14.08.2013 Views

Todo List for COLTRIMS setup: - AMOS Experiment at LBNL

Todo List for COLTRIMS setup: - AMOS Experiment at LBNL

Todo List for COLTRIMS setup: - AMOS Experiment at LBNL

SHOW MORE
SHOW LESS

You also want an ePaper? Increase the reach of your titles

YUMPU automatically turns print PDFs into web optimized ePapers that Google loves.

<strong>COLTRIMS</strong>-Project Management:<br />

Autom<strong>at</strong>ic Upd<strong>at</strong>e<br />

Upd<strong>at</strong>ed: 6/18/2010<br />

# Check Task D<strong>at</strong>e Done<br />

1 go after Rootsblower => Bruce has to be contacted again, and again,<br />

and again. Rootsblower never worked. Totti found old rootspump –<br />

exchanged the oil. Tests where made. Of no use <strong>for</strong> N2. For He it<br />

might makes a difference – we couldn’t see any improvement <strong>for</strong> He<br />

either on 7/20/2009. Pump stored in Storage2.<br />

2 two convectrons have a problem: Check is needed (replacement).<br />

Totti is on it. We have two working controllers and one broken<br />

one. We need a salvage meter <strong>for</strong> the broken one (they don’t<br />

make them anymore)<br />

3 we need a drill and a stand <strong>for</strong> the workbench and a little vice <strong>for</strong> the<br />

moveable workbench => Totti starts looking. Done.<br />

4 electron detector needs new pl<strong>at</strong>es => Reinhard will supply a new<br />

stack. Frankfurt people will bring it to the beamtime. We will also need<br />

two ceramic rings and an MCP holder. Totti asked <strong>for</strong> th<strong>at</strong>: Answer is<br />

“Yes”. We get a complete new Hex detector. Totti will bring it.<br />

5 decoupling box has grounding/noise problem: Needs test and debug.<br />

Tim is building a new set + anode decoupling boxes with b<strong>at</strong>tery packs<br />

(<strong>for</strong> MISTERS)<br />

6 controller cart should be replaced by a 8020 design: Markus. The big<br />

Helmholtz coils powersupply will go in a separ<strong>at</strong>e cart. Christian took<br />

over. Parts are ordered and arrived (Dec. 2008). Christian puts it<br />

together. (almost) done 1/8/09 (see task 178 below)<br />

7 new coils + powersupply (=> Totti started to look around): Needs<br />

planning, designing and construction. We will wait till Markus shows<br />

up here. Got powersupply from 88: Mike Bell and Steve Cooper work<br />

on safety (Totti). Coils: Markus is on it; hopes to finish with design by<br />

Oct. 15 2008. Design finished in Nov 08 and 8020 parts are ordered<br />

and arrived. Still <strong>at</strong> the safety guys (April 2009). Mike Fahmie (x4030)<br />

is in charge <strong>for</strong> all safety issues and the final ok. Coils can be wound<br />

starting first week of May 2009. Mike Bell will design holding pl<strong>at</strong>e and<br />

connections until this. Coils are finished with winding in 77 (7/14/09).<br />

Connections (pl<strong>at</strong>e) is still missing. Done (8/01/2009)<br />

by: TW<br />

Summer<br />

2007<br />

Summer<br />

2007<br />

Spring<br />

2007<br />

August<br />

2007<br />

Summer<br />

2007<br />

8/01/2009<br />

8/01/2009<br />

1


8 differential pumping stage: New tube (8 x 120mm ?) => Tim’s baby.<br />

Sun took over. Ken is machining parts<br />

9 repair of powersupplies, HP voltmeter, fast amplifier and CFD (Lothar<br />

will repair the CFDs once he is here): Totti is on it<br />

10 <strong>for</strong>m<strong>at</strong> d<strong>at</strong>a analysis computer, reinstall and get all the software<br />

running again => Totti will get in contact with Jim and work on it: Done<br />

11 a new 800 l turbo pump <strong>for</strong> <strong>COLTRIMS</strong> chamber is needed: Shim<strong>at</strong>su<br />

Totti: Seiko Seiki pump is repaired in time – we will use th<strong>at</strong> while we<br />

wait <strong>for</strong> the new pump<br />

12 leak test <strong>for</strong> source chamber would be nice. No leak from outside;<br />

micro leak is between last valve and chamber flange.<br />

13 check all ion gauges. They are all functioning (as well as the<br />

controller). Some filaments might be burned – so we might not have<br />

two everywhere. Sun and Totti<br />

14 marks <strong>for</strong> beamline 11 are needed => Totti will get in contact with<br />

Hendrik, Tolek and Mary (survey group). Hendrik contacted me: They<br />

will talk to the survey group but we have to check again. Scheduled <strong>for</strong><br />

January 30 th 2008. Done – marks are on the floor, but it is not clear<br />

how far the beamline has to be rot<strong>at</strong>ed.<br />

15 a new adapter flange chamber-to-differential-pumping-stage with<br />

bellow would be nice: Needs ideas and discussion. Tim found better<br />

design and is on it<br />

16 make jet-dump tube moveable => Totti has an idea. Sun is<br />

constructing. Ken is on it<br />

17 <br />

cooling of jet is mysterious: Wh<strong>at</strong> should we do ? Markus. Project<br />

postponed (new cold trap with copper rod might solve the problem)<br />

Cold trap is bad; only -115°C on copper wire, 10 cm behind trap. Most<br />

likely connection between wire and trap itself. => new trap, may be<br />

with complete rebuild of jet system<br />

18 a Drytel <strong>for</strong> the differential pumping stage is needed: Discussion open.<br />

Sun borrowed one from ALS<br />

19 a <strong>for</strong>epump <strong>for</strong> the <strong>COLTRIMS</strong> chamber is needed : Discussion open.<br />

We use a Scroll pump from ALS vacuum people (signed out by whom<br />

?)<br />

Spring<br />

2007<br />

Spring<br />

2007<br />

Spring<br />

2007<br />

Summer<br />

2007<br />

End 2008<br />

Summer<br />

2007<br />

Early<br />

spring<br />

2008<br />

Summer<br />

2007<br />

Summer<br />

2007<br />

January<br />

2009<br />

Spring<br />

2007<br />

Spring<br />

2007<br />

2


20 Chamber blind flange should turn into feedthrough flange. Totti has 4<br />

SHV 2 ¾ flange. We need an adapter to 6in. Sun is on it and found<br />

the parts<br />

Spring<br />

2007<br />

21 Oil <strong>for</strong> all turbo pumps have to be checked, e.g. replaced ! Sun did it… Summer<br />

2007<br />

22 We need a little stronger powersupply <strong>for</strong> the rainbow coils: Done by<br />

Totti<br />

23 We need a ruler on the exit slits inside the chamber: We have to find<br />

something made out of Aluminum. Sun did it<br />

24 We need two R<strong>AMOS</strong> boxes in lab 102 => Totti: Steve is on it and<br />

gets back to us. Outlets are installed.<br />

25 SAFETY: There are still chemicals in the lab: Wh<strong>at</strong> should we do ?<br />

Totti contacts Jerry….<br />

26 2 digital Frankfurt r<strong>at</strong>emeter desirable: Totti emailed to Reinhard and<br />

Lothar. Answer is “NO – not now”<br />

27 Exchange 3-fold SHV feedthrough with 4-fold SHV feedthrough: =><br />

Hunt <strong>for</strong> good one (1E-9Torr). Totti found one – hopefully it works.<br />

Sun mounted it. Gives good vacuum.<br />

28 SAFETY: Fasten the chamber to the ground. Totti: In progress…<br />

(Fred Angliss)<br />

Summer<br />

2007<br />

Summer<br />

2007<br />

Fall 2007<br />

Fall 2007<br />

Summer<br />

2007<br />

Summer<br />

2007<br />

Spring<br />

2008<br />

29 Get salvage parts from cleaning. Totti Spring<br />

2008<br />

30 Turn of the fume hood. Totti: Answer is “NO”. Hood is part of the AC<br />

system of lab 102<br />

31 Think about the use of a hex det and a 120mm <strong>for</strong> BL 10 experiment:<br />

Hex Det = Yes. Detectors have to be set-up (put together and look <strong>for</strong><br />

wiring). We have to find out how the 80mm detector can be mounted<br />

to the big spectrometer and how to lift the spectrometer or <strong>setup</strong> the<br />

big spectrometer<br />

32 Get in contact with Claude Linus and Dennis Collins <strong>at</strong> building 88:<br />

300A/30V Powersupply: Totti did it and got the powersupply<br />

Winter<br />

2007<br />

Summer<br />

2007<br />

Summer<br />

2007<br />

3


33 We need an efficient beamdump <strong>for</strong> 30 to 55 eV photons (Woods<br />

Horn): We will mount a 6in bellow <strong>at</strong> the exit of the chamber. Support<br />

