01 32 00 - CONSTRUCTION PROGRESS DOCUMENTATION<br />

October 5, 2012<br />

g. Meetings and significant decisions.<br />

h. Unusual events.<br />

i. Stoppages, delays, shortages, and losses.<br />

j. Meter readings and similar recordings.<br />

k. Emergency procedures.<br />

l. Orders and requests of authorities having jurisdiction.<br />

m. Contract Modifications received and implemented.<br />

n. Services connected and disconnected.<br />

o. Equipment or system tests and startups.<br />

p. Substantial Completions authorized.<br />

B. Field Condition Reports:<br />

1. Immediately on discovery of a difference between field conditions and the Contract Documents,<br />

prepare a report.<br />

2. Submit report with a Request for Information.<br />

3. Include recommendations for rectifying the difference, including changing the Contract Documents.<br />

2.5 SPECIAL REPORTS<br />

A. General:<br />

1. Submit special reports directly to Owner's Representative and to Architect within one day of an<br />

occurrence.<br />

2. Distribute copies of report to parties affected by the occurrence.<br />

B. Reporting Unusual Events:<br />

1. When an event of an unusual and significant nature occurs at <strong>Project</strong> site, whether or not related<br />

directly to the Work, prepare and submit a special report.<br />

2. List chain of events, persons participating, response by Contractor's personnel, evaluation of<br />

results or effects, and similar pertinent information.<br />

PART 3 - EXECUTION<br />

3.1 CONTRACTOR'S CONSTRUCTION SCHEDULE<br />

A. Contractor's <strong>Construction</strong> Schedule Updating:<br />

1. At monthly intervals, update schedule to reflect actual construction progress and activities.<br />

2. Issue updated schedule at least three days before next regularly scheduled progress meeting.<br />

3. Include with updated schedule a report of changes in logic, durations, actual starts and finishes,<br />

and activity durations.<br />

4. As the Work progresses, indicate Actual Completion percentage for each activity.<br />

B. Distribution:<br />

1. Distribute copies of approved schedule and subsequently updated schedule to:<br />

a. Architect.<br />

b. Owner's Representative.<br />

c. Sub-contractors.<br />

d. Testing and inspecting agencies.<br />

e. Other parties identified by Contractor with a need-to-know schedule responsibility.<br />

2. Post copies in <strong>Project</strong> field office.<br />

3. Delete parties from distribution when they have completed their assigned portion of the Work and<br />

are no longer involved in performance of construction activities.<br />

END OF SECTION<br />

01 32 00 - CONSTRUCTION PROGRESS DOCUMENTATION<br />