Facilities Management Workshop<br />

May 14-18, 2005 Toronto, Ontario<br />

Modernizing <strong>Toll</strong> Facilities<br />

<strong>Toll</strong> <strong>Plaza</strong> Reconfiguration / Reconstruction<br />

<strong>Atlantic</strong> <strong>City</strong> <strong><strong>Express</strong>way</strong><br />

<strong>Pleasantville</strong> <strong>Toll</strong> <strong>Plaza</strong><br />

<strong>Express</strong> E-Z <strong>Pass</strong> Improvements /<br />

Elevated Walkway<br />

Presented By:<br />

STEVEN RENZI<br />

Project Manager – Buildings / Transportation Group<br />

Maguire Group Inc.


Facilities Management Workshop<br />

May 14-18, 2005 Toronto, Ontario<br />

OWNER:<br />

South Jersey Transportation Authority<br />

Hammonton, NJ<br />

PROJECT:<br />

<strong>Atlantic</strong> <strong>City</strong> <strong><strong>Express</strong>way</strong><br />

<strong>Pleasantville</strong> <strong>Toll</strong> <strong>Plaza</strong><br />

Phase 1 - <strong>Express</strong> E-Z <strong>Pass</strong> Improvements<br />

Phase 2 - Elevated Walkway<br />

SPEAKER:<br />

STEVEN A. RENZI<br />

Project Manager<br />

Maguire Group Inc.<br />

Engineers / Planners<br />

Lawrenceville, NJ


Facilities Management Workshop<br />

May 14-18, 2005 Toronto, Ontario<br />

AGENDA<br />

Overview – South Jersey Transportation Authority<br />

History – <strong>Pleasantville</strong> <strong>Toll</strong> <strong>Plaza</strong><br />

Project Design / Construction Issues<br />

Phase 1 – <strong>Express</strong> E-Z E Z <strong>Pass</strong> Improvements<br />

Phase 2 - Elevated Walkway<br />

Question / Answer Period


Facilities Management Workshop<br />

May 14-18, 2005 Toronto, Ontario<br />

South Jersey Transportation Authority<br />

State Authority created in 1991, as successor to New Jersey <strong><strong>Express</strong>way</strong><br />

Authority & <strong>Atlantic</strong> County Transportation Authority<br />

Authority, known as “SJTA”, operates and coordinates Southern NJ’s<br />

Transportation System - highway network, aviation facilities, & transportation<br />

problems of <strong>Atlantic</strong> County.<br />

One major component is <strong>Atlantic</strong> <strong>City</strong> <strong><strong>Express</strong>way</strong> - 44 mile long toll road,<br />

starts 10 miles east of Philadelphia, PA into <strong>Atlantic</strong> <strong>City</strong>, NJ - opened for traffic<br />

in stages in 1964 & 1965.<br />

13 Interchanges provide access to major arterial routes, including Garden<br />

State Parkway, & 7 toll plazas control toll revenue collections.<br />

Second major component is <strong>Atlantic</strong> <strong>City</strong> Airport, approx. 5,000 acres in<br />

size & located near Interchange 9 of <strong><strong>Express</strong>way</strong>, 10 miles northwest of A.C.<br />

Principal focus of Authority: Utilize Transportation Facilities to stimulate<br />

Economic Development throughout Southern New Jersey.


Facilities Management Workshop<br />

May 14-18, 2005 Toronto, Ontario<br />

<strong>Pleasantville</strong> <strong>Toll</strong> <strong>Plaza</strong><br />

History<br />

1965 – <strong>Plaza</strong> first opened; Located directly outside of <strong>Atlantic</strong> <strong>City</strong> –<br />