rods were constructed by Totti and are in the machine shop. We need<br />

a good stand <strong>for</strong> the 6in pipe then (found something made out of<br />

steel).<br />

34 Spectrometer has to be simul<strong>at</strong>ed and designed: Need in<strong>for</strong>m<strong>at</strong>ion<br />

about KER and Electron energy first. Sun’s job and she is on it<br />

35 Get in contact with David Kilcoyne from BL 10L Fluxcurves, beam<br />

height, space constraints etc. Sun and Totti<br />

Summer<br />

2007<br />

Spring<br />

2007<br />

Spring<br />

2007<br />

36 We need a big Ethylene gas bottle. Sun Summer<br />

2007<br />

37 A computer <strong>for</strong> Acquiris: Has been ordered by Totti and M<strong>at</strong>thias – it<br />

has to be set up once it is here. Done by Totti<br />

38 We have to check with David Kilcoyne again about: Polariz<strong>at</strong>ion and<br />

gas cell in front of our <strong>setup</strong> and reloc<strong>at</strong>ion of the two cabinets <strong>at</strong> the<br />

beamline. Totti and Sun will do th<strong>at</strong><br />

Summer<br />

2007<br />

Summer<br />

2007<br />

39 Setup spectrometer: Sun did it Summer<br />

2007<br />

40 Implement bellow into differential pumping stage and test <strong>for</strong> good<br />

pressure: Sun did it<br />

41 Detectors need new cables of the right length and a coppering on the<br />

electron side: Sun and Totti did it<br />

Summer<br />

2007<br />

Summer<br />

2007<br />

42 Turn the “B<strong>at</strong>man” (machine shop work): Sun did it Summer<br />

2007<br />

43 Look <strong>for</strong> Acetylene as a backup plan and CO <strong>for</strong> calibr<strong>at</strong>ion (in<strong>for</strong>m<br />

David th<strong>at</strong> we want to use the yellow gas cabinet): Sun did it<br />

44 Construct and <strong>setup</strong> a movable table <strong>for</strong> differential stage: Totti, Sun<br />

and Felix<br />

Summer<br />

2007<br />

Summer<br />

2007<br />

45 Software <strong>for</strong> Acquiris is missing: Frankfurt Fall 2007<br />

46 Preanalysis routine <strong>for</strong> C2H4 (PAW): Sun is on it Fall 2007<br />

47 Get Telescope from building 88 (Bob Shannon): Totti got it Spring<br />

2008<br />

4


End of 2-Bunch-Run 8/2007<br />

48 Replace 4 to 2¾in adapter on collim<strong>at</strong>or cross (put new aperture<br />

inside): Felix<br />

Winter<br />

2007<br />

49 Exchange 4-fold BNC feedthrough with 4-fold SHV-feedthrough: Felix Winter<br />

2007<br />

50 SAFETY: Build gas manifold (bypass to Scroll pump and convectron<br />

needed, <strong>at</strong> least three inputs desirable): Felix and Totti<br />

51 SAFETY: Exhaust <strong>for</strong> diaphragm pump needs connection to KF: Felix<br />

and Totti<br />

52 Repair decoupling cylinders (note, there are 100 instead of 150 Ohm<br />

in one of them) and b<strong>at</strong>tery boxes: Josh and Felix<br />

53 Check tools <strong>for</strong> missing parts: For instance small round files are<br />

needed. Felix and Sun<br />

Spring<br />

2008<br />

Spring<br />

2008<br />

Summer<br />

2008<br />

Spring<br />

2008<br />

54 Check and order Lemo cables: Felix and Totti Spring<br />

2008<br />

55 Check and make short (3in) SHV cables: Felix Spring<br />

2008<br />

56 Check and order Lemo adapters, T’s, 50 Ohm….: Felix and Totti Spring<br />

2008<br />

57 Check digital scope (one channel might be broken <strong>at</strong> low amplific<strong>at</strong>ion;<br />

ask Tim): Tim and Felix. Channel 1 below 100mV does not work –<br />

repair is too expensive<br />

58 Think about rainbow coils: How can we increase the current going<br />

through ? Felix and Totti: New computer cables in parallel<br />

59 Change the offset flange <strong>at</strong> chamber entrance (according to new<br />

spectrometer): Felix<br />

60 Get adapter <strong>for</strong> new turbo pump and mount it: Totti got it/mounting<br />

postponed<br />

61 Arms and their Mounting pl<strong>at</strong>es <strong>for</strong> Helmholtz-coils have to be<br />

changed to 8020 design: Felix<br />

Spring<br />

2008<br />

Spring<br />

2008<br />

Spring<br />

2008<br />

Summer<br />

2008<br />

Summer<br />

2008<br />

62 Organize a Drytell and the rebuilt Scroll pump from Evan: Sun Spring<br />

2008<br />

5


63 Check <strong>for</strong> Alc<strong>at</strong>el ACP20 (found in the dumpster) with Evan again:<br />

Totti – can not be repaired ;-(<br />

64 <br />

Software upgrades on computers: COBOLD, SIMION and Compilers:<br />

Markus orders; hopefully done by Oct. 15. Compiler arrived and was<br />

installed on Markus and Christians computer.<br />

65 Check and get Kwikflange (Hoses, clamps, rings…) and Swagelok<br />

(valves, bending tool…): Felix and Totti<br />

66 Connect printer to acquisition computer and get new cartridges: Felix<br />

and Totti. Totti installed the printer; cartridges are new but print heads<br />

are bad. Too expensive to replace. Buying a new printer (150$) is<br />

cheaper (low priority)<br />

Spring<br />

2008<br />

Winter<br />

2008<br />

Spring<br />

2008<br />

Summer<br />

2008<br />

67 Put pumps on wheels: Felix Spring<br />

2008<br />

68 Make a jet test with the roots pump: Felix and Totti Spring<br />

2008<br />

69 Repair chamber ion gauge and cable: Felix and Sun Spring<br />

2008<br />

End of 2-Bunch-Run 3/2008<br />

70 Get Electronics Rack from ALS (sector 10): Sun, Totti and Steve<br />

Cooper<br />

71 Get electronics (Powersupply, CFD, NIM bins) from repair: Totti (one<br />

CFD is still in repair). Done<br />

Spring<br />

2008<br />

Summer<br />

2008<br />

72 New phosphor screen: Sun and Felix Summer<br />

2008<br />

73 Mark more tools with pink dot: Sun, Totti and Felix Summer<br />

2008<br />

74 Wh<strong>at</strong> should we do with the Hex-Anode ? Totti, Reinhard, Lothar. Has<br />

to be replaced with new one. Markus brought it.<br />

75 Adapters <strong>for</strong> differential stage need taped holes <strong>for</strong> center piece of the<br />

tube. Sun and Felix<br />

Summer<br />

2008<br />

Summer<br />

2008<br />

6


76 New 2 nd (and 3 rd ?) harddrive <strong>for</strong> D<strong>at</strong>a acquisition computer has to be<br />

ordered and mounted (SATA): M<strong>at</strong>thias ordered two and installed<br />

them.<br />

77 SAFETY: Connection <strong>for</strong> 300A power supply (208VAC/50A) plus<br />

safety shield around electrodes: Totti, Evan and Steve Cooper. Device<br />

is in EI shop<br />

Spring<br />

2008<br />

Summer<br />

2008<br />

78 On/Off switch <strong>for</strong> scroll pump is needed: Totti and Steve Cooper Spring<br />

2008<br />

79 Need convectron <strong>for</strong> 1 st stage: Felix and Totti Spring<br />

2008<br />

80 Need convectron <strong>for</strong> gas manifold: Felix and Totti Spring<br />

2008<br />

81 W<strong>at</strong>er connection in 102: Felix and Sun Spring<br />

2008<br />

82 Need gases and regul<strong>at</strong>ors <strong>for</strong> N2, CO, CO2, Ne: Felix and Sun Summer<br />

2008<br />

83 80mm detectors have to be reassembled: Felix and Sun (+Totti) Summer<br />

2008<br />

84 Stabilized Jet-he<strong>at</strong>ing; need controller, power supply and test<br />

Irina works on it<br />

6/17/2010<br />

85 SAFETY: Order Earmuffs: Felix Spring<br />

2008<br />

86 Coldtrap lids should be higher and might need holes: Felix Spring<br />

2008<br />

87 Mount CF150 cross <strong>for</strong> long spectrometer: Felix and Sun Spring<br />

2008<br />

88 Lab improvement list: All. Totti - no input from other team members Summer<br />

2008<br />

End of 2-Bunch-Run 8/2008<br />

89 Makeover of the differential pumping stage: Tube has to be part of the<br />

stage not of the chamber. postponed<br />

7


6 New controller cart needed (8020): Markus. Christian took over; parts<br />

are ordered and arrived (Dec. 2008). Some parts are still missing and<br />

have to be ordered. Stuff arrived. Christian puts things together. Alupl<strong>at</strong>es<br />

