SRK Consulting<br />
<strong>Staatsolie</strong> Refinery Draft EIA Report: Non-technical Summary Page xii<br />
# Impact Significance rating Key mitigation/optimisation measures<br />
WR4<br />
WR5<br />
TE1<br />
Potential contamination of the Suriname<br />
River through a large, uncontrolled<br />
release of pollutants during the<br />
operations phase.<br />
Potential contamination of groundwater<br />
resources<br />
Potential contamination of vegetation /<br />
habitat<br />
Before mitigation/<br />
optimisation<br />
After mitigation/<br />
optimisation<br />
Low Very Low<br />
Low Insignificant<br />
Low Very Low<br />
TE2 Potential impact on terrestrial fauna. Very Low Very Low<br />
AE1<br />
AE2<br />
Potential loss of aquatic diversity due to<br />
increased sedimentation / turbidity during<br />
the construction phase<br />
Potential loss of aquatic diversity due to<br />
toxicological effects as result of small<br />
continuous releases of pollutants<br />
Potential loss of aquatic diversity due to<br />
toxicological effects as result of large,<br />
accidental release of pollutants<br />
Ensure adequate spill response measures are included in the Emergency Response Plan.<br />
Ensure adequate spill containment and response equipment are available, including oil booms and oil<br />
spill dispersants.<br />
Regularly maintain all equipment to prevent failures of pipelines, etc.<br />
Ensure all on site staff are trained in the requirements of the Emergency Response Plan and in the use of<br />
spill containment and response equipment.<br />
Ensure all safety precautions are taken during loading and off-loading of potential contaminants.<br />
Develop (or maintain and adapt) procedures for the safe transport, handling and storage of potential<br />
pollutants.<br />
Locate hazardous material storage facilities, especially fuel storage, as far as practically possible from<br />
the Suriname River.<br />
Design and construct hazardous material storage facilities with suitable impermeable materials and a<br />
minimum 110% containment capacity.<br />
Ensure all on site staff are trained in the use of spill prevention measures.<br />
Clean up any spills immediately, through containment and removal of free product and appropriate<br />
rehabilitation or disposal of contaminated soils.<br />
Implement an ongoing and comprehensive water and effluent quality monitoring programme with<br />
regular reporting of monitoring results to NIMOS.<br />
Limit the footprint of construction activities, including laydown areas.<br />
Implement mitigation measures to reduce the potential impact of soil and water contamination.<br />
Implement mitigation measures to reduce the potential impact on air quality.<br />
Limit the footprint of construction activities, including laydown areas.<br />
Implement mitigation measures to limit the potential contamination of vegetation/habitat.<br />
Implement mitigation measures to minimise noise impacts.<br />
Very Low Very Low Implement mitigation measures to reduce the potential impacts on surface water quality.<br />
Low Very Low Implement mitigation measures to reduce the potential impact of soil and water contamination.<br />
Low Very Low Implement mitigation measures to reduce the potential impact of soil and water contamination.<br />
FOUD/dalc 398251_<strong>Staatsolie</strong>_Draft EIR_Non-technical Summary FINAL.doc November 2009