6 <strong>Toll</strong> Lanes – Fare was $ .25 cents<br />

1978 – 2 Lanes Added; 1 each direction - 8 Total Lanes<br />

1981 – 4 Lanes Added; 2 each direction - 12 Total Lanes;<br />

Fare still $.25 cents<br />

1997 - E-Z <strong>Pass</strong> Equipment installed<br />

1998 – Fare increases to $.50 cents<br />

2001 – Brigantine Connector Opened & diverted more traffic onto<br />

<strong><strong>Express</strong>way</strong><br />

2003 - Phase 1 – <strong>Express</strong> E-Z <strong>Pass</strong> Construction begins<br />

May 2004 – Phase 1 Complete; 5 Lanes Eastbound / 4 Lanes<br />

Westbound / 4 <strong>Express</strong> E-Z <strong>Pass</strong> Lanes - 13 Total Lanes<br />

October 2004 – Phase 2 – Elevated Walkway Construction starts


Facilities Management Workshop<br />

May 14-18, 2005 Toronto, Ontario<br />

<strong>Pleasantville</strong> <strong>Toll</strong> <strong>Plaza</strong> – Elevated Walkway<br />

Project History – Design Intent<br />

Maguire Group contracted by SJTA in 2001 – to provide A/E services for<br />

elevated bridge to span entire toll plaza<br />

Major Issues to Address :<br />

Safety of toll collectors –<strong>Toll</strong> collectors currently had to cross dedicated E-<br />

Z <strong>Pass</strong> lanes, as well as manual & automated coin lanes to reach collection<br />

booths<br />

Traffic congestion - new elevated walkway would provide safe access for<br />

toll staff & reduce pedestrian traffic thus increasing driving safety


Facilities Management Workshop<br />

May 14-18, 2005 Toronto, Ontario<br />

<strong>Pleasantville</strong> <strong>Toll</strong> <strong>Plaza</strong> – Elevated Walkway<br />

Design Issues / Constraints<br />

Tight Site Constraints - Tidal Wetlands on North side of project -<br />

existing Administration Building & parking Lot on South side.<br />

Existing Electric / Utility Services – Old & outdated, new services &<br />

upgrades needed for new toll plaza facility<br />

<strong>Toll</strong> <strong>Plaza</strong> Operations - design to be phased - toll plaza to remain<br />

operational to collect revenue throughout construction period.<br />

Existing Geotechnical Conditions – subsurface elements -mostly<br />

sandy materials - not allow for tunnel design - Overhead Walkway only<br />

option.<br />

<strong>Toll</strong> Lane Restrictions - Strict <strong>Toll</strong> Lane Occupancy requirements to<br />

be enforced during construction – design to incorporate


Facilities Management Workshop<br />

May 14-18, 2005 Toronto, Ontario<br />

<strong>Pleasantville</strong> <strong>Toll</strong> <strong>Plaza</strong> – Elevated Walkway<br />

Original Design Concepts<br />

New <strong>Toll</strong> <strong>Plaza</strong> Improvements include:<br />

Pre-Engineered Steel Truss Bridge – single span, 240 Ft. L x 14Ft W,<br />

spanning entire toll plaza<br />

2 Structural Towers & Walkway - fully enclosed, complete HVAC systems, fire<br />

protection & plumbing, new electrical / communication systems, & elevators / stairs<br />

for each tower<br />

Walkway Exterior – combination of insulated aluminum panels & insulated glass<br />

panels / curved standing seam metal roof<br />

Tower Exterior – finished concrete panels, glass panel system, and corrugated<br />

metal panels<br />

4 Mechanical Lifts – 2 each direction; located at 4 ACM booths to raise coin<br />

vaults from booth to walkway<br />

New Electric / Power Service & Distribution System - design for entire plaza<br />

New Standby Generator & Associated Work<br />

Decorative Neon / Accent Lighting – located on bridge / tower structures.<br />

New <strong>Toll</strong> Lane, Concrete Island & Booth – located in eastbound direction


Facilities Management Workshop<br />

May 14-18, 2005 Toronto, Ontario<br />

<strong>Pleasantville</strong> <strong>Toll</strong> <strong>Plaza</strong> – Elevated Walkway<br />

