KUFPEC intends to develop the WA-356-P gas reserves<br />
through the Wheatstone LNG project. Several<br />
project milestones and key elements were<br />
achieved during 2010 in preparation for the Final<br />
Investment Decision into the Wheatstone LNG<br />
hub which will be operated by Chevron.<br />
Serveral Wheatstone LNG Project Agreements<br />
were signed at a ceremony that took place 9th December<br />
in Perth.<br />
In 2010, several LNG purchasers commenced due<br />
Yacheng Field<br />
(KUFPEC: 14.7%)<br />
KUFPEC net production during 2010 was 7,179<br />
boepd compared to 6,369 boepd in 2009. Increased<br />
production was due to offtaker demand.<br />
4 additional wells were drilled in 2010 to maintain<br />
production levels. Negotiations were also completed<br />
with CNOOC regarding the Y13-4 and Y13-<br />
6 tie-in to Yacheng Field platform. This will allow<br />
CNOOC to increase its production from the surdiligence<br />
and negotiations on LNG Sales and<br />
Equity Purchase with the WA-356 Joint Venturers.<br />
As a result of this, a number of Heads of<br />
Agreements have been finalized and signed.<br />
LNG Sales and Equity Purchase meetings will<br />
continue with LNG off-takers in 2011.<br />
To comply with State regulations, the Wheatstone<br />
Environmental Impact Study was released<br />
for public comment in late 2010. In 2010 also<br />
witnessed the signature of Wheatstone Native<br />
Title Agreements.<br />
WA-191-P<br />
(KUFPEC: 33.4%)<br />
The exploration well Finucane South-1 is scheduled<br />
for drilling in mid 2011. This well will delineate<br />
additional possible reserves which will form<br />
WA-335-P<br />
(KUFPEC: 24.5%)<br />
This Permit was partially farmed-out to BHP in<br />
2009. As part of the farm-out agreement, BHP ac-<br />
PHILIPPINES<br />
SC-60<br />
(KUFPEC: 30%)<br />
The exploration well Silangan-1ST was drilled in<br />
Q3 2010. It failed to discover hydrocarbons. Operator,<br />
Shell Philippines, acquired a CSEM (Con-<br />
China<br />
the basis of a joint development of the Fletcher<br />
oil discovery. If successful, the development<br />
project may be tied-back to Mutineer-Exeter<br />
Field.<br />
quired a new 3D seismic survey 2010. A decision<br />
will be made in 2011 whether to drill a well.<br />
trolled Source Electromagnetic Survey) in late<br />
2010 to be evaluated in 2011 for the remaining<br />
potential on the block.<br />
rounding area and for Yacheng Joint Venture<br />
Partners to receive tariffs for facility utilization.<br />
A liquid gas manufacturing facility was constructed<br />
during 2010 on Hainan Island and the<br />
LPG sale contract concluded, with the first cargo<br />
scheduled for the first half of 2011.<br />