<strong>for</strong> the top and bottom are designed and have to go into the<br />

machine shop. They are now mounted. Frame is rein<strong>for</strong>ced. Still some<br />

brackets are missing. Feet got altered (4/12/09). Got plexi glass lips<br />

on top. Frame is assembled. First modules went in (5/1/09). Feet are<br />

ready to be <strong>at</strong>tached (5/19/09). Modules have to go up to make a<br />

complete unit fit <strong>at</strong> the bottom (6/2/09). Folder boxes needed <strong>for</strong> safety<br />

and emergency shutdown list: Totti ordered something and mounted it<br />

(6/9/09). Labels on Power cords are needed. Power has to be<br />

redistributed evenly. Brackets are needed to <strong>at</strong>tach chain <strong>for</strong> seismic<br />

safety (chains and quick connectors have to be found and cut: Totti<br />

found something <strong>for</strong> a start). Totti did it (6/4/09). Totti ordered double<br />

8020 brackets <strong>for</strong> feet and installed them 9/18/09.<br />

91 Aluminum pl<strong>at</strong>es (mesh-holders) <strong>for</strong> spectrometers need holes and<br />

threads to take detector + new Aluminum arms are needed (to replace<br />

the broken ones; done by Felix). Markus; scheduled <strong>for</strong> end of Nov.<br />

Still have to go in the machine shop. Done<br />

92 <br />

93 <br />

SAFETY: Complete check on all regul<strong>at</strong>ors <strong>for</strong> all gases and pressure<br />

ranges: Markus + Christian; scheduled <strong>for</strong> Dec. => Regul<strong>at</strong>ors <strong>for</strong><br />

flammable gases (H2, CO, CmHn) tested and ok (3 x 60 psi, 2 x 600<br />

psi); Rare gases, N2 (4 x 60 psi, 1 x 1200 psi). Have couple of broken<br />

or unknown ones (will repair when needed). Look out <strong>for</strong> spare one<br />

with high pressure (1000psi, rare gases). Good regul<strong>at</strong>ors are labeled<br />

now.<br />

New/big coils may need new 8020 arms (longer and perhaps<br />

stronger): Totti (has to wait on Markus to finish designing and<br />

construction of the coils first; 8020 profiles are available and need to<br />

be cut then). Checked: Old arms do the job<br />

94 Check LEMO, BNC, SHV cables, Ts, barrels and adapters: Markus +<br />

Christian. SHV and Lemo cables, Ts and adapters checked and bad<br />

ones rejected<br />

95 Check the anode cylinders + new (universal) voltage divider or b<strong>at</strong>tery<br />

boxes are needed (perhaps with potis). Think of 6 SHV connectors…:<br />

Josh and Felix are on it. They put voltage divider in cylinders – works<br />

well…<br />

96 New voltage divider boxes are needed <strong>for</strong> the detectors (to have potis<br />

would be nice): Felix is on it<br />

97 2 more decoupling boxes <strong>for</strong> the spectrometer are needed: Felix is on<br />

it<br />

7/20/2009<br />

+<br />

9/18/2009<br />

1/30/2009<br />

01/26/2009<br />

05/11/2009<br />

January<br />

2009<br />

Summer<br />

2008<br />

Summer<br />

2008<br />

Summer<br />

2008<br />

8


98 Moveable Scintill<strong>at</strong>or going inside the spectrometer of any size has to<br />

be constructed (<strong>at</strong>tached to the chamber – not to the spectrometer):<br />

Totti started looking around. Josh is building the support arm – did not<br />

work; needs improvement: Totti took over and reconstructed some<br />

parts and made a new rail system. Parts are ready, installed and work<br />

“ok” (not perfect). Push-pull and 4xSHV feedthroughs got switched.<br />

Arm <strong>for</strong> front phosphor is adjusted. Phosphor or Szintill<strong>at</strong>or is still<br />

missing and Vacuum test is needed (Markus)… See 138<br />

99 Nozzle was clogged – we cleaned it but a jet test is necessary:<br />

Markus. Nozzle is free – cooling remains a problem<br />

100 <br />

SAFETY: Pumps on wheels: Get rid of the wooden boards (fire<br />

hazards) and replace with Aluminum: Markus + Christian; projected <strong>for</strong><br />

January 2009.<br />

101 Measure the convectron gauges: There has to be 20 Ohm between<br />

pin 1 and 2 (if not it is likely to be broken). One can clean a convectron<br />

with Alcohol or Acetone cautiously<br />

=> moved down<br />

102 We need a new MCP holder <strong>for</strong> 80mm pl<strong>at</strong>es th<strong>at</strong> fit the 120mm Quad<br />

Anode plus a ceramic ring with a big copper pl<strong>at</strong>e/ring on the front to<br />

compens<strong>at</strong>e fringe fields (recoil det): Markus, Sven and Ottmar<br />

103 Electronic Rack: Rack blower in the middle has a damaged fan on the<br />

right. Replace. Totti looked <strong>at</strong> it and cleaned a little with pressurized<br />

air. Does not run gre<strong>at</strong> but is ok <strong>for</strong> now.<br />

8/30/2008<br />

Spring<br />

2008<br />

01/25/2009<br />

Summer<br />

2008<br />

8/15/2008<br />

104 SAFETY: Rainbow coils: Replace orange plug. Totti did it 8/20/2008<br />

105 SAFETY: We need more little electronic boxes with grounding (robust<br />

style): Load Resistors, Voltage divider (<strong>for</strong> Grid or Copperpl<strong>at</strong>e)…<br />

Especially 1:10 and 1:20 voltage divider are needed <strong>for</strong> monitoring<br />

Voltages up to 1000 or 2000 V (Totti got input from EM shop: SHV-<br />

Banana is not available – voltage dividers with output of max 100V are<br />

okay in order to bring it to BNC). Totti ordered 20 boxes (<strong>for</strong><br />

<strong>COLTRIMS</strong> and MISTERS). Christian will build them and is on it.<br />

Almost finished – tests would be desirable.<br />

106 Decoupling boxes need mechanical support: Christian + Totti. 4<br />

pieces are machined in the shop <strong>for</strong> <strong>COLTRIMS</strong>. If it works we will<br />

order 4 more <strong>for</strong> MISTERS. Totti gave drawings to Rene. Christian will<br />

order threaded rods and nuts.<br />

2/20.2009<br />

11/08/2008<br />

9


107 Check the very short SHV-SHV cables <strong>for</strong> damage: They are poorly<br />

made – very unreliable. Complain <strong>at</strong> EI shop (see 94): Markus +<br />

Christian. 4 SHV bad cables found (still working, but plastic insul<strong>at</strong>ion<br />

<strong>at</strong> connector damaged) => put in “useful broken cable”-box<br />

1/30/2009<br />

108 Manifold: Replace one valve with a lockable one. Totti did it. 8/15/2008<br />

109 Phosphor: Front phosphor was weak and peeling off in vacuum (too<br />

much glue ?). Totti spoke to David K. about flaking phosphor: We<br />

made the layer too thick. He will help with air brushing phosphor on<br />

glass pl<strong>at</strong>es – Totti and David did it. Small Phosphor or Scintill<strong>at</strong>or <strong>for</strong><br />

spectrometer arm is still missing – Totti did it. See also 123 and 138<br />

92 <br />

SAFETY: Check regul<strong>at</strong>ors <strong>for</strong> leaks and appropri<strong>at</strong>e range (high<br />

pressure). Markus + Christian<br />

111 Rods <strong>for</strong> anode cylinders are still missing. Ken is on it. Totti will check.<br />

Done and installed. Needed rewiring. Test would be good…<br />

112 SAFETY: Check crane post <strong>for</strong> missing screws. Replace broken<br />

brackets. Totti did it – not all the screws are in but it seems ok.<br />

113 SAFETY: Check crane wheel <strong>at</strong> the tip. Totti did it and gener<strong>at</strong>ed a<br />

required crane log book<br />

114 We need a NIM-NIM power cable – 10 feet long<br />

115 Oil <strong>for</strong> the small 4 turbo pumps needs to be ordered from Pfeiffer:<br />

Totti. Ordered 8/20/09. Arrived 9/3/09. Inserted 9/8/09.<br />

116 Redesign MCP Holder pl<strong>at</strong>e <strong>for</strong> Hexdetector and Quad 80 (similar to<br />

DLD120). Markus; will be finished by end of Oct. Still in machine shop.<br />

(Jan 2009)<br />

117 Ion Gauge in Source Chamber: Replace broken filament (David K.<br />

might help us out). New filament available in ALS shop ($70) but we<br />

might be able to use a filament from the old ion gauges. Totti did it,<br />

see below.<br />

118 SAFETY: Replace the 30 year old ion gauges with new ones. Cables<br />

to connect to the old controllers have to be fabric<strong>at</strong>ed though (EM<br />

