03.06.2014 Views

Versar, Inc. - Armed Services Board of Contract Appeals

Versar, Inc. - Armed Services Board of Contract Appeals

Versar, Inc. - Armed Services Board of Contract Appeals

SHOW MORE
SHOW LESS

You also want an ePaper? Increase the reach of your titles

YUMPU automatically turns print PDFs into web optimized ePapers that Google loves.

& ROOF DETAILS," and its Detail A5, which depicted bracing requirements, without<br />

limitation concerning its application, except that additional bracing was not required for<br />

items under 50 pounds and, with additional bracing, items could be up to 250 pounds.<br />

(R4, tab 736 at 9872) <strong>Versar</strong> and JJK contended the detail was specific and pertained<br />

only to additional joint reinforcement for outside air units and AHUs, much larger and<br />

heavier than FCUs, although the detail did not so state. There is no evidence they<br />

inquired prior to FCU installation or that <strong>Versar</strong> relied upon this interpretation when it<br />

entered into the TO. The directive affected hundreds <strong>of</strong> locations, including 90% <strong>of</strong>the<br />

FCUs and pipe hanger supports. Ms. Harvill acknowledged that the drawings regarding<br />

FCU details did not refer to A5/A-503 and that in a 1 February 2007 memorandum to<br />

Mr. Redmond she had stated that the detail was referred to in one section <strong>of</strong>the drawings<br />

but not as a general requirement. On 10 September 2007 <strong>Versar</strong> submitted RFI No. 59<br />

stating the installation had been inspected and approved previously, per February 2007<br />

documentation by Mr. Redmond. It sought a change order ifmore reinforcement were<br />

required. (R4, tab 384 at 4347, tab 403 at 4592-93, see R4, tab 40.3 at 4592; ex. A-36 at<br />

1; tr. 3/136-40,4/35-36,116-17, 8/79,113-14) Mr. Bernal opined that the detail was<br />

industry standard and "typical" for items exceeding 50 pounds but acknowledged that it<br />

was not referenced in the FCU details (tr. 8/192, 9/35).<br />

96. On 7 September 2007 <strong>Versar</strong> requested a 60-day extension and equitable<br />

adjustment, with costs to be provided, on FCU issues. The CO asked it to resubmit<br />

, without a monetary element, to save time. (R4, tab 400; ti. 3/24-27)<br />

97. On 18 September 2007 <strong>Versar</strong> reduced its extension request to 45 days, citing<br />

FCU issues and alleged government-caused delays. The COR recommended denial. On<br />

27 September 2007 <strong>Versar</strong> reiterated its prior requ~sts and sought two more weeks related<br />

to commissioning and pre-final inspection; AFCEE acceptance <strong>of</strong> a 14 September 2007<br />

substantial completion date; a date for pre-final inspection; 8:ndconfirmation that it would<br />

not be held in default. (R4, tabs 400,412,413, 418; tr. 3/27, 29-33)<br />

98. On 28 September 2007 <strong>Versar</strong> submitted invoice No. 10, for 1 April 2007 to <br />

date. The COR rejected it, stating internally that he would not sign until<strong>Versar</strong> had met <br />

CDRL and project completion requirements, including submitting a schedule showing <br />

how it had arrived at the completion percentage. (R4, tab 423) <br />

99. Also on 28 September 2007, CO Bryant issued a forbearance notice to <strong>Versar</strong><br />

stating that its failure to comply with Mod. No.3, under which the performance period<br />

would expire on 30 September 2007, breached the Commencement, Prosecution, and<br />

Completion <strong>of</strong> Work and the TO Procedures clauses. She concluded that, while allowing<br />

<strong>Versar</strong> to continue to perform, the government was not forbearing its contractual rights and<br />

remedies, including under the Default clause. (R4, tab 632 at 7857) The CO testified that<br />

i<br />

40

Hooray! Your file is uploaded and ready to be published.

Saved successfully!

Ooh no, something went wrong!