Deliveries <strong>of</strong> material for construction (e.g. pipes, concrete, precast structures, pumps) – on<br />

average 5 deliveries per day. During peak periods <strong>of</strong> construction (e.g. concrete pours) up to<br />

10 deliveries a day may be required.<br />

Most <strong>of</strong> the construction vehicles and deliveries would be directed to privately owned Fishburn<br />

Road , adjacent to the Elgas Caverns where a dedicated parking, site <strong>of</strong>fices and laydown area<br />

would be established. Road is currently closed to traffic and therefore there would no conflict with<br />

existing traffic and accesses. As noted above, the site would be accessed via highly trafficked<br />

regional roads with AADTs in excess <strong>of</strong> 20000 movements per day. Any increases in traffic on<br />

these regional roads due to construction activities would be negligible.<br />

There would also be a negligible increase in traffic associated with the operation <strong>of</strong> BLB2. This<br />

increase would be from increased operational and maintenance staff required to operate the new<br />

facility (