28 November 2008<br />

Resource Consents Hearings Panel<br />

Minutes<br />

1489/11/08 APOLOGIES<br />

AGENDA ITEM NO. 1<br />

There were no apologies.<br />

1490/11/08 A NOTIFIED <strong>RESOURCE</strong> CONSENT APPLICATION UNDER SECTION<br />

88 OF THE <strong>RESOURCE</strong> MANAGEMENT ACT 1991<br />

AN APPLICATION FOR CONSENT TO CONSTRUCT AND OPERATE A<br />

NEW COMMERCIAL COMPLEX WITH ASSOCIATED PARKING<br />

SPACES, ONSITE DISPOSAL AND LANDSCAPING AT 1A TAPU<br />

ROAD, HUAPAI<br />

FILE REF L54342<br />

WARD Western<br />

AGENDA ITEM NO. 2<br />

FURTHER, THE APPLICANT REQUESTS THAT THE CONSENT BE<br />

GRANTED FOR A TEN YEAR PERIOD<br />

Address: 1A Tapu Road, Huapai<br />

APPLICANTS: REM DEVELOPMENTS LIMITED<br />

9.00 a.m. The applicant seeks consent to develop the site at 1A Tapu Road, Huapai to establish and<br />

operate commercial buildings on the property. The applicant proposes to undertake the work in two<br />

stages. The first stage involves the construction and use of a two storey commercial building in the<br />

south-western corner of the site adjacent to both Tapu Road and State Highway 16. This building will<br />

contain three shops, a GJ Gardner office and a café. Due to the inability to connect to the public<br />

wastewater system the development has been designed to dispose of all stormwater and wastewater<br />

on site for Stage 1. The second stage will entail construction and use of a second building located<br />

towards the eastern side of the site adjacent to State Highway 16. The two storey building will contain<br />

some 315m 2 of ground floor area at each level. It is proposed that Stage 2 will commence once a<br />

public wastewater system is available and Stage 1 has been connected to it.<br />

The applicant, Mr Ross Morley (REM Developments Ltd), and the applicant’s representatives, Mr<br />

Graham Parfitt (Planning Consultant), Mr Peter Eising (Architect - Pacific Environments) and his<br />

assistant Lutz Kreissler (Architect/Designer), Ms Sally Peake (Landscape Architect), Mr Joshua<br />

Hyland (Traffic Engineer), Ms Sarah Jones (Landscape Designer), Mr Duncan Elliott (Civil and<br />

Structural Engineer), and Mr Paul Riethmaier (Engineer and proprietor of Reflection Treatment<br />

Systems), present.<br />

None of the submitters attended the hearing.<br />

9.03 a.m. The Chairperson opened the hearing and outlined the meeting procedure.<br />

Mr Maddren of Maddren Property Limited had contacted a Resource Consent Administrator the<br />

previous day to request that his submission be considered by the Panel. He advised that he would not<br />

be attending the hearing, but that he had read the planner’s report and he considered the planner had<br />

covered his original concerns.