shop). Totti is on it and bought 3 gauges. Gauges are installed and the<br />

broken one is repaired with a filament of an old ion gauge. NOTE: We<br />

are not oper<strong>at</strong>ional because of the cables! EI people will order 4 “pigtails”<br />

and modify our old cables. Work in progress. Done – test needed<br />

(Markus who has to per<strong>for</strong>m the vacuum test: 1/16/09 test done –<br />

cable were wired the wrong way by EI shop). Now everything is ok.<br />

12/01/2008<br />

January<br />

2009<br />

9/1/2008<br />

8/17/2008<br />

11/30/2008<br />

9/8/2009<br />

2/18/2009<br />

8/16/2008<br />

10/1/2008<br />

10


119 <br />

Convectron gauge in Manifold has problem: Try to readjust or replace.<br />

Markus + Christian; starts with 17 and 123. Oct. 15. => Manifold<br />

convectron gauge shows right pressure.<br />

120 Repair Phillips CFD 715: Center channel jumps in time (seen on<br />

computer, it is not a cable delay problem). Give to Eric Henson. Totti<br />

did it<br />

January<br />

2009<br />

8/15/2008<br />

121 Repair Ortec 441 R<strong>at</strong>emeter. Give to Eric Henson. Totti did it 8/15/2008<br />

122 Powersupply of Helmholtz coils: Display is broken; maybe more. Give<br />

to EM shop. Totti did it. Back from repair. Should work.<br />

123 Open the jet which got clogged during summer beamtime: Clean the<br />

nozzle. Get new Swagelok filter. Remove mesh in front of nozzle !?<br />

Totti prepared dismount of turbo pump. Markus + Christian. Markus<br />

cleaned nozzle and put stuff back together. Jettest and vacuum test<br />

(also of the phosphor feedthrough) is still needed. First test gave<br />

factor too small rise in jetdump. Reopened and reduced the distance<br />

to skimmer from 11 to 5 mm. Now jet is working fine (no new filter was<br />

implemented though).<br />

8/15/2008<br />

1/21/2009<br />

124 Check all 5 NIM bins (each slot) <strong>for</strong> voltages. Totti did it 8/16/2008<br />

125 Pin <strong>at</strong> 120mm quad anode fell off. Solder…. Totti did it 8/16/2008<br />

126 Re-center the Chamber on the frame. Adjust the little frame <strong>for</strong> the<br />

differential pumping stage. Totti did it<br />

127 SAFTEY: Earthquake brackets <strong>for</strong> Chambers in 102 and 104 are not<br />

safe. Redesign needed. Totti did it – prototype will be made by Rene.<br />

Prototype is now revised. Rene is making 12 stereotypes. Done and<br />

installed<br />

128 Harddrives in d<strong>at</strong>a acquisition and d<strong>at</strong>a analysis computer have to be<br />

replaced. Perhaps order four 500 GB HDs (check if BIOS would be<br />

happy with th<strong>at</strong>). Think of the possible options. M<strong>at</strong>thias ordered HDs<br />

and they arrived. However, there are not mounted yet. Markus will<br />

replace some: see 148.<br />

129 Monitor of d<strong>at</strong>a analysis computer has a problem. Might be still under<br />

warranty. Totti is on it. Sent it out <strong>for</strong> repair. Came back and was also<br />

broken. Send out again. Came back and works.<br />

130 SAFETY: Multiple outlets near w<strong>at</strong>er lines (within 6 feet) need plastic<br />

box: Totti did it<br />

8/16/2008<br />

9/9/2008<br />

12/01/2008<br />

9/11/2008<br />

8/22/2008<br />

11


131 SAFETY: As found during summer beamtime lid needs support<br />

threaded rods (+cylinders with delrin ends) to take the load in case we<br />

open the chamber and work under the lid: Markus. Rods were<br />

designed and machine in cooper<strong>at</strong>ion with machinist (Rene Delano)<br />

and engineer. Parts in machine shop. Only 3 instead of 4 rods were<br />

done. Test needed. Done: 3 rods are strong enough.<br />

132 SAFETY: We have to find a way to get the LN2 out of the trap fast<br />

and safe in case we have to open the chamber: Sun will ask Frank<br />

Zucca. Markus will sketch a delrin lid with inlet <strong>for</strong> pressurized air and<br />

an outlet <strong>for</strong> LN2 (+ pressure relief valve maybe). Totti took over:<br />

Sketch was presented to Jim Floyd. He will think about it and get back<br />

to us… Vacuum cleaner in combin<strong>at</strong>ion with dewar might do the job.<br />

Lid <strong>for</strong> dewar was constructed and machined with Rene (safety<br />

aspects taken into account). Vacuum cleaner war ordered and arrived.<br />

Test with w<strong>at</strong>er worked ok. Test with LN2 failed: The hose was too<br />

small. Totti “organized” bigger hose (LN2 certific<strong>at</strong>ed) and insul<strong>at</strong>ed it<br />

with foam. Test was positive. Rene makes new handle. Done – will<br />

work.<br />

133 Jetdump endpl<strong>at</strong>e and nut have to be milled down to gain some<br />

clearance between the spectrometer and the Jetdump: Totti made a<br />

drawing. It is in the machine shop. Done and installed. Jetdump tube<br />

needs adjustment: see 137<br />

134 SAFETY: Electronic rack has a broken wheel. Needs replacement<br />

wheels (with brakes). Chamber wheels don’t look so well either (Totti<br />

replaced them)… Markus; order goes out with 6 and 7. Markus and<br />

Christian replaced the wheel.<br />

135 D<strong>at</strong>a acquisition computer has a driver problem with the DVD writer. It<br />

can not burn DVDs. Totti tried to upd<strong>at</strong>e the driver (but there are no<br />

newer versions out there) and upd<strong>at</strong>ed NERO. Still no success. Help<br />

from somebody else is needed. M<strong>at</strong>thias did it: Cable was loose due<br />

to transport<strong>at</strong>ion from and to the ALS.<br />

136 SAFETY: ALS wooden roll stoppers need rubber pads. Sun ordered<br />

parts. Totti cut rubber pads and improved 30 wooden brackets (we are<br />

out of rubber pads and silicon glue again). Sun ordered more.<br />

137 Jetdump tube in Jetdump-cylinder needs adjustment. Markus +<br />

Christian + Sun<br />

10/1/2008<br />

1/19/2009<br />

8/27/2008<br />

11/20/2008<br />

9/5/2008<br />

9/8/2008<br />

2/25/2009<br />

12


138 We need 5mm wide and 5cm long glass pl<strong>at</strong>es <strong>for</strong> the phosphor and<br />

help from David Kilcoyne with airbrushing. Totti ordered new glass<br />

cutter. Sun cut the class pl<strong>at</strong>es. Totti and Sun will approach David and<br />

Hendrik. Phosphor is on pl<strong>at</strong>es (thanks to David). Pl<strong>at</strong>es were tested<br />

<strong>at</strong> HH Laser in 458. We saw something and taking in account th<strong>at</strong> this<br />

was 10Hz it might work <strong>at</strong> the ALS. Totti remains skeptical…<br />

139 Helmholtz Powersupplies need place to store them. Ask in building 2<br />

and so on…: Markus. One powersupply (800 A / 20 V) got stored in<br />

storage (warehouse). No place <strong>for</strong> the PowerTen powersupply has<br />

been found yet (Feb. 2009). Put Powerten Powersupply in the back of<br />

building 7 and labeled it 9/30/09.<br />

140 SAFETY: New Helmholtz coils need save cable and w<strong>at</strong>er hose<br />

connection. Plastic box is needed or similar. Markus will check back<br />

on EI shop. => Plastic box is fine, still waiting <strong>for</strong> official safety<br />

inspectors (April. 2009). M. Bell: “No w<strong>at</strong>er leak detection needed but<br />

flow controller is desirable” (March. 2009). Temper<strong>at</strong>ure sensor would<br />

be a good idea as well. Mike Bell took over. Done 7/31/09.<br />

141 SAFETY: Administr<strong>at</strong>ive lockout procedure <strong>for</strong> gas manifold + labels +<br />

swagelok cap are needed. Rene put cap on a chain, Totti made Alu<br />

labels and wrote the admin. Procedure (which was <strong>for</strong>warded to the<br />

ALS safety staff by Dec. 18). Input from Donna Hamamoto and Will<br />

Thur are expected <strong>for</strong> January 2009. No feedback to two more emails<br />

– case closed <strong>for</strong> now.<br />

142 Ne spectrometer has to be simul<strong>at</strong>ed (Allen) and constructed and<br />

fitted to the chamber + the right offset flange has to be found and<br />

mounted (Markus).<br />

143 SAFETY: Portable box with Personal Protective Equipment <strong>for</strong> the<br />

ALS beamtimes is needed (containing gloves, earplugs, earmuffs,<br />

glasses, goggles…). Totti and Sun put something together. Wrong<br />

earmuffs were delivered (RMA in process). Box still needs some<br />

labels about the contents on the outside (Totti did it – waiting <strong>for</strong><br />

