Versar, Inc. - Armed Services Board of Contract Appeals
Versar, Inc. - Armed Services Board of Contract Appeals
Versar, Inc. - Armed Services Board of Contract Appeals
You also want an ePaper? Increase the reach of your titles
YUMPU automatically turns print PDFs into web optimized ePapers that Google loves.
& ROOF DETAILS," and its Detail A5, which depicted bracing requirements, without<br />
limitation concerning its application, except that additional bracing was not required for<br />
items under 50 pounds and, with additional bracing, items could be up to 250 pounds.<br />
(R4, tab 736 at 9872) <strong>Versar</strong> and JJK contended the detail was specific and pertained<br />
only to additional joint reinforcement for outside air units and AHUs, much larger and<br />
heavier than FCUs, although the detail did not so state. There is no evidence they<br />
inquired prior to FCU installation or that <strong>Versar</strong> relied upon this interpretation when it<br />
entered into the TO. The directive affected hundreds <strong>of</strong> locations, including 90% <strong>of</strong>the<br />
FCUs and pipe hanger supports. Ms. Harvill acknowledged that the drawings regarding<br />
FCU details did not refer to A5/A-503 and that in a 1 February 2007 memorandum to<br />
Mr. Redmond she had stated that the detail was referred to in one section <strong>of</strong>the drawings<br />
but not as a general requirement. On 10 September 2007 <strong>Versar</strong> submitted RFI No. 59<br />
stating the installation had been inspected and approved previously, per February 2007<br />
documentation by Mr. Redmond. It sought a change order ifmore reinforcement were<br />
required. (R4, tab 384 at 4347, tab 403 at 4592-93, see R4, tab 40.3 at 4592; ex. A-36 at<br />
1; tr. 3/136-40,4/35-36,116-17, 8/79,113-14) Mr. Bernal opined that the detail was<br />
industry standard and "typical" for items exceeding 50 pounds but acknowledged that it<br />
was not referenced in the FCU details (tr. 8/192, 9/35).<br />
96. On 7 September 2007 <strong>Versar</strong> requested a 60-day extension and equitable<br />
adjustment, with costs to be provided, on FCU issues. The CO asked it to resubmit<br />
, without a monetary element, to save time. (R4, tab 400; ti. 3/24-27)<br />
97. On 18 September 2007 <strong>Versar</strong> reduced its extension request to 45 days, citing<br />
FCU issues and alleged government-caused delays. The COR recommended denial. On<br />
27 September 2007 <strong>Versar</strong> reiterated its prior requ~sts and sought two more weeks related<br />
to commissioning and pre-final inspection; AFCEE acceptance <strong>of</strong> a 14 September 2007<br />
substantial completion date; a date for pre-final inspection; 8:ndconfirmation that it would<br />
not be held in default. (R4, tabs 400,412,413, 418; tr. 3/27, 29-33)<br />
98. On 28 September 2007 <strong>Versar</strong> submitted invoice No. 10, for 1 April 2007 to <br />
date. The COR rejected it, stating internally that he would not sign until<strong>Versar</strong> had met <br />
CDRL and project completion requirements, including submitting a schedule showing <br />
how it had arrived at the completion percentage. (R4, tab 423) <br />
99. Also on 28 September 2007, CO Bryant issued a forbearance notice to <strong>Versar</strong><br />
stating that its failure to comply with Mod. No.3, under which the performance period<br />
would expire on 30 September 2007, breached the Commencement, Prosecution, and<br />
Completion <strong>of</strong> Work and the TO Procedures clauses. She concluded that, while allowing<br />
<strong>Versar</strong> to continue to perform, the government was not forbearing its contractual rights and<br />
remedies, including under the Default clause. (R4, tab 632 at 7857) The CO testified that<br />
i<br />
40