Operation<br />
De-energize/Shutdown<br />
WARNING: Lethal Voltage<br />
Review the system configuration to identify all possible sources of energy.<br />
Ensure ALL sources of power are disconnected before performing any<br />
installation or maintenance on this equipment. Confirm that the terminals are<br />
de-energized using a validated voltmeter (rated for a minimum 1000 Vac and<br />
1000 Vdc) to verify the de-energized condition.<br />
WARNING: Burn Hazard<br />
Internal parts can become hot during operation. Do not remove the cover<br />
during operation or touch any internal parts. Be sure to allow them sufficient<br />
time to cool down before attempting to perform any maintenance.<br />
2<br />
1. Open the PV Breakers. 1<br />
2. Open the AC Breakers. 2<br />
A<br />
3. Open the DC Breaker for the Battery.<br />
4. Using a digital volt-meter, verify 0 Vdc on the<br />
Battery terminals of the Inverter<br />
(i.e., place voltmeter leads on and in<br />
Figure 34 on page 47).<br />
5. Using a digital volt-meter, verify 0 Vdc on the<br />
PV terminal<br />
(i.e., place voltmeter leads on and<br />
in Figure 34 on page 47).<br />
6. Using a digital volt-meter, verify 0 Vac on the<br />
AC Breakers<br />
(i.e., Place voltmeter leads on 6+ and 6– in<br />
Figure 34 on page 47).<br />
1<br />
3<br />
A<br />
Outlets are model-dependent.<br />
120 V systems will have a 120V outlet,<br />
230 V <strong>Systems</strong> will have a 230 V outlet.<br />
Figure 33<br />
Shutdown Procedures<br />
46 900-0095-01-00 Rev A