Numbering of tertiary packaging<br />

All boxes should be numbered consecutively. Shipping documents should be included in the<br />

box labeled number 1, and this box should be clearly labeled with the words “Contains<br />

shipping documents.”<br />

<strong>The</strong> shipment must be packed in such a way that its contents withstand shipping conditions<br />

without breakage or damage. Outer shipping cartons must be sturdy enough <strong>for</strong> export.<br />

C. Schedule <strong>for</strong> construction<br />

Task Time frame<br />

Prepare<br />

2 days<br />

(transportation of components and materials to site)<br />

Build foundation, construct ash and needle pits<br />

21 days<br />

(includes inspection and quality control)<br />

Install incinerator<br />

10 days<br />

(includes inspection and quality control)<br />

Complete wall, roof, and enclosure structure<br />

12 days<br />

(includes inspection and quality control)<br />

Finish installation details<br />

13 days<br />

(operator work zone, fence, door, storage facilities; includes inspection and<br />

quality control)<br />

Total days 58 days<br />

D. Training<br />

Upon installation of the incinerator, the company chosen should also be able to provide the<br />

following:<br />

� Introductory training <strong>for</strong> all new incinerator operators.<br />

� Retraining of operators after approximately one year of operational experience.<br />

� Follow-on training or retraining as considered necessary to ensure best practices <strong>for</strong><br />

operation of the incinerator.<br />

E. Maintenance<br />

<strong>The</strong> company chosen should be able to provide to ensure the following:<br />

� Maintenance (under a separate agreement) when necessary as considered by the<br />

purchaser. Note: purchaser can create a separate agreement with a schedule <strong>for</strong><br />

maintenance and supervisory visits.<br />

� Replacement parts.<br />

� Unscheduled maintenance if un<strong>for</strong>eseen defects of the incinerator occur.<br />

F. Manufacturer support<br />

<strong>The</strong> manufacturer must provide the following:<br />

� Warranties and guarantees <strong>for</strong> the expected life of the system.<br />

� <strong>The</strong> terms and conditions <strong>for</strong> technical support.<br />

� Training curriculum <strong>for</strong> installation, operation, and routine service.<br />

� A proposal <strong>for</strong> maintenance and repair support <strong>for</strong> the life of the product (5 years if an<br />

auto-combustion type or 10 years if a fuel-assisted type).<br />

� List of references.<br />

� Service and operators manuals. Manuals must be provided in the local language and<br />

must be simple and explicit.<br />

35