PLEASE REFER TO: Barton Soroka<br />
Email: bsoroka@grj.ca<br />
July 16, 2021<br />
Without Prejudice<br />
Attention: Ryan Nagel<br />
Dear Sir:<br />
Re: Q.B.G. 1157 of 2019<br />
Our File #15294.001 BPS<br />
Your client has requested that the <strong>RM</strong> consent to the continued removal of aggregate from his land<br />
in order to continue with remediation, per the Skynorth Gravel Pit Reclamation Plan. Prior to<br />
providing authorization, the <strong>RM</strong> requires additional information from your client.<br />
Costs<br />
The <strong>RM</strong> has incurred significant legal costs over the multi-year struggle to have your client comply<br />
with the Orders that have been made. The <strong>RM</strong> is requesting that your client agree to pay <strong>$32</strong>,306<br />
to the <strong>RM</strong> as compensation for the costs incurred in enforcing the Orders.<br />
Inclinometers<br />
Your client has been clear from the beginning that the work he is doing is to prevent<br />
sloping/slumping and/or danger related to the incline(s) on the land. As such, the <strong>RM</strong> is requesting<br />
that the reclamation plan include the installation of inclinometers to continue to monitor this area<br />
of concern. An engineered inclinometer design will be forwarded to the <strong>RM</strong> for approval. The<br />
design will include a recommended schedule for testing. Test results will be immediately shared<br />
with the <strong>RM</strong> as well as potential land purchasers.<br />
Contact Information<br />
Phone 306 790 3190<br />
Email bsoroka@grj.ca<br />
Address 1914 Hamilton Street #700 Regina SK S4P 3N6
2<br />
Detailed Plan<br />
Please confirm the specific area proposed for remediation. The March 2021 ‘Skynorth 2020<br />
Gravel Pit Reclamation Plan’ does not clearly specify the area intended for remediation.<br />
The <strong>RM</strong> is requesting that your client provide a timeline of extraction. This timeline can be based<br />
on a start date of August 15 th , 2021 for reference. The <strong>RM</strong> further requests information on who<br />
will be completing the extraction and what will be done with the extracted aggregate. The <strong>RM</strong><br />
prefers that the extraction be done by a 3 rd party to ensure the safety of the land in the future.<br />
Road Maintenance Agreement<br />
Your client will be required to enter into a Road Maintenance Agreement with the <strong>RM</strong> prior to<br />
removing extracted gravel.<br />
Conclusion<br />
We look forward to your response to the above noted concerns.<br />
GERRAND RATH JOHNSON LLP<br />
Per:<br />
BS<br />
CC:<br />
Barton Soroka