Schedule -2: Form of Agreement<br />

6.1.1 An abstract of the cost of the Services payable to the Consultant is set forth in<br />

Annex-5 of the Agreement.<br />

6.1.2 Except as may be otherwise agreed under Clause 2.6 and subject to Clauses<br />

4.2.2 and 6.1.3, the payments under this Agreement shall not exceed the<br />

agreement value specified herein (the “Agreement Value”). The Parties agree<br />

that the Agreement Value is Rs. ………. ( Rupees …………………….),<br />

which does not include the Additional Costs specified in Annex-5 (the<br />

“Additional Costs”).<br />

6.1.3 Notwithstanding anything to the contrary contained in Clause 6.1.2, if<br />

pursuant to the provisions of Clauses 2.6 and 2.7, the Parties agree that<br />

additional payments shall be made to the Consultant in order to cover any<br />

additional expenditures not envisaged in the cost estimates referred to in<br />

Clause 6.1.1 above, the Agreement Value set forth in Clause 6.1.2 above shall<br />

be increased by the amount or amounts, as the case may be, of any such<br />

additional payments.<br />

6.2 Currency of payment<br />

All payments shall be made in Indian Rupees. The Consultant shall be free to<br />

convert Rupees into any foreign currency as per Applicable Laws.<br />

6.3 Mode of billing and payment<br />

Billing and payments in respect of the Services shall be made as follows:-<br />

(a)<br />

(b)<br />

The Consultant shall be paid for its services as per the Payment<br />

Schedule at Annex-6 of this Agreement, and Clauses 5.2 and 5.3 of the<br />

TOR, and the rates specified in Annex-4 of this Agreement, subject to<br />

the Consultant fulfilling the following conditions:<br />

(i)<br />

No payment shall be due for the next stage till the Consultant<br />

completes to the satisfaction of the Authority the work pertaining<br />

to the preceding stage. Provided, however, that for the Deliverables<br />

specified at KD7 and KD8 in Clause 5.2 of the TOR, payment shall<br />

be due and payable by the Authority for the man hours spent during<br />

each calendar month;<br />

(ii) The Authority shall pay to the Consultant, only the undisputed<br />

amount.<br />

The Authority shall cause the payment due to the Consultant to be made<br />

within 30 (thirty) days after the receipt by the Authority of duly<br />

completed bills with necessary particulars (the “Due Date”). Interest at<br />

the rate of 10% (ten per cent) per annum shall become payable by the<br />

Authority as from the Due Date on any amount due by, but not paid on<br />

or before, such Due Date.<br />

(c ) The final payment under this Clause 6.3 shall be made only after the<br />

final Deliverable shall have been submitted by the Consultant and<br />

RFP for Financial Consultant: <strong>Hyderabad</strong> <strong>Metro</strong> <strong>Rail</strong> (MRTS) Project 70