 Basis of σ f
- Page 23 and 24: 3rd Quarter, 2009 165 be used to as
- Page 25 and 26: 3rd Quarter, 2009 167 The Nord Stre
- Page 27: 3rd Quarter, 2009 169 Table 1. Pipe
- Page 31 and 32: 3rd Quarter, 2009 173 Fig.3. Typica
- Page 33 and 34: 3rd Quarter, 2009 175 Assessing pip
- Page 35 and 36: 3rd Quarter, 2009 177 Fig.2. Failed
- Page 37 and 38: 3rd Quarter, 2009 179 Fig.5. EPRI-J
- Page 39 and 40: 3rd Quarter, 2009 181 Fig.7. Plasti
- Page 41 and 42: 3rd Quarter, 2009 183 Behaviour of
- Page 43 and 44: 3rd Quarter, 2009 185 Table 1. Test
- Page 45 and 46: 3rd Quarter, 2009 187 Fig.5. Strain
- Page 47 and 48: 3rd Quarter, 2009 189 2000. Laborat
- Page 49 and 50: 3rd Quarter, 2009 191 Advanced nume
- Page 51 and 52: 3rd Quarter, 2009 193 Fig.4. A hypo
- Page 53 and 54: 3rd Quarter, 2009 195 A disc pig mo
- Page 55 and 56: 3rd Quarter, 2009 197 Fig.4. Plot o
- Page 57 and 58: 3rd Quarter, 2009 199 Table 4. Leng
- Page 59 and 60: 3rd Quarter, 2009 201 characteristi
- Page 61 and 62: 3rd Quarter, 2009 203 Appendix (con
- Page 63 and 64: 3rd Quarter, 2009 205 Soil reaction
- Page 65 and 66: 3rd Quarter, 2009 207 Fig.3. Pipeli
- Page 67 and 68: 3rd Quarter, 2009 209 Fig.8. Simula
- Page 69 and 70: 3rd Quarter, 2009 211 A second set
- Page 71 and 72: 3rd Quarter, 2009 213 Full range st
- Page 73 and 74: 3rd Quarter, 2009 215 Secondly, if
- Page 75 and 76: 3rd Quarter, 2009 217 Fig.4d-f (top
- Page 77 and 78: 3rd Quarter, 2009 219 n, n 1, n 2 (
- Page 79 and 80:
3rd Quarter, 2009 221 ‘double-n
- Page 81 and 82:
3rd Quarter, 2009 223 Correction A
- Page 83 and 84:
Sample issue