40. EXTRA ITEM /SUBSTITUED ITEMS<br />

The rates for extra items/substituted items of work, ordered to be<br />

operated/executed shall be derived as under:<br />

a) If the item of work is similar to the item for which, the bidder has quoted rates<br />

in SOQR , the quoted rate shall be applicable.<br />

b) If the rate for the item does not appear in the SOQR , the rate shall be derived<br />

from similar items of work indicated in SOQR<br />

c) The rates for those items of work which cannot be derived from quoted rates<br />

in the SOQR shall be derived from the prevailing market rates of material and<br />

labour plus 10% towards contractor’s overheads and profits. The opinion of<br />

the Engineer in charge as to the current market rates for materials and the<br />

quantum of labour and material involved per unit shall be final and binding on<br />

the contractor.<br />

For this purpose and for the purpose of sub-clause (c) above, the coefficient<br />

of labour, material and wastage shall be adopted from the CPWD analysis of<br />

rates/standard schedule of rates as decided by the Engineer –in charge. The<br />

contractor shall submit vouchers /quotations in proof of rates paid /likely to<br />

be paid for material and labour.<br />

Above provisions for derivation of rates of extra items/substituted items shall<br />

supersede the provisions indicated in GCC.<br />

41. EXTENSION OF TIME FOR COMPLETION DUE TO ADDITION,<br />

ALTERATION AND SUBSTITUTED WORK<br />

a) In case of any addition alteration or substitution work, the time of completion<br />

of work shall be extended in the proportion to the value of altered, additional<br />

or substituted work that it bears to the original contract value of work and<br />

time. Over and above this, a further period to the extent of 20% of such<br />

extension shall be allowed to the contractor.<br />

b) The contractor shall not be entitled to increase in prices or for any<br />

compensation whatsoever on account of the extension of time allowed.<br />

c) Any extension of time granted under the provision of this clause shall be<br />

without prejudice to other conditions of contract and will not absolve the<br />

contractor from the obligations of other clauses under the contract.<br />

The decision of the owner in this regard will be final and binding on the<br />

contractor.<br />