3.<br />
Maricopa County Lower Buckeye Jail<br />
<strong>Construction</strong> Cost: $98.9 million<br />
Start Date: June, 2001<br />
Completion Date: July, <strong>2003</strong><br />
Owner: Maricopa County Criminal Justice Facilities<br />
<strong>Construction</strong> Manager: Hunt Jacobs<br />
General Contractor: Target General<br />
Architect: DLR Group<br />
Engineer: Brooks Hersey & Associates<br />
Electrical: Rosendin Electric<br />
Concrete: Suntec; TPAC<br />
Masonry: Sun Valley Masonry<br />
Mechanical: IMCOR<br />
Steel: S & H Steel<br />
Summary: The project consists of a 1,808 bed, 654,000<br />
-sq.-ft. jail facility at the County's Durango Complex.<br />
Another two-story building on the 29-acre site will house<br />
inmate services such as the 60-bed infirmary, psychiatric<br />
hospital, and dentistry. The facility will also be the central<br />
psychiatric hospital for the entire jail system's 8,000<br />
inmates. A 600-ft. underground tunnel from the inmate<br />
blocks will lessen the public and staff exposure to<br />
inmates during transit to the various services. While<br />
much of the two, six-story inmate buildings are pre-cast<br />
concrete, designers also employed extensive use of<br />
masonry.<br />