STAKEHOLDER ANALYSIS<br />
3.5. Outl<strong>in</strong>e assumptions and risks<br />
We can still go one step further <strong>in</strong> the analysis if we determ<strong>in</strong>e the potential<br />
risks <strong>in</strong>volved if key stakeholders’ expectations were not met.<br />
To cont<strong>in</strong>ue with this stage of the analysis, the work team must go back to<br />
Table 4 and add a new concept under the head<strong>in</strong>g ‘Assumptions and Risks’.<br />
This new concept is <strong>in</strong>cluded <strong>in</strong> the follow<strong>in</strong>g Table, which shows only the<br />
aspects or measures that backers of the project must take on board <strong>in</strong> order to<br />
m<strong>in</strong>imize any possible risks caused by dissatisfied stakeholders. As the project<br />
has still not reached the implementation stage, it would be speculative to<br />
venture what these risks might be, as stakeholders’ <strong>in</strong>itial reactions are<br />
unknown. As a result, this section rema<strong>in</strong>s unf<strong>in</strong>ished, <strong>for</strong> the time be<strong>in</strong>g at<br />
least.<br />
Table 5. Classification of importance-<strong>in</strong>fluence with assumption of risk to<br />
the Gulf of Cadix Offshore W<strong>in</strong>d Farm Project.<br />
KEY<br />
STAKEHOLDER<br />
Barbate<br />
Fishermen’s<br />
Guild<br />
Conil<br />
Fishermen’s<br />
Guild<br />
Barbate Tuna<br />
Fishers<br />
Conil Tuna<br />
Fishers<br />
Zahara de los<br />
Atunes Tuna<br />
Fishers<br />
OPP- 51 Tuna<br />
Products Org.<br />
Barbate<br />
Shipowners’<br />
Assoc.<br />
Conil<br />
Shipowners’<br />
Assoc.<br />
Barbate Town<br />
Council<br />
Conil Town<br />
Council<br />
Estimated<br />
Project<br />
Impact<br />
H<br />
H<br />
H<br />
H<br />
H<br />
H<br />
H<br />
H<br />
H<br />
Estimated<br />
priority<br />
Assumptions and risks<br />
1 Obta<strong>in</strong> impact studies that verify<br />
unfavourable impact of project on<br />
resources.<br />
1 Obta<strong>in</strong> impact studies that verify<br />
unfavourable impact of project on<br />
resources.<br />
1 Obta<strong>in</strong> impact studies that verify<br />
unfavourable impact of project on blue<br />
f<strong>in</strong> tuna migration routes.<br />
1 Obta<strong>in</strong> impact studies that verify<br />
unfavourable impact of project on blue<br />
f<strong>in</strong> tuna migration routes.<br />
H 1 Obta<strong>in</strong> impact studies that verify<br />
unfavourable impact of project on blue<br />
f<strong>in</strong> tuna migration routes.<br />
H Obta<strong>in</strong> impact studies that verify<br />
unfavourable impact of project on<br />
H<br />
H<br />
resources.<br />
1 Obta<strong>in</strong> impact studies that verify<br />
unfavourable impact of project on<br />
resources, shipp<strong>in</strong>g and safety.<br />
H 1 Obta<strong>in</strong> impact studies that verify<br />
unfavourable impact of project on<br />
resources, shipp<strong>in</strong>g and safety.<br />
M 2 Obta<strong>in</strong> impact studies that verify<br />
unfavourable impact of project on<br />
resources, shipp<strong>in</strong>g and safety and<br />
impact on landscape.<br />
M 2 Obta<strong>in</strong> impact studies that verify<br />
unfavourable impact of project on<br />
resources, shipp<strong>in</strong>g and safety and<br />
impact on landscape.<br />
28