03.06.2014 Views

Versar, Inc. - Armed Services Board of Contract Appeals

Versar, Inc. - Armed Services Board of Contract Appeals

Versar, Inc. - Armed Services Board of Contract Appeals

SHOW MORE
SHOW LESS

Create successful ePaper yourself

Turn your PDF publications into a flip-book with our unique Google optimized e-Paper software.

least a month from being functional and ready for commissioning. <strong>Versar</strong> did not agree.<br />

(Ex. G-73; tr. 4/192-95, 6/10-15, 20-22)<br />

111. The government conducted its pre-final inspection/commissioning in March<br />

2008. PSC's Gabriel Manriquez, the project's mechanical engineer <strong>of</strong>record, conducted<br />

the commissioning. <strong>Versar</strong> deemed that he had pertinent knowledge and treated it fairly. '<br />

The Commissioning Report concluded that, in general, the main mechanical system<br />

components were functioning satisfactorily within the specified criteria. (R4, tabs 549,<br />

983 at 11985, 11987; exs. A-116, G-49; tr. 2/52, 4/191, 197-201,6/134, 7/68-82, 167)<br />

The government conducted its final inspection in May 2008. On 5 June 2008 the CO<br />

established 4 June 2008 as the project's beneficial occupancy date (BOD), contingent<br />

upon completion <strong>of</strong> a final punch list by 6 June 2008, which <strong>Versar</strong> accQmplished, and<br />

verification by Mr. Valenzuela on 17 June 2008, which occurred. (R4, tabs 505, 514,<br />

997, 1004 at 12357, ~ 56; ex. G-50; tr. 3/43,4/204-08) Citing the Warranty clause, the<br />

CO stated that the one-year warranty was effective from 4 June 2008 through 3 June<br />

2009, in effect setting the 4 June 2008 BOD as the date <strong>of</strong> final acceptance (or<br />

government possession) (R4, tab 514).<br />

112. In May-June 2008 the CO told <strong>Versar</strong> that its invoices had been rejected and'<br />

AFCEE would withhold 10% retainage becaus~ the COR didnot agree with the stated<br />

completion percentage. On 20 June 2008 <strong>Versar</strong> consolidated invoices Nos. 9~11 into<br />

No. 12, for'$959,137, for 1 March 2007-13 March 2008, and advised itwould su~mit an<br />

REA. On 25 June 2008 the' CO notified <strong>Versar</strong> that the government would retain 10%, or<br />

$95,913.70, from invoice No. J2 to cover school relocation and other costs. She<br />

authorized payment <strong>of</strong> the $863,223.30 balance on 25 June 2008, but the government has'<br />

not refuted <strong>Versar</strong>'s allegation that it was not paid until 16 September 2008.' <strong>Versar</strong><br />

submitted invoice No. 13, dated 27 June 2008, for $491,291.69, for 14 March-27 June<br />

, 2008, which was rejected, but the reason is not clear. On8 July 2008 it asked the CO to<br />

clarify the basis for the No. 12 withholding and for a danlages breakdown~ (R4, tabs 517,<br />

518, 519 at 6098~ 521, 562 at 6904, tabs 598, 599 at 7391; tr. 2/209-11)<br />

113. On 21 August 2008 CO Brown issued a demand to <strong>Versar</strong> for $660,721.00<br />

(R4, tab 532). Her final decision <strong>of</strong>that date .claimed damages from 30 September 2007<br />

to date. She cited the Payments clause (due to lack <strong>of</strong> an approved schedule, the<br />

government was not able to establish completion percentages); the lnspection clause<br />

(because the project was not ready for inspection, <strong>Versar</strong> was responsible for all costs <strong>of</strong><br />

two additional final inspections); the Default clause (<strong>Versar</strong> was liable for all government<br />

costs

Hooray! Your file is uploaded and ready to be published.

Saved successfully!

Ooh no, something went wrong!