Cumulative mining capacity of the fleet provided by AMS meets the earthmoving requirements<br />

of the mining schedule as generated by Nzema technical management and properly supports<br />

mining operations. The in-pit material excavation is largely conducted by two Liebherr 984C<br />

back-hoe excavators equipped with 7m3 buckets (main production units). Waste and near-pit<br />

ore haulage is mainly conducted by CAT 777 off-highway trucks; and material hauled out of<br />

smaller satellite pits utilizes articulated Volvo A35F trucks.<br />

The ore control strategy targeting delineation of ore and waste uses RC holes piercing multiple<br />

benches. The geological and assay information, obtained by 18m holes, assayed every 1m,<br />

represents an input to the grade control block model used by geologists and surveyors for final<br />

ore/waste discrimination and in-pit mark-up.<br />

Drilling and blasting is performed on 6 to 15m benches, depending on geological and<br />

geotechnical settings of a given deposit, with blasted material excavated in discrete 3m high<br />

flitches.<br />

Production blasting is performed by MAXAM Ghana Ltd (MAXAM).<br />

The explosives magazine on site consists of the ammonium nitrate mixing shed for the<br />

manufacturing of bulk explosives, four 20 footer containers for storing detonators, high<br />

explosives and other explosive accessories. The supply of detonators, boosters, bulk explosives,<br />

initiating systems and other explosives material into the magazines for storage and further use<br />

on the mine is the responsibility of MAXAM.<br />

The waste rock dumps associated with mining operations are constructed to meet the<br />

requirements of the Ghana Mining Regulations and the EPA. The condemnation drilling covered<br />

the areas allocated for waste dumps and was completed during 2009 to 2010.<br />

The current reserves supports another 7 years of mine life. The primary objective of the project<br />

production schedule has been to maximize the early cash flow from the operation by delaying<br />

the increased mining costs and bringing revenue forward as much as possible. This objective has<br />

been achieved within the following constraints:<br />

• Ensuring continuous ore supply to the processing plant for the selected 2 Mtpa<br />

throughput rate<br />

• Land access constraints<br />

• Keeping the vertical mining advance rates generally below 9m (3 flitches) per month<br />

(except at the start and end of the pit stages depending on the bench quantities)<br />

• Maintaining a supply of approximately four weeks of mill feed in the ROM stockpile at a<br />

reasonable grade<br />

• Maintaining constant working strip ratios and consequently smooth mining rates for<br />

extended periods of time as much as possible.<br />

Table 1.5 below represents the key parameters of the current mining schedule.<br />