Revised Design / Upgrades<br />

October 2002 – NJ Govenor announced $45 Million <strong>Express</strong> E-Z <strong>Pass</strong><br />

Program – to be incorporated at all toll plaza locations throughout NJ<br />

New Design Improvements Include:<br />

<strong>Express</strong> E-Z <strong>Pass</strong> Lanes – 4 Total – 2 each direction, new advanced technology<br />

motorists can drive at speeds of 45 MPH straight through plaza;<br />

Existing toll booths removed; <strong>Express</strong> lanes separated by concrete barrier curbs<br />

New Approach / Overhead Sign Package - Install new toll plaza approach signs;<br />

design to coordinate with other <strong>Express</strong> E-Z <strong>Pass</strong> plaza locations throughout NJ<br />

Overhead Steel Gantry – holds enhanced E-Z <strong>Pass</strong> equipment & cameras,<br />

motorists drive underneath<br />

New Design requires Project Phasing:<br />

Phase 1 – <strong>Express</strong> E-Z <strong>Pass</strong> Improvements<br />

( Started 10 /04 – Completed 5/04 )<br />

Phase 2 - Elevated Walkway<br />

( Started 10 /05 – Completion Scheduled 6/05 )


Facilities Management Workshop<br />

May 14-18, 2005 Toronto, Ontario<br />

<strong>Pleasantville</strong> <strong>Toll</strong> <strong>Plaza</strong><br />

Phase 1 - <strong>Express</strong> E-Z <strong>Pass</strong> Improvements<br />

New <strong>Toll</strong> Lane Construction<br />

NJ Governor – Removal of 1 st <strong>Toll</strong> Booth


Facilities Management Workshop<br />

May 14-18, 2005 Toronto, Ontario<br />

<strong>Pleasantville</strong> <strong>Toll</strong> <strong>Plaza</strong><br />

Phase 1 - <strong>Express</strong> E-Z <strong>Pass</strong> Improvements<br />

Demolition 3 Existing <strong>Toll</strong> Booths<br />

<strong>Express</strong> E-Z E Z <strong>Pass</strong> Lanes -<br />

Construction


Facilities Management Workshop<br />

May 14-18, 2005 Toronto, Ontario<br />

<strong>Pleasantville</strong> <strong>Toll</strong> <strong>Plaza</strong><br />

Phase 1 - <strong>Express</strong> E-Z <strong>Pass</strong> Improvements<br />

<strong>Express</strong> E-Z E Z <strong>Pass</strong> – Concrete Barrier<br />

Construction<br />

<strong>Express</strong> E-Z E Z <strong>Pass</strong> – Steel Gantry


Facilities Management Workshop<br />

May 14-18, 2005 Toronto, Ontario<br />

<strong>Pleasantville</strong> <strong>Toll</strong> <strong>Plaza</strong><br />

Phase 1 - <strong>Express</strong> E-Z <strong>Pass</strong> Improvements<br />

Final Paving / Stripping<br />

<strong>Express</strong> E-Z E Z <strong>Pass</strong><br />

New Overhead Sign Structure


Facilities Management Workshop<br />

May 14-18, 2005 Toronto, Ontario<br />

<strong>Pleasantville</strong> <strong>Toll</strong> <strong>Plaza</strong><br />

Phase 1 - <strong>Express</strong> E-Z <strong>Pass</strong> Improvements<br />

Aerial View – Phase 1 Final Completion


Facilities Management Workshop<br />

May 14-18, 2005 Toronto, Ontario<br />

<strong>Pleasantville</strong> <strong>Toll</strong> <strong>Plaza</strong><br />

Phase 1 - <strong>Express</strong> E-Z <strong>Pass</strong> Improvements<br />

May 6, 2004<br />

NJ Govenor opened first <strong>Express</strong> E-Z <strong>Pass</strong> Lanes in Southern New<br />

Jersey at <strong>Pleasantville</strong> <strong>Toll</strong> <strong>Plaza</strong><br />

