03.06.2014 Views

Versar, Inc. - Armed Services Board of Contract Appeals

Versar, Inc. - Armed Services Board of Contract Appeals

Versar, Inc. - Armed Services Board of Contract Appeals

SHOW MORE
SHOW LESS

Create successful ePaper yourself

Turn your PDF publications into a flip-book with our unique Google optimized e-Paper software.

25. The specifications called for seismic protection per TI 809-04 and data from<br />

the CO. Under § 15070A, ~ 1.1, listed p~blications were part <strong>of</strong>the specifications to the<br />

extent referenced. The SMACNA manual was listyd but not referenced further. Shop<br />

drawings required government approval and were to include detail drawings, catalog cuts,<br />

and numerous other details. Design calculations stamped by a registered engineer were<br />

required, including to verify the ability <strong>of</strong>structural members to which bracing was<br />

attached to carry the load. The TO did not specify the number <strong>of</strong>seismic restraints but<br />

transverse sway bracing for steel and copper pipe was to be per § 13080 and longitudinal<br />

sway bracing was to be at 40-foot intervals unless otherwise indicated'. There were no<br />

contrary indications. (R4, tab 38 at 633 (§ 13080, ~~ 1.2.1, 1.3), at 636 (~~ 3.5, 3.5.1), tab<br />

41 at 675-77 (§15070A, ~~ 1.1, 1.2.,1, 1.2.4, 1.2.5.1, 1.4), at 679 (~~ 3.5.1, J.5.2), tab 56 at<br />

1018-21 (§ 16070A, ~~ 1.1, 1.2, 1.3.3,2.2,3.2.5))<br />

26. The HV AC system was a four pipe chilled water, water boiler system. Section<br />

13080 governed the seismic restraints on a loop <strong>of</strong> four 6 to 8-inch pipes running<br />

throughout the building's corridors from the mechanical room to feed the air handling<br />

units (AHUs) and FCUs. Drawing No. M-I05 depicted the piping loop and FCUs. (R4,<br />

tab 736 at 9879, see also tab 773 at 10462; tr. 1/78-80,3/61, 78, 80-81)<br />

27. On 23 August 2006 the CO disapproved <strong>Versar</strong>'s 19 July 2006 submittal <br />

No. 13, pertaining to vibration and seismic isolation under § 15070A, due to lack <strong>of</strong> <br />

bracing and stamped design calculations (R4, tab 96 at 1880, 1888). Tom Redmond <strong>of</strong> <br />

Parsons informed the COR on 23 August that, although V ersar' s submittal was not <br />

complete, its piping, ductwork and equipment support systems conformed to industry <br />

standards and specifications and looked like "good quality work" (id. at 1882). <br />

28. On 25 September 2006 Custom fired its project manager (ex. G-33 at 1234).<br />

29. On 3-4 October 2006 Ms. Harvill visited the site to verify the location <strong>of</strong>new<br />

pipes for the HV AC system, ductwork and existing domestic supply pipes. She did not<br />

issue her resulting memorandUin on the basis it would be better to wait until PSC could<br />

coordinate with seismic requirements. (Ex. A-30 at 3, ex. A-39 at 1; tr. 8/114-15)<br />

30. As <strong>of</strong> 11 October 2006 JJK was still processing the submittal register,<br />

outstanding for several weeks; Custom committed to bringing additional forces onsite<br />

during the Christmas break to maintain schedule; and JJK had delivered a seismic<br />

submittal but it was missing calculations for piping and only equipment data had been<br />

supplied. On 14 October 2006 <strong>Versar</strong> notified JJK that; after waiting a few months, it had<br />

, received a seismic protection package that did not analyze all necessary equipment or<br />

include all required information, including calculations and design elements, and<br />

drawings were not clearly labeled and were incomplete. On 2 November 2006 <strong>Versar</strong>'s<br />

20

Hooray! Your file is uploaded and ready to be published.

Saved successfully!

Ooh no, something went wrong!