Earmuffs: Sun got them).<br />

144 Spare blue HP NIM bin with broken 12V and a silver Tenelec NIM bin<br />

with broken 6V was found <strong>at</strong> salvage area. Totti gave it to Eric Henson<br />

(who is in the hospital <strong>for</strong> some weeks) <strong>for</strong> repair around Dec. 18 and<br />

Jan. 22/08. Eric is out <strong>for</strong> a couple of months (3/31/09). Eric is back<br />

but hasn’t started yet (9/10/09). Totti picked them up and brought<br />

them to the ALS (3/21/10).<br />

=> moved down<br />

12/06/2008<br />

9/30/2009<br />

7/31/2009<br />

1/22/2009<br />

2/20/2009<br />

1/12/2008<br />

13


145 Gases have to be ordered: Ne, He, CO (gas cabinet). Markus. Gases<br />

ordered (CO lecture bottle UHP, Neon bottle 80 research grade)<br />

146 CF150 cross with turbo pump has to be mounted on recoil ion side.<br />

Markus<br />

147 8020 support of differential pumping stage is weak. 1530 Profiles<br />

would be stronger. Totti ordered some stuff from 8020 (9/10/09).<br />

Arrived 9/18/09. Needs to be mounted. Totti did it 9/25/09<br />

1/10/2009<br />

2/3/2009<br />

9/25/2009<br />

148 Mount two new Hard Drives into D<strong>at</strong>a Analysis Computer. Markus 2/26/2009<br />

149 Attaching hex80 to 80 Spectrometer has to be solved. Markus has an<br />

idea and designs parts.<br />

150 SAFETY: Quartz glass protection cover <strong>for</strong> CF40 glass flange on<br />

Jetdump. Markus got one.<br />

2/26/2009<br />

2/5/2009<br />

End of 2-Bunch-Run 3/2009<br />

151 SAFETY: Thin green grounding cable on chamber frame (electron<br />

side) needs to be replaced + there is another one with a loose<br />

connection <strong>at</strong> the lug. We need more grounding cables as back-up<br />

Christian + Totti replaced the bad and three short ones 3/26/09. We<br />

now have some short spares (not really good ones). It’s still a good<br />

idea to have about 5 good spares (AWG14, 1.25m long or so). Totti<br />

took care of it.<br />

152 SAFETY: Chamber needs motorcycle jack or something like th<strong>at</strong> to<br />

position it while it is elev<strong>at</strong>ed Totti thinks of transfer pl<strong>at</strong>es from<br />

McMaster instead. Ordered. Is in 77 <strong>for</strong> welding (5/12/09)… Parts are<br />

done (5/21/09). Test needed with new electronic rack <strong>for</strong> instance.<br />

Have to wait on Christian to finish it first. Test done (5/22/09). Will<br />

work but we need scissor jacks to stabilize chamber and take the<br />

weight once we put the pl<strong>at</strong>es under the feet. Totti ordered two jacks<br />

(arrived 5/26/09). Put a box together with transfer pl<strong>at</strong>es and scissor<br />

jacks (under the workbench). Depending on the height of the chamber<br />

wooden blocks might be needed too – we should look out <strong>for</strong><br />

something (building 7 and 79).<br />

153 SAFETY: Last lockable valve on manifold was missing: Totti ordered<br />

it; arrived 3/11; replaced it + changed admin lockout procedure.<br />

3/31/2009<br />

5/26/0209<br />

3/18/2009<br />

14


154 SAFETY: Anchor bolts in 102 were pulled out of the floor. Totti filed in<br />

work order 3/18/2009 and got in contact with Monroe Thomas. Hope<br />

to get got more help <strong>for</strong>m James Mankini… Mankini contacted Fred<br />

Angliss (he will stop by 4/1/09). Steve Cooper stepped in and<br />

contacted Tom Reese: Deeper drilling is necessary. Th<strong>at</strong> requires<br />

floor scanning. Steve Cooper arranged <strong>for</strong> floor scanning (4/1/09). The<br />

scanning report will be sent to James Mankini in the near future <strong>for</strong><br />

completion of the drill permit. In the meantime Fred Angliss took a look<br />

<strong>at</strong> the floor and concluded the following: A) the wrong anchor bolts<br />

were installed (they were not in agreement with his calcul<strong>at</strong>ions). B)<br />

The concrete is busted <strong>at</strong> two places, thus the tiles should come out in<br />

order to take a closer look. C) He recommends replacing all 8 anchor<br />

bolts with 3/8in HILTI KB-TZ, 2.5in embedded. The tiles have to be<br />

removed wherever the concrete is busted in order to conclude<br />

(together with Fred) if a deeper drilling would fix the problem or if the<br />

concrete needs to be fixed first (Carpenters do th<strong>at</strong> 4/2/09). Totti<br />

moved the chamber <strong>for</strong> this purpose. Tom Reese will then send<br />

somebody to take all 8 anchor bolts out. Done: Anchor bolts installed<br />

by carpenter (Warren Elliot). Chamber back in place.<br />

155 SAFETY: Main grounding cables have to remain with frame, pump<br />

cart or electronic rack. Totti put labels on except controller cart (we<br />

wait <strong>for</strong> the new cart here – done: Totti put label on 5/28/09)<br />

156 Electronic/Detector tests: a) test new decoupling boxes and voltage<br />

divider, b) lens potis, c) spectrometer voltage dividers, d) old<br />

decoupling cylinders (150 Ohm, contacts, cable configur<strong>at</strong>ion…), e)<br />

fast amplifier (need labels <strong>for</strong> polarity, amp. Factor) Christian.<br />

Everything soldered and ready to be tested 7/10/09 (we need a<br />

detector and spectrometer in vacuum). Done<br />

157 Spectrometer voltmeter (on the right hand side of the rack) has bad<br />

switch: fix it Totti. Took the front panel out and filed the slot <strong>for</strong> the<br />

button a little bigger. Works better but not gre<strong>at</strong>.<br />

158 MISTERS decoupling cylinders have to be modified as a back-up<br />

Christian. Done 7/10/09. Test is still needed.<br />

159 We have to buy more meshes (80%, 200 micron). We lost 7 sheets<br />

Markus. Quote requested (4/14/08). Ordered (4/20/09). Arrived and<br />

cut. Stuff was pretty crumpled on roll. Loss is estim<strong>at</strong>ed to 50%.<br />

Markus complained <strong>at</strong> TWP Inc. but they don’t care…<br />

160 We need a KF, CF and screw supply suitcase <strong>for</strong> the beamtime. Totti<br />

found something 3/25/09. Nuts & Bolts supply is fine. We need more<br />

supplies to fill the CF/KF suitcase. Totti bought some stuff, but KF25<br />

o-rings are missing <strong>for</strong> instance (ALS shop is out of it)… got some<br />

4/14/09. We now have the minimum equipment.<br />

4/7/2009<br />

3/31/2009<br />

7/28/2009<br />

3/24/2009<br />

7/28/2009<br />

4/30/2009<br />

4/14/2009<br />

15


161 SHV-whip needs new label Totti did it. Decoupling boxes and<br />

cylinders + voltage divider need labels and drawings etc. Markus did it<br />

162 D<strong>at</strong>a analysis computer is getting too slow: We should use Sun’s or<br />

M<strong>at</strong>thias’ computer. Ali offered his PC and Monitor… We will use<br />

M<strong>at</strong>thias computer as analysis computer. Needs re<strong>for</strong>m<strong>at</strong>ting since it<br />

is fubar software wise. With IT service (8/24/09). Totti brought it back<br />

from IT service and <strong>setup</strong> the accounts and put IT security software<br />

on it (8/31/09). Needs ROOT, PAW, COBOLD, Background, R<strong>at</strong>e<br />

Alarm, Backup Programs, Compiler, Origin, GS, Acrob<strong>at</strong>… Totti<br />

started putting stuff on 9/17/09 (Cobold, Background, R<strong>at</strong>e Alarm,<br />

Backup Programs, GS, PAW, ROOT, Compiler). Totti moved<br />

computer to 2-102 and put it in gear 9/23/09. Markus put more<br />

programs on it 3/10/10<br />

163 Work on Jet: Cooling (new coldtrap), nozzle cleaning or new nozzle<br />

design. Jet test with Roots pump <strong>for</strong> He (it might help) Markus. New<br />

nozzle and holding parts designed and in machine shop with Rene<br />

(4/9/09). First approach (using old coldtrap). New coldtrap is designed<br />

and in machine shop with Rene (4/21/09). CF35 pipe was ordered<br />

and arrived (4/29/09). Filter and gold gasket brought from Frankfurt<br />

(6/03/09). Everything put together 7/13/09. Jettest on 7/14/09 without<br />

and with Roots Forepump. Analysis of the results shows th<strong>at</strong> rootspump<br />

does not help. Per<strong>for</strong>mance with respect to the old design =<br />

