6.2 ACTIVITY PRA2: SET THE IMMD SCOPE<br />
INTRODUCTION<br />
This activity determines the boundaries of the IMMD based on<br />
requirements and constraints (schedule, funding, logistics, etc.).<br />
The scope defines the extent, or range, of the IMC to be included in<br />
this IMMD. The scope is framed around the mission or goals of the<br />
IMC and the requirements of the IMMD. The scope sets the context<br />
for all data collection, analysis, and planning activities. For example,<br />
some groups or process functions may be eliminated from the analysis<br />
due to schedule or contractual constraints. This activity is also used to<br />
collect information (if possible) from stakeholders related to the IMC’s<br />
success criteria. Stakeholders will usually have some opinion as to<br />
what constitutes success for this IMC. This information is used later to<br />
establish the IMC’s success threshold 13 .<br />
WHAT IS SCOPE?<br />
The scope of the IMMD essentially defines how much of the IMC is to<br />
be included. For example:<br />
• The IMMD could be limited to only the group of people officially<br />
designated as the incident response team or CSIRT<br />
• Contractors or service providers may be excluded or included<br />
• One of the incident management functions, such as Protect, could<br />
be excluded<br />
• Specific groups in the organization that would be difficult or timeconsuming<br />
to include, such as remotely located groups or groups<br />
within secure facilities that the analysis team cannot access, could<br />
be excluded<br />
OBJECTIVES<br />
This activity answers the following question:<br />
• What is the scope of the IMMD?<br />
The main objectives of this activity are to set the scope of the IMMD<br />
and to gather stakeholder input on the IMC’s success threshold.<br />
13 Note that the success threshold could be set here or later, but it must be set no later than in activity A5 Establish<br />
the IMC success profile.<br />
28 | CMU/SEI-2008-TR-007