05 50 00 – METAL FABRICATIONS<br />

October 5, 2012<br />

d. Failure of connections.<br />

e. Other detrimental effects.<br />

f. Base engineering calculation on surface temperatures of materials due to both solar heat<br />

gain and nighttime-sky heat loss.<br />

F. Environmental Characteristics:<br />

1. Where choice exists, use pourable products, adhesives, and finishes that have no formaldehyde<br />

content, are water-based rather than solvent-based, and are certified to not off-gas.<br />

2. Use interior opaque topcoat paints that comply with VOC limits and chemical component<br />

restrictions of Green Seal Standard GS-11.<br />

3. At minimum, select materials that comply with Code of Federal Regulations Chapter 40, articles<br />

59.400 – 59.413 governing V.O.C. emissions for architectural coatings.<br />

4. Where choice exists, use composite products that contain highest possible percentage of recycled<br />

material.<br />

5. Where choice exists, obtain products from manufacturers closest to <strong>Project</strong> Site.<br />

1.3 SUBMITTALS<br />

A. Product Data: For the following:<br />

1. Paint products.<br />

2. Grout.<br />

3. Provide documentation of VOC content of all adhesives, sealants, primers, and paints.<br />

B. Shop Drawings:<br />

1. Detail fabrication and erection of each metal fabrication indicated.<br />

2. Include plans, elevations, sections, and details of metal fabrications and their connections.<br />

3. Show anchorage and accessory items.<br />

4. Provide templates for anchors and bolts specified for installation under other Sections.<br />

5. For metal fabrications indicated in Performance Requirements article above to comply with design<br />

loads, include structural analysis data signed and sealed by the professional engineer licensed in<br />

Oregon responsible for their preparation.<br />

C. Samples for Initial Selection:<br />

1. Handrail Bracket:<br />

a. Selection of units resembling brackets represented generically in Drawings, suitable to<br />

substrates and installation conditions, and of metals indicated or, if not indicated, as<br />

directed by Architect.<br />

2. Powder-coating color chart, including colors within range indicated by Architect.<br />

D. Samples for Verification:<br />

1. Handrail Bracket: Full-size unit with finish selected from Samples for Initial Selection..<br />

2. Approved sample in good condition may be installed in final work.<br />

E. Welding Certificates:<br />

1. Copies of certificates for welding procedures and personnel.<br />

F. Qualification Data:<br />

1. For firms and persons specified in "Quality Assurance" Article to demonstrate their capabilities and<br />

experience.<br />

2. Include lists of completed projects with project names and addresses, names and addresses of<br />

architects and owners, and other information specified.<br />

1.4 QUALITY ASSURANCE<br />