??? New coldtrap is still in shop and needs to be mounted (8/2/09).<br />

Totti and Rene decided on the length and welding procedure of cold<br />

trap. M<strong>at</strong>erial got ordered. Totti spoke to Bob Conroy how to <strong>at</strong>tach<br />

the copper braid. Rene drilled the holes in the rod and in the newly<br />

designed clamp. Rene points out th<strong>at</strong> knife edge on CF100 flange is<br />

not wonderful – could be polished !? Copper bottom and CF100 top<br />

flange is done. Next step: Cut the stainless tube by 6.5mm, weld cold<br />

trap (Rene). Weld copper braid to clamp and rod (Bob) 10/29/09.<br />

Copper rod + braid + clamp done and shaped down. Coldtrap<br />

completely welded 11/20/09. Resistor needs to be <strong>at</strong>tached and<br />

jetflange on chamber rot<strong>at</strong>ed + new gas inlet + makeover of rainbow<br />

coils (see 198).<br />

164 D<strong>at</strong>a acquisition computer needs recovery Markus brought it to IT<br />

Service 3/20/2009; we might need to replace the harddrive. Totti<br />

picked it up. New Seag<strong>at</strong>e HD was installed. Upd<strong>at</strong>ed XP, Symantec<br />

and Spybot + defragmented C and D drive. Got rid of Spybot and<br />

Symantec and put Sophos on acqu. and analysis computer.<br />

165 New 120 spectrometer (copper pl<strong>at</strong>es + drift tube needed) Markus.<br />

Spectrometer parts and det. mounting in machine shop. Alu pipe<br />

ordered and arrived (4/29/09). Parts are in machine shop: copper<br />

pl<strong>at</strong>e in 80, drift tube etc. with Rene… Core is assembled by Christian.<br />

Drift follows… Resistors connected (06/25/09), Drift still missing. Done<br />

7/10/09 (incl. mesh in front of Recoil Ion Det).<br />

4/14/2009<br />

3/10/2010<br />

2/17/2010<br />

3/23/2009<br />

7/10/2009<br />

16


166 Long CF150 spool + bello <strong>for</strong> spectrometer + frame or stand has to be<br />

in place Markus. Parts designed and machine shop. Vacuum parts<br />

found – some need testing (see 175). Need to order 8020 parts: goes<br />

out with stuff <strong>for</strong> Christian <strong>for</strong> cart (4/24/09). Assembled (5/5/09).<br />

Vacuum test needed. Vacuum is fine (7/14/09)<br />

167 Rail <strong>for</strong> phosphor screen needs makeover Totti took it out of the<br />

chamber and brought it to the machine shop. Rene is on it 3/30/09.<br />

Totti fi(l)ne tuned the rail system and did a first adjustment. Should<br />

work a little better now. Totti noticed th<strong>at</strong> the black handle <strong>at</strong> the end<br />

got loose a little bit and tighten it again using both little setscrews<br />

(weak point)…<br />

168 One more layer of phosphor on the glasses would be nice Totti +<br />

David. More tests in the meantime shows th<strong>at</strong> it works the way it is <strong>for</strong><br />

now<br />

169 SAFETY: CSD guest procedure, Gasmanifold, JHA, AHD, OJT,<br />

Emergency Shutdown <strong>List</strong> have to be in place Totti (is in contact with<br />

Tracey Bigelow from HR; goes very slowly). Looks like EID can be<br />

issued perhaps 2 to 3 weeks in advance. PGI <strong>for</strong>m has to be filled out<br />

be<strong>for</strong>e by every guest by all means 4/14/09. W<strong>at</strong>ch out: There is a<br />

new PGI <strong>for</strong>m (un<strong>for</strong>tun<strong>at</strong>ely write protected). Because of th<strong>at</strong> and a<br />

missing internet interface <strong>at</strong> CSD we go via ALS again. We added a<br />

new AHD like document <strong>for</strong> people to read be<strong>for</strong>e they work with the<br />

<strong>COLTRIMS</strong> appar<strong>at</strong>us. The <strong>LBNL</strong> JHA system will face an overhaul<br />

within 6 to 12 months. We have to wait <strong>for</strong> this outcome.<br />

170 Apertures insets <strong>for</strong> slits in chamber needed Markus made one.<br />

Daniel may makes a better version (no not really).<br />

171 Program <strong>for</strong> autom<strong>at</strong>ic Backup (like FileSync) is needed Christian<br />

installed it. It should be implemented in the red background box. Totti<br />

put something together <strong>for</strong> coltrims/lbl and local account…<br />

172 Spectrometer simul<strong>at</strong>ions <strong>for</strong> He experiment Markus is on it. Done:<br />

Total spectrometer length 1.5 m<br />

173 SAFETY: Noise exposure in labs 102 and 104. Totti is in contact with<br />

Herb Toor and Rich Mc Clure from facilities <strong>for</strong> tests (Herb will show<br />

up in 104 Mar. 23; <strong>for</strong> 102 we have to give him a holler once the<br />

appar<strong>at</strong>us is running again). According to Herb: no probs (72 to 77db)<br />

in 104 and 106. Herb stopped by July 14, 09 to check the noise level<br />

in 102. It came out to 79db, which is no problem.<br />

Herb measured the compressed air nozzles (9/24/09). The have<br />

100dB – thus hearing protection is highly recommended. Totti put<br />

warning signs in the three labs.<br />

7/14/2009<br />

3/31/2009<br />

6/17/2010<br />

7/10/2009<br />

8/1/2009<br />

3/30/2009<br />

4/12/2009<br />

7/14/2009<br />

9/24/2009<br />

17


174 Get quote <strong>for</strong> modifying CF200 pipe by adding 2x CF35 flanges (77<br />

machine shop). Markus: 1000 $. Different solution found (see 175).<br />

175 Check recycled vacuum parts (bello and CF200 spool) <strong>for</strong> recoil ion<br />

spectrometer arm with Frank Zucca. Markus. Equipment is <strong>at</strong> pl<strong>at</strong>ing<br />

shop <strong>for</strong> UHV cleaning (4/21/09). With Frank <strong>for</strong> UHV test (4/24/09). 2<br />

out of 3 bellos are okay (bad one has label).<br />

176 Get compass to check magnetic field orient<strong>at</strong>ion of Helmholtz coils.<br />

Markus. Ordered <strong>at</strong> McMaster; arrived – is in toolbox<br />

177 SAFETY: New Controller Cart needs seismic safety <strong>at</strong> least <strong>for</strong> 102.<br />

Totti made drawings <strong>for</strong> the 8020 feet like <strong>at</strong> the chamber and gave<br />

them to Ken Shiler (5/28/09) – done (6/9/09). We need a unistrut bar<br />

and two long threaded rods <strong>for</strong> the ALS. Totti found unistrut bar and<br />

rods + nuts and washers (5/28/09). Bar and Rod need to be cut. Totti<br />

cut everything and assembled a bracket and labeled it (5/29/09).<br />

Christian needs to <strong>at</strong>tach 8020 brackets <strong>for</strong> <strong>at</strong>taching a chain (see 6):<br />

Did it (6/4/09). Totti found chain and quick connectors as well as<br />

shackles and bolted on some 8020 brackets: Might work – need<br />

second opinion (6/3/09). New McMaster feet and threaded rods have<br />

to be ordered – done and installed (6/18/09). Brackets are ready to be<br />

drilled to the floor – need to know position first (have to wait on<br />

Markus and Christian). Totti is in contact with Fred Angliss and James<br />

Mankini. Fred Angliss approved 3/8" Hilti HIS inserts with RE-500<br />

epoxy and 3/8" A193 grade B7 threaded rods installed with a hammer<br />

drill and carbide bit in accordance with ICC ESR-2322 (see<br />

http://www.icc-es.org/reports/pdf_files/ICC-ES/ESR-2322.pdf) and<br />

special inspection during install<strong>at</strong>ion. Contact Johnny Johnson x5371<br />

to schedule the inspection. Position <strong>for</strong> cart found and marked. New<br />

floor scanning is needed (HIS inserts go 5 in deep) – done 9/10/09.<br />

Monroe Thomas asked <strong>for</strong> Drill Permit. Monroe also has the epoxy<br />

glue which is needed <strong>for</strong> the HIS inserts (9/17/09). Everything drilled<br />

and glued 9/24/09. Totti and Rene drilled 0.5in holes in the brackets –<br />

everything fits.<br />

178 SAFETY: Totti got copper grounding pl<strong>at</strong>e from Steve Cooper <strong>for</strong> the<br />

new controller cart (7/14/09). Christian will get screws and mount it:<br />

Done. Diaphragm pumps need good grounding cable: Done. Strain<br />

relief on one pump and plug on the other one have to be fixed: Still<br />

has to go to Steve Cooper. Christian brought both pumps to Steve<br />

(8/20/09). Totti got them and reinstalled them in the cart.<br />

4/20/2009<br />

4/24/2009<br />

4/15/2009<br />

9/25/2009<br />

8/31/2009<br />

End of 2-Bunch-Run 8/2009<br />

18


179 (8/2/09) Ion getter pump <strong>at</strong> BL 11 has to be moved out of the way.<br />

