[B-TRAC EVALUATION AND IMPACT STUDY] December 10, 2012<br />
2.5 ACTUAL FUNDING FOR B-TRAC PROJECT<br />
The B-TRAC scheme was started in the year 2006-07 and the annual grants given by the<br />
government <strong>for</strong> implementation of this project are as follows;<br />
Table 2.5: Actual Funding <strong>for</strong> B-TRAC Project<br />
Year Amount Released<br />
2006-07 Rs. 44 Crores<br />
2007-08 Rs. 35 Crores<br />
2008-09 Nil<br />
2009-10 Rs. 40 Crores<br />
2010-11 Rs. 5 Crores<br />
Total Rs. 124 Crores<br />
Though, the government had released funds from the financial year 2006-07, the<br />
implementation of the project started in the year 2008-09.<br />
2.6 STATUS OF B-TRAC PROJECT IMPLEMENTATION<br />
The status of B-TRAC project implementation as per TTIC <strong>Report</strong> (June 2012) in different phases<br />
is given below,<br />
Phase 1 (2006-07)<br />
Sl. No. Components Target <strong>for</strong> Project Period Status<br />
1 Road Markings 62,500 Sq. mts Tender Closed<br />
2 Upgradation of Existing<br />
Signals<br />
164 Locations Maintenance Period<br />
Completed<br />
3 Traffic Signage 1500 Nos. Tender Closed<br />
4 Lane Delineator Tubular<br />
Cones<br />
10,000 Nos. Tender Closed<br />