21.06.2021 Views

CEAC-2021-07-July

You also want an ePaper? Increase the reach of your titles

YUMPU automatically turns print PDFs into web optimized ePapers that Google loves.

Georgia Nuclear Plant Now Delayed<br />

Until 2022 as Costs Mount By Jeff Amy | Associated Press<br />

ATLANTA (AP) — Georgia Power Co. has announced that<br />

delays in completing testing means the first new unit at its<br />

Vogtle plant is now unlikely to start generating electricity<br />

before January at the earliest.<br />

The unit of Atlanta-based Southern Co. had in recent years<br />

been aiming to complete the first unit in November, but<br />

officials recently told investors that it would probably be<br />

finished in December. Company officials have said that testing<br />

began in late April, would take three weeks longer than<br />

expected, and is unlikely to be completed before late June,<br />

adding more time to construction and startup.<br />

The additional month will add another $48 million to the<br />

cost of the two nuclear units being built alongside two existing<br />

units near Augusta. The project is now projected to cost<br />

more than $26 billion for all its owners, including Georgia<br />

Power, electric cooperatives and municipal utilities. Ultimately,<br />

most electric customers in Georgia, except those in<br />

the northwest corner of the state served by affiliates of the<br />

Tennessee Valley Authority, will have to pay for the plant.<br />

Florida’s Jacksonville Electric Authority is also obligated to<br />

buy power from Vogtle.<br />

The further delay was disclosed in a periodic hearing with<br />

the Georgia Public Service Commission to discuss spending<br />

and construction progress on the only nuclear plant being<br />

built in the U.S. Commissioners must ultimately decide how<br />

much of Georgia Power’s share of the spending is allowable<br />

and how paying the bill will be phased in for 2.6 million<br />

ratepayers.<br />

Customers are already paying for part of the plant. Rates<br />

have gone up 3.4 percent to pay for earlier costs and Georgia<br />

Power projects rates will rise another 6.6 percentage points<br />

for a total increase of 10 percent.<br />

The reactors, approved in 2012, were initially estimated to<br />

cost a total of $14 billion, with the first new reactor originally<br />

planned to start generation in 2016. Delays and costs<br />

spiraled, especially after the main contractor filed for bankruptcy<br />

in 2017. The company and regulators insist that the<br />

plant is the best source of future clean and reliable energy<br />

for Georgia.<br />

The first new reactor is 98 percent complete, but Southern<br />

Nuclear Vice President Aaron Abramovitz said risk of delays<br />

and problems doesn’t go away.<br />

“I would expect risk to decrease,” he told regulators. “I<br />

would not expect risk to go to zero.”<br />

U.S. Secretary of Energy Rick Perry speaks during a press event at the construction<br />

site of Vogtle Units 3 and 4 at the Alvin W. Vogtle Electric Generating<br />

Plant, in Waynesboro, Ga. Georgia Power Co. recently told regulators<br />

that the first new reactor at the power plant isn’t expected to be complete<br />

until January 2022 at the earliest because of delays in testing. (Hyosub Shin/<br />

Atlanta Journal-Constitution via AP, File)<br />

Georgia Power has agreed to write off about the first $700<br />

million over the $7.3 billion that the Public Service Commission<br />

has approved. The company currently projects $8.7<br />

billion in spending, though, plus borrowing costs ratepayers<br />

will also have to repay. The company could seek repayment<br />

of some of the amount over $7.3 billion.<br />

“Exceeding the $7.3 billion, that does not mean the costs are<br />

unrecoverable, it just means the standard of proof there has<br />

changed, it has gotten higher,” said Georgia Power’s Jeremiah<br />

Haswell.<br />

The company says that workers being out with COVID-19 has<br />

caused delays in recent months, as well as having to redo<br />

electrical and other work that the company decided wasn’t<br />

up to standard. Georgia Power said there’s some evidence<br />

that contractors were declaring work complete without testing<br />

for deficiencies, relying on inspectors to catch it and fix<br />

any problems later. The company is currently engaged in hot<br />

functional testing of the first reactor and has encountered<br />

more expansion of metal parts as systems were more heated<br />

up than anticipated.<br />

“There’s a chance we may need to make some adjustments<br />

to the structural supports,” Stephen Kuczynski, president<br />

and CEO of Southern Nuclear, said of the thermal expansion<br />

issues.<br />

The second new reactor is supposed to start operating in<br />

November 2022. The company says it is still on schedule.<br />

Volume 86 · Number 7 | 17

Hooray! Your file is uploaded and ready to be published.

Saved successfully!

Ooh no, something went wrong!