• To achieve a 10% reduction in all cases of MRSA. For the period April to<br />
December 2010 there were 31 new cases, compared to 53 in the same period<br />
last year which equates to 42%<br />
• Epidemic gastroenteritis – to maintain the average ward closure time due to<br />
epidemic gastroenteritis below 7 days. For the period April to December 2010<br />
there were 4 ward closures with an average ward closure period of 5.5 days.<br />
• Hand hygiene compliance – for all wards to perform at least 1 monthly hand<br />
hygiene audit with a compliance rate of 95%. For the period April to December<br />
2010 overall compliance was 99%.<br />
• Alcohol hand gel - for the availability of alcohol hand gel in clinical areas to be<br />
maintained as close to 100% as possible. For the period April to December 2010<br />
availability was 98%.<br />
• Surgical site surveillance – to continue surgical site surveillance on all major<br />
procedures. Majority of procedures now covered.<br />
• Delivery of a Postgraduate Certificate in Infection Prevention and Control in<br />
collaboration with the Peninsular School of Medicine and Dentistry. Two module<br />
PGCert to run in spring and summer 2011.<br />
• Infection Control Website developed and updated.<br />
• Saving Lives High Impact Interventions – all wards to perform at least 1 audit for<br />
in use medial devices, compliance monitored through the dashboard.<br />
C. Difficile Reporting<br />
Sarah Widnell / Jayne Glynn V7 21.03.11 17