Talk to Hendrik. Totti + Markus + Support<br />

9/29/09 Remind Hendrik again end of November, begin December<br />

(Shutdown in December). Totti writes email to Hendrik & Tolek<br />

10/28/09. Did it: got positive reply on this.<br />

12/07/09 Ion getter pump will not be moved away, but whole chamber<br />

disconnected from beamline. Center pipe will also be dismounted.<br />

180 (8/2/09) BL 11 needs glass valve <strong>for</strong> speeding up alignment process.<br />

Talk to Hendrik. Totti + Markus + Support. Bruce Rude has thicker<br />

glass window <strong>for</strong> VAT g<strong>at</strong>e valve to comply with safety standard. Tony<br />

Warwick has to be contacted and involved <strong>for</strong> the safety issues <strong>at</strong> the<br />

ALS. Totti spoke to Tony and Jim Floyd: No radi<strong>at</strong>ion problem just<br />

mechanical stability. Bruce Rude can give us the right window (he<br />

also has the tool to mount it). Totti writes email to Hendrik & Tolek<br />

10/28/09. Did it: got neg<strong>at</strong>ive reply on this. Wh<strong>at</strong> now ?<br />

= moved down<br />

181 (8/3/09) the new Helmholtz coils need two separ<strong>at</strong>e w<strong>at</strong>erlines to be<br />

reserved <strong>at</strong> BL 11. Talk to Hendrik. Totti + Markus + Support. Markus<br />

let w<strong>at</strong>erlines hanging <strong>at</strong> BL. Totti put remark on beamtime<br />

prepar<strong>at</strong>ion list (8/25/09):<br />

http://amo-csd.lbl.gov/downloads/Checklist%20<strong>for</strong>%20Beamtime.pdf<br />

182 (8/2/09) New Helmholtz coils need fix<strong>at</strong>ions: 8020 clamp on top and<br />

8020 (with brackets) <strong>at</strong> chamber frame (left and right post). Totti +<br />

Markus. 8020 brackets determined to be 5.5in long. Totti found 8020<br />

m<strong>at</strong>erial, cut it and mounted the pieces. We need to order brackets<br />

and plastic end caps from 8020 plus more Velcro straps from<br />

McMasters… (8/26/09). Totti orders from 8020. Markus orders from<br />

McMaster (9/10/09). 8020 arrived 9/19/09. Totti put plastic caps +<br />

brackets + velcro on 9/23/09. Test mount 8/25/09: works<br />

12/07/2009<br />

8/25/2009<br />

9/23/2009<br />

19


183 (8/2/09) New Helmholtz coils need makeover: Connectors, tie raps, …<br />

8020 arms need en<strong>for</strong>cement on the top part. Totti cut the w<strong>at</strong>er<br />

hoses short. Totti ordered some 8020 stuff – 9/10/09. 8020 stuff<br />

arrived and Totti put brackets on arms (not recommended to open)<br />

9/18/09. Totti cut plastic hose and put the screws on the Coils. Totti<br />

flipped the 8 Alu brackets to reverse up and down 9/21/09. Arms and<br />

coils were aligned and test-mounted 9/23/09. Totti and Markus put<br />

sleeve (McMaster 1459T17) around the power supply cables 9/24/09.<br />

6 feet are missing. Markus orders more… W<strong>at</strong>er hoses were cut short<br />

9/30/09. SAFETY: Need new cover (Totti got rid of the sharp edges of<br />

the interim cover). More sleeve arrived and Totti put it + low profile tie<br />

wraps + yellow tape on the cables <strong>at</strong> the power supply and the coils.<br />

Totti fixed the loose clamps on one coil 10/6/09. Markus designed<br />

cover and ordered m<strong>at</strong>erial; stuff is with Ken Shiler. Totti got parts and<br />

gave it a shot – doesn’t fit; brought it back to Ken Shiler. 10/28/09<br />

Covers are back. Totti found screws and assembled everything. Fits,<br />

but we need to close the big holes on the bottom. (Old covers are kept<br />

as spares in storage 2). Totti came up with sketch. With Ken Shiler<br />

10/29/09. Cover is done and fits 11/10/09<br />

184 (8/2/09) New controller cart should have rot<strong>at</strong>able wheels on backside<br />

too <strong>for</strong> better maneuverability. Markus will order from McMaster<br />

(30305T811); ordered 8/24/09. Wheels arrived and Totti mounted<br />

them 8/26/09.<br />

185 (8/2/09) 70l turbo pump (Alc<strong>at</strong>el) needs new place/mount <strong>at</strong> chamber<br />

frame (8020). Totti came up with idea and brought sketch + turbo +<br />

8020 (60x60) to Ken Shiler (8/26/09). Parts done 9/17/09. Totti got<br />

them and installed everything on <strong>COLTRIMS</strong> frame. Shorter KF25<br />

hose + curve and longer KF40 hose needed. Totti got everything and<br />

installed it.<br />

115 (8/2/09) Oil change <strong>for</strong> turbo pumps after beamtime (also the big<br />

guy?): Totti. Ordered <strong>for</strong> the 4 small turbo pumps (8/20/09) – the big<br />

guy looks ok, but second opinion is needed. Arrived 9/3/09. Installed<br />

by Totti (9/8/09).<br />

186 (8/2/09) Grounding pl<strong>at</strong>e on one side of the frame has to be moved to<br />

the other corner. Longer grounding cable desirable. Put back the<br />

grounding cable borrowed from MISTERS. Markus (8/26/09). Totti<br />

removed the grounding pl<strong>at</strong>e from inappropri<strong>at</strong>e position (pushed<br />

upwards and flipped to the inside) – 8/32/09.<br />

187 SAFETY: (8/2/09) more and longer plastic exhaust hoses are needed<br />

(order <strong>for</strong> MISTERS as well). Markus. Ordered. Arrived 3/9/09. Totti<br />

cut it and installed KF flanges.<br />

11/10/2009<br />

8/26/2009<br />

9/17/2009<br />

9/8/2009<br />

8/26/2009<br />

8/31/2009<br />

9/4/2009<br />

20


188 (8/2/09) labels are missing: @ mult. outlets of the controller cart and<br />

NIM rack (“Requires separ<strong>at</strong>e Fuse”); @ fan in controller cart (“start<br />

fan be<strong>for</strong>e switching on the controllers”) and fans in NIM rack. Totti did<br />

it (8/24/09).<br />

189 (8/4/09) Bring back Alc<strong>at</strong>el turbo pump to Frank Zucca after run.<br />

Markus<br />

190 (8/13/09) Transport<strong>at</strong>ion cart <strong>for</strong> new Helmholtz Coils needed. Markus<br />

put it together. Needs some more parts - Ken Shiler is on it (9/3/09).<br />

Markus put it together 9/23/09.<br />

191 (8/15/09) All cables (Lemo, BNC, SHV, controller cables) need check<br />

<strong>for</strong> bad shielding etc.<br />

=> moved down<br />

192 (8/15/09) Storage and Backup solution needed <strong>for</strong> analysis and<br />

backup PC’s (+ Server). Totti found “StarTech.com 3.5in Silver 4<br />

Drive eSATA Multi Raid External Hard Drive Encl.” in eBuy (CDW-G).<br />

Will order 2 of them after input from Frankfurt experts (Till + Jan).<br />

Ordered two towers (incl. controller card) plus one additional controller<br />

card (8/24/09)<br />

Parts: StarTech.com 3.5in Silver 4 Drive eSATA Multi RAID External<br />

Hard Drive Encl, Mfg. Part: SAT3540ER, CDW Part: 1584610,<br />

UNSPSC: 43201802, Hard drive array - 4 bays ( SATA-300 ) - 0 x HD<br />

- Serial ATA-300 (external), $226.00<br />

1 Port PCI Express es<strong>at</strong>a II controller card, StarTech.com ID:<br />

PEXESATA1, $23<br />

Stuff arrived and has been tested (9/4/09). Works fine <strong>for</strong> the most<br />

part. The SiI Manager software on the computer with the non original<br />

controller cart did not see the storage tower device. Totti called<br />

startech and fixed it (see below).<br />

If there is trouble with the non original controller card and “SiI<br />

Manager 4726” software download the l<strong>at</strong>est software from<br />

http://www.startech.com/. Search <strong>for</strong> Product “SAT3540ER” on the<br />

