10.09.2020 Views

ASPHALTopcs | Summer 2017 | VOL 30 | NO 2

You also want an ePaper? Increase the reach of your titles

YUMPU automatically turns print PDFs into web optimized ePapers that Google loves.

transfer areas in the composite<br />

pavement structure, the solution<br />

to the voids was to drill 11,000 holes<br />

to inject grout under pressure below<br />

the concrete. In addition, 6,600 steel<br />

dowel bars were installed to help<br />

transfer the load between the<br />

concrete slabs.<br />

“The slots for the dowel bars<br />

required specialized machinery,<br />

so we contracted Randy Cole of<br />

Cole Concrete Cutting in Wyoming,”<br />

Carinci says. “This company has one<br />

of three machines in the U.S. that can<br />

do this work. It was critical that Cole’s<br />

equipment be used from April 1 to<br />

the 17. Equipment in Canada can<br />

only make <strong>30</strong>0 slots per day, whereas<br />

Cole’s machine made 900 and had<br />

a capacity of 1,200 slots per day.”<br />

Runway 05-23 runs east-west and<br />

is 3,<strong>30</strong>0 metres long by 61 metres<br />

wide. Once the concrete repair work<br />

was complete, 20,000 tonnes of<br />

PGAC 64-28 lower course asphalt<br />

was laid. The surface course asphalt<br />

required 50,000 tonnes of PGAC<br />

70-28 polymer-modified asphalt<br />

cement. Work was staggered for<br />

the rehabilitation of two interacting<br />

runways (15L-33R and 15R-33L), with<br />

three days devoted to each of those<br />

portions of the runway to minimize<br />

disruptions to the runways.<br />

Prior to the application of the surface<br />

course, some areas were padded to<br />

meet the specified longitudinal profile<br />

of the runway. The built-up crown<br />

of the runway has approximately<br />

200 mm of asphalt on top of the<br />

original concrete base, and the<br />

intersecting runways gradually<br />

slope to meet the crown of the<br />

primary 05-23 runway.<br />

“Most of the loads are on the centre<br />

23 metres of the runway, so we didn’t<br />

do a lot of work on the concrete<br />

outside of this area,” says Kevin<br />

Chee, Senior Civil Engineer for GTAA.<br />

“There is 200 mm of asphalt at the<br />

centre of the runway at 1,000 metres<br />

in length on the west end, because<br />

testing showed the greatest number<br />

of voids in this location. There is<br />

hardly any load at the edges of the<br />

runway, so these sections only had<br />

a 65 mm asphalt overlay.”<br />

Excavation work ran day and night,<br />

while concrete pours and asphalt<br />

paving work occurred during the<br />

day. Echelon paving of the runway<br />

surface course took place in just 10<br />

days, with one steady 60 mm thickness<br />

for the surface pavement. Each of six<br />

pavers paved five metre swaths for the<br />

centre <strong>30</strong> metres of the runway. The<br />

base asphalt was carried out by four<br />

paving crews, while the surface asphalt<br />

required six paving crews, four shuttle<br />

buggies, 40 trucks and two asphalt<br />

plants producing a total of 8,000<br />

tonnes of asphalt per day.<br />

“It was important not to have any cold<br />

joints at the wheel path of aircraft, so<br />

the job required echelon paving with<br />

six pavers for the centre <strong>30</strong> metres ››<br />

SUMMER <strong>2017</strong> 13

Hooray! Your file is uploaded and ready to be published.

Saved successfully!

Ooh no, something went wrong!