15.06.2014 Views

Annual Report 2011 - Roscommon County Council

Annual Report 2011 - Roscommon County Council