Increased number of vehicles handled each hour:<br />

Old dedicated E-Z <strong>Pass</strong> Lanes – 1,200 cars /hr<br />

New <strong>Express</strong> E-Z <strong>Pass</strong> Lanes - 1,800 cars /hr (50% increase)<br />

Entire <strong>Plaza</strong> (Old Configuration) – 8,600 cars /hr<br />

New <strong>Express</strong> <strong>Plaza</strong> Design - 11,700 cars /hr (40% capacity increase)<br />

<strong>Pleasantville</strong> handles approx. 83,000 vehicles daily during peak summer months,<br />

with 65% motorists using E-Z <strong>Pass</strong><br />

Statistics show 90% of motorists choose <strong>Express</strong> Lanes vs. traditional E-Z <strong>Pass</strong><br />

lanes, reducing congestion & alleviating traffic problems / accidents.


Facilities Management Workshop<br />

May 14-18, 2005 Toronto, Ontario<br />

<strong>Pleasantville</strong> <strong>Toll</strong> <strong>Plaza</strong><br />

Phase 2 - Elevated Walkway<br />

Construction – South Tower Foundation<br />

4FT Concrete Thick –Mat Foundation


Facilities Management Workshop<br />

May 14-18, 2005 Toronto, Ontario<br />

<strong>Pleasantville</strong> <strong>Toll</strong> <strong>Plaza</strong><br />

Phase 2 - Elevated Walkway<br />

Formwork – Structural Tower Walls<br />

Pre-Engineered Bridge - On –Site<br />

Erection


Facilities Management Workshop<br />

May 14-18, 2005 Toronto, Ontario<br />

<strong>Pleasantville</strong> <strong>Toll</strong> <strong>Plaza</strong><br />

Phase 2 - Elevated Walkway<br />

April 12, 2005<br />

BRIDGE STRUCTURE SETTING<br />

Overnight Closure - A.C. <strong><strong>Express</strong>way</strong><br />

From 9 PM to 6 AM<br />

Coordination between numerous State Agencies:<br />

SJTA / NJSP / GSP / NJDOT / Local Police Departments<br />

No traffic - In or Out of <strong>Atlantic</strong> <strong>City</strong> / Closed Both Directions<br />

No Accidents Reported / Complete Success


Facilities Management Workshop<br />

May 14-18, 2005 Toronto, Ontario<br />

<strong>Pleasantville</strong> <strong>Toll</strong> <strong>Plaza</strong><br />

Phase 2 - Elevated Walkway<br />

STEP 1:<br />

Bridge Moved Into<br />

<strong>Express</strong> E-Z E Z <strong>Pass</strong><br />

Lane<br />

STEP 2:<br />

550 Ton Crane<br />

Lifting Bridge


Facilities Management Workshop<br />

May 14-18, 2005 Toronto, Ontario<br />

<strong>Pleasantville</strong> <strong>Toll</strong> <strong>Plaza</strong><br />

Phase 2 - Elevated Walkway<br />

STEP 3:<br />

Bridge Lifted Over<br />

Tower Abutments<br />

STEP 4:<br />

Bridge Set On<br />

Tower Abutments


Facilities Management Workshop<br />

May 14-18, 2005 Toronto, Ontario<br />

<strong>Pleasantville</strong> <strong>Toll</strong> <strong>Plaza</strong><br />

Phase 2 - Elevated Walkway<br />

View of Bridge /Towers - Traveling from <strong>Atlantic</strong> <strong>City</strong><br />

View of Bridge /Towers<br />

from Admin. Bldg. Side


Facilities Management Workshop<br />

May 14-18, 2005 Toronto, Ontario<br />

South Jersey Transportation Authority<br />

<strong>Atlantic</strong> <strong>City</strong> <strong><strong>Express</strong>way</strong> - <strong>Pleasantville</strong> <strong>Toll</strong> <strong>Plaza</strong><br />

