ASPHALTopcs | Summer 2017 | VOL 30 | NO 2
Create successful ePaper yourself
Turn your PDF publications into a flip-book with our unique Google optimized e-Paper software.
One of the four MTVs and two of the six pavers<br />
working on the surface course on the south side<br />
of the centreline of Runway 05-23. (Pave-Al)<br />
scheduled for October <strong>2017</strong> and later<br />
in 2018, were included in the spring<br />
phases, which further complicated<br />
logistics planning.<br />
“The approach to the project<br />
schedule initially was very<br />
conservative, as we were uncertain<br />
about the weather,” says Chris<br />
Stewart, Manager, Airside and<br />
Infrastructure Engineering, GTAA.<br />
“We had never started a major<br />
pavement restoration project so<br />
early in the year; typically we don’t<br />
start projects until mid-April. When<br />
combined with a milder than average<br />
spring, the concerted efforts of all<br />
parties paid off to allow us to advance<br />
the schedule for phase three and four<br />
and complete the work on May 16.<br />
This project was very important to<br />
make sure that the busiest runway<br />
in Canada could safely and reliably<br />
operate into the future. Although it<br />
resulted in some unfortunate delays<br />
to our customers and noise impact<br />
to our community, it was good to<br />
12 OAPC | ASPHALTOPICS<br />
see that we were able to significantly<br />
mitigate the timespan of those delays<br />
and relieve the noise impact through<br />
our efforts to complete the project<br />
more quickly than originally planned.”<br />
That’s the beauty<br />
of asphalt; you can<br />
pave today and be<br />
open tomorrow.<br />
– Carinci<br />
Efficient workmanship by experienced<br />
heavy civil contractors was also key<br />
in ensuring that the project was<br />
completed on time. The 05-23 runway<br />
and related taxiways were constructed<br />
by Pave-Al Limited and Gazzola Paving<br />
Ltd., who have partnered in the past<br />
with other Toronto Pearson runway<br />
projects. The companies’ combined<br />
manpower, equipment and paving<br />
materials, as well as the expertise<br />
and work ethic of subtrades, provided<br />
the robust workforce that was needed<br />
to tackle such a large and time-sensitive<br />
project.<br />
“Both Pave-Al and Gazzola Paving<br />
each have a plant close to the airport,<br />
with a daily capacity of 4,000 tonnes<br />
of asphalt for each company,” says<br />
Albert Carinci, Contract Manager for<br />
Pave-Al Limited. “Combined, we can<br />
reduce the down time significantly<br />
and can do in two days what would<br />
normally take a week.”<br />
While the rehabilitation project was<br />
designed in-house, the GTAA hired<br />
engineering firm, Englobe, for on-site<br />
quality control of the project and<br />
to test the integrity of the existing<br />
runway. Heavy Weight Deflectometer<br />
(HWD) testing assessed the efficiency<br />
of load transfer in the concrete joints,<br />
and through Ground Penetrating<br />
Radar (GPR), lower density material or<br />
voids were located. After establishing<br />
the location of voids and weak load