10.09.2020 Views

ASPHALTopcs | Summer 2017 | VOL 30 | NO 2

Create successful ePaper yourself

Turn your PDF publications into a flip-book with our unique Google optimized e-Paper software.

One of the four MTVs and two of the six pavers<br />

working on the surface course on the south side<br />

of the centreline of Runway 05-23. (Pave-Al)<br />

scheduled for October <strong>2017</strong> and later<br />

in 2018, were included in the spring<br />

phases, which further complicated<br />

logistics planning.<br />

“The approach to the project<br />

schedule initially was very<br />

conservative, as we were uncertain<br />

about the weather,” says Chris<br />

Stewart, Manager, Airside and<br />

Infrastructure Engineering, GTAA.<br />

“We had never started a major<br />

pavement restoration project so<br />

early in the year; typically we don’t<br />

start projects until mid-April. When<br />

combined with a milder than average<br />

spring, the concerted efforts of all<br />

parties paid off to allow us to advance<br />

the schedule for phase three and four<br />

and complete the work on May 16.<br />

This project was very important to<br />

make sure that the busiest runway<br />

in Canada could safely and reliably<br />

operate into the future. Although it<br />

resulted in some unfortunate delays<br />

to our customers and noise impact<br />

to our community, it was good to<br />

12 OAPC | ASPHALTOPICS<br />

see that we were able to significantly<br />

mitigate the timespan of those delays<br />

and relieve the noise impact through<br />

our efforts to complete the project<br />

more quickly than originally planned.”<br />

That’s the beauty<br />

of asphalt; you can<br />

pave today and be<br />

open tomorrow.<br />

– Carinci<br />

Efficient workmanship by experienced<br />

heavy civil contractors was also key<br />

in ensuring that the project was<br />

completed on time. The 05-23 runway<br />

and related taxiways were constructed<br />

by Pave-Al Limited and Gazzola Paving<br />

Ltd., who have partnered in the past<br />

with other Toronto Pearson runway<br />

projects. The companies’ combined<br />

manpower, equipment and paving<br />

materials, as well as the expertise<br />

and work ethic of subtrades, provided<br />

the robust workforce that was needed<br />

to tackle such a large and time-sensitive<br />

project.<br />

“Both Pave-Al and Gazzola Paving<br />

each have a plant close to the airport,<br />

with a daily capacity of 4,000 tonnes<br />

of asphalt for each company,” says<br />

Albert Carinci, Contract Manager for<br />

Pave-Al Limited. “Combined, we can<br />

reduce the down time significantly<br />

and can do in two days what would<br />

normally take a week.”<br />

While the rehabilitation project was<br />

designed in-house, the GTAA hired<br />

engineering firm, Englobe, for on-site<br />

quality control of the project and<br />

to test the integrity of the existing<br />

runway. Heavy Weight Deflectometer<br />

(HWD) testing assessed the efficiency<br />

of load transfer in the concrete joints,<br />

and through Ground Penetrating<br />

Radar (GPR), lower density material or<br />

voids were located. After establishing<br />

the location of voids and weak load

Hooray! Your file is uploaded and ready to be published.

Saved successfully!

Ooh no, something went wrong!