Phase 1 & 2 Complete<br />

Elevated Walkway – Nighttime Rendering<br />

“GATEWAY INTO ATLANTIC CITY”


Facilities Management Workshop<br />

May 14-18, 2005 Toronto, Ontario<br />

Modernizing <strong>Toll</strong> Facilities<br />

<strong>Toll</strong> <strong>Plaza</strong> Reconfiguration / Reconstruction<br />

<strong>Atlantic</strong> <strong>City</strong> <strong><strong>Express</strong>way</strong><br />

<strong>Pleasantville</strong> <strong>Toll</strong> <strong>Plaza</strong><br />

<strong>Express</strong> E-Z <strong>Pass</strong> Improvements /<br />

Elevated Walkway<br />

Presented By:<br />

STEVEN RENZI<br />

Project Manager – Buildings / Transportation Group<br />

Maguire Group Inc.<br />

P: (609) 912-0860<br />

E-mail: Srenzi@maguiregroup.com<br />

Website: www.MaguireGroup.com


Facilities Management Workshop<br />

May 14-18, 2005 Toronto, Ontario<br />

Overview - Maguire Group Inc.<br />

Leading Full-Service Architectural, Engineering, &<br />

Planning Firm in the Northeast Since 1938<br />

Corporate Office in Foxboro, MA with 11 Branch offices<br />

throughout the North-<strong>Atlantic</strong> Region and Virgin Islands<br />

Over 350 Employees<br />

90% of Business come from Repeat Clients<br />

Winner of Two Presidential Awards for Design Excellence<br />

Transportation Projects comprise approximately 50% of<br />

Annual Sales


Facilities Management Workshop<br />

May 14-18, 2005 Toronto, Ontario<br />

Maguire Group Inc. –<br />

Only A/E Firm to Win Two<br />

Presidential Awards<br />

Charles River Project<br />

Boston, Massachusetts<br />

Waterplace Park<br />

Providence, Rhode Island


Facilities Management Workshop<br />

May 14-18, 2005 Toronto, Ontario<br />

Areas of Expertise!<br />

Architecture<br />

Power<br />

Development &<br />

Environ. Services<br />

Marine<br />

Military<br />

Transportation<br />

Water Resources


Facilities Management Workshop<br />

May 14-18, 2005 Toronto, Ontario<br />

Office Locations<br />

Portland, Maine<br />

Portsmouth, New Hampshire<br />

Headquarters<br />

Foxborough, Massachusetts<br />

Providence, RI<br />

New Britain, Connecticut<br />

State College, PA<br />

Harrisburg, PA<br />

Philadelphia, PA<br />

Pittsburgh, PA<br />

Lawrenceville, New Jersey<br />

<strong>Atlantic</strong> <strong>City</strong>, New Jersey


Facilities Management Workshop<br />

May 14-18, 2005 Toronto, Ontario<br />

The Maguire Group Structure<br />

Business Units<br />

<br />

<br />

Buildings Group<br />

- Military Design Services<br />

- Architectural Design & Design /Build Services<br />

- Structural /Mechanical /Electrical /Plumbing Services<br />

-- Project Management Services<br />

Civil Works Group<br />

- Water Resources / Port Marine<br />

- Site Development & Environmental Design Services<br />

<br />

Transportation Group<br />

- Highway/Roadway/Bridge Design<br />

- Construction Administration/Management/Inspection Services


Facilities Management Workshop<br />

May 14-18, 2005 Toronto, Ontario<br />

Transportation Group<br />

Boston Central Artery and Tunnel<br />

Project<br />

Boston, MA<br />

Highway /Bridge /Tunnel Design<br />

Waterplace Park, Providence, RI<br />

Presidential Design Award Winner<br />

I -195 Project - Providence,<br />

RI<br />

Highway & Bridge Design<br />

Construction Inspection / Project Management<br />

Amos K. Hutchinson Bypass“<strong>Toll</strong><br />

66”<br />

Westmoreland County, PA