upper right hand of the webpage, download and unzip. Deinstall old<br />

drivers and manager software. Reboot. Then go “start”, “settings”,<br />

“control panel”, “add new hardware” and browse <strong>for</strong> the new “*.inf” file<br />

of the download while installing the driver. Then install new manager.<br />

There is a folder called “SAT3540ER” on the c:\ of TWeber-x09 with<br />

the files. (controller card can stay installed in the computer while doing<br />

all th<strong>at</strong>). [Altern<strong>at</strong>ive suggested by Startech support: PEXESATA2 as<br />

controller card instead of PEXESTA1; it runs the Sil3132.]<br />

8/26/2009<br />

9/23/2009<br />

9/04/2009<br />

21


193 SAFETY: (8/31/09) Electrical Inventory Inspection (Steve Chow et al.)<br />

• HP Duo Power Supply (<strong>for</strong> rainbow coils) needs strain relief in<br />

the back. EI-shop. Totti brought it to EI shop 9/21/09. Done<br />

9/23/09.<br />

• Keithley Voltmeter needs either a handle or a cover <strong>for</strong> the<br />

holes. Totti fixed it 8/31/09.<br />

• Seiko Seiki Turbo Pump Controller needs strain relief <strong>for</strong> AC<br />

power. Totti did it 8/31/09.<br />

• Belkacem power supply needs new terminal, fuse box, and AC<br />

power cover. EI-shop. Totti brought it to EI shop 9/23/09. Done<br />

9/23/09.<br />

• Variag needs new powercord. EI-shop. Totti brought it to EI<br />

shop 9/21/09. Done 9/23/09.<br />

• Small NIM bin needs powercord to be cut and hole closed. Totti<br />

did it 8/31/09.<br />

• Ion gauge cable has no strain relief. Totti fixed it 8/31/09.<br />

• Turbo pump controller cable has broken strain relief. Totti fixed<br />

it 8/31/09.<br />

• Thermovac controller cables have no strain relief. Totti fixed it<br />

8/31/09.<br />

• Nim Fan AC cord is frayed. EI-shop. Totti brought it to EI shop<br />

9/21/09. Done 9/23/09.<br />

• PicoAmp Meter needs new AC power cord. EI-shop. Totti<br />

brought it to EI shop 9/23/09. Done 11/16/09<br />

• MH Prior power supply has two prong AC power cable. Needs<br />

replacement. EI-shop. Totti brought it to EI shop 9/21/09. Done<br />

9/23/09.<br />

• Broken He<strong>at</strong>ing tapes. EI-shop. Totti brought one (new plug) to<br />

EI shop 9/23/09. The other one perhaps can be fixed with a<br />

Luesterklemme ? NO – got fixed with shrink hose (9/29/09)<br />

•<br />

2 Blue Diaphragm pumps need new power cords. Totti brought<br />

them to EI shop 11/12/09. Done 11/17/09<br />

Mike Bell has been contacted. Stacked all the devices in 106 <strong>for</strong> pick<br />

up by some EI shop guy. Have to check back on EI shop. They don’t<br />

pick it up – Totti brings it to EI shop in two loads (see above).<br />

11/17/2009<br />

194 Handle Bars <strong>for</strong> Controller cart would be nice. Totti ordered from 9/30/2009<br />

McMasters 9/29/09. Arrived 9/30/09 and were mounted.<br />

195 Safety (Security): Server Backup Computer needs new power<br />

supply. Totti did it 9/29/09. Server got new hard drives after boot<br />

sector problems 12/22/09.<br />

9/29/2009<br />

12/22/2009<br />

22


196 11/17/09 Fast Lothar NIM CFD’s need test <strong>for</strong> time jitter or walk<br />

problem according to Markus’ analysis. Markus runs test and is in<br />

contact with Lothar – might exchange or repair them over Christmas.<br />

Lothar things it was a bad walk and threshold adjustment. No test<br />

were done.<br />

197 <br />

12/15/09 Look <strong>for</strong> CO and order, also talk to Donna. Markus ordered 2<br />

midsize bottles. Bottle arrived and is outside building 7 (locked).<br />

Bottles labeled<br />

and put in ALS gas storage.<br />

198 12/15/09 Resize Helmholtz cage after moving? May be needs to be a<br />

little bigger. Markus: New Cable/Clamps and Rods are ordered and<br />

arrived. Cage posts need to be further apart + old and new rods need<br />

to be cut + install new cable. 1/7/10 Totti made new stand-offs in<br />

machine shop and mounted them. Exchanged Al rods <strong>at</strong> the vertical<br />

side. New horizontal rods need to be measured, cut and mounted:<br />

Done 1/8/10. Florian and Totti adjusted height (1/20/10). Florian and<br />

Irina installed computer cable. Resistance checked. Should work.<br />

Some cables still need to be fastened to the frame.<br />

199 <br />

12/1/09 CO spectrometer simul<strong>at</strong>ion: Design is almost finished<br />

(12/20/09). Drift tube needs to be cut + tapped holes <strong>for</strong> feet installed.<br />

CF 150-250 Adapter is needed. 8020 support <strong>for</strong> CF250<br />

spool needs<br />

to be built. Check CF250 spool (is out of the dumpster). Markus brings<br />

hexanode and mesh from Frankfurt. Totti borrowed 13 ¼ to 8 in flange<br />

(Frank Zucca) and 13 ¼ to 2 ¾ flange (Eli Rothenburg); a second 13<br />

¼ to 8 in flange would be better – got it from Bruce Rude (1/14/10).<br />

Florian and Markus build spectrometer and fitted it into chamber<br />

(3/10/10)<br />

163 12/1/09 Jet cooling still needs to be put together and tested. Gas inlet<br />

is missing. Glands have to be ordered and welded to new stainless<br />

steel tube – Glands arrived 1/710. Florian brought it to 77 (1/22/10).<br />

Parts came back and were installed. Leak found on nozzle to copper<br />

block connection (insert was tightened). Works but no big<br />

improvement <strong>for</strong> cold jet (-125C <strong>at</strong> Nozzle, -153C <strong>at</strong> Coldtrap Copper<br />

rod, ideal would be -196C).<br />

200 1/19/10 D<strong>at</strong>a acquisition computer crashed with blue screen<br />

and was<br />

unstable after reboot. Totti imaged oper<strong>at</strong>ing system to a new<br />

harddrive with IT service and exchanged SATA cable.<br />

201 1/26/10 Connectors <strong>for</strong> 12pin feedthrough (anode) and perhaps <strong>for</strong><br />

SHV feedthroughs are needed. Florian found pins <strong>at</strong> http://www.multicontact-usa.com<br />

– part-number 41.6000, type B1-TH (1/26/10).<br />

Orderd and arrived. Florian made new cables<br />

20/12/2009<br />

2/11/2010<br />

3/12/2010<br />

3/10/2010<br />

2/17/10<br />

1/20/10<br />

2/5/2010<br />

23


202 SAFETY: (2/17/10) Jet cold trap sends condens<strong>at</strong>e w<strong>at</strong>er on rainbow<br />

coils, Helmholtz coils, floor and perhaps a pump if loc<strong>at</strong>ed<br />

underne<strong>at</strong>h. Foam or w<strong>at</strong>er collector is needed. Markus ordered three<br />

sponges and some absorbent m<strong>at</strong>erial (3/5/10) . Test needed.<br />

Absorbent m<strong>at</strong>erial didn’t help much. Totti installed some sponges.<br />

Test needed (4/2/10)<br />

203 <br />

New spectrometer pl<strong>at</strong>es m<strong>at</strong>e from phosphor bronze – ordered <strong>at</strong><br />

McMaster. They were supposed to be fl<strong>at</strong> (not from a coil), but have<br />

still been curved too much. Even with putting <strong>for</strong>ce on the mounted<br />

spectrometer stack, the<br />

distance between two pl<strong>at</strong>es can exceed 30<br />

%. -> Don’t take phosphor bronze from McMaster <strong>for</strong><br />

spectrometer pl<strong>at</strong>es!!! Markus<br />

4/2/2010<br />

2/26/2010<br />

204 (3/9/10) Allen and Markus gave feedback about drifting and jumping<br />

spectrometer voltage: Totti ordered two Stand<strong>for</strong>d PS325 and a<br />

rackmount (3/9/10)<br />

3/9/2010<br />

115 Oil <strong>for</strong> big turbo pump needed: Markus ordered from Pfeiffer (2/15/10). 6/10/2010<br />

Arrived 3/10/10. Needs to be filled in… Done 6/10/10<br />

End of 2-Bunch-Run 4/2010<br />

24

Hooray! Your file is uploaded and ready to be published.

Saved successfully!

Ooh no, something went wrong!