9. Under SOW ~~ 9.1.1 and 9.1.2 the contractor was to conduct pre-final and final<br />

inspections and publish the findings (R4, tab 2 at 85).<br />

10. Under SOW Division 01, Project Administration, Management and General<br />

Conditions, the contractor had to supply a full-time site superintendent (R4, tab 2 at 89).<br />

11. TO'§ 0 1140, ~ 1.1, noted that the school would be open during construction<br />

and the contract()r was to cause the least possible interference, with special attention to<br />

phasing. There were eight phases. For phases 3-6, all work in each was to be complete<br />

and accepted by the CO before the next started. (R4, tab 6 at 265, tab 575 at 7163-64, tab<br />

578 at7181, tabs 579, 736 at 9831A, tab 742 at 9960-62; ex. G-118; tr. 3/67, 71-74,<br />

.81-84, 129,4/21-27) Under the Use and Possession clause, government use or possession<br />

is not acceptance (finding 1). There is no documentary evidence that the CO fonnally<br />

accepted any phase prior to final project inspection and acceptance.<br />

12. TO § 01330, ~ 1.1.1, noted that the Specifications and Drawings for<br />

Construction clause, ~~ (d), ( e) and (f) (finding 1), applied to all submittals. Unger'<br />

~ 1.1.2, "Construction Progress Schedule" and "Submittal register" were required<br />

preconstruction submittals.· (R4, tab 7 at 270) Paragraph 1.4.3 provided:<br />

a. Coordinate scheduling, sequencing, preparing and<br />

processing <strong>of</strong>submittals with performance <strong>of</strong>work so<br />

that work will not be delayed by submittal processing.<br />

Allow for potential requirements to resubmit.<br />

b. Except as specified otherwise, allow review period,<br />

beginning with receipt by approving authority, that<br />

includes at least 15 working days for submittals for QC<br />

Manager approval and 20 working days for submittals for<br />

[CO] approval. ... [Resubmittal review period is same.]<br />

d. No delay damages or tinle extensions will be allowed for<br />

time lost iIi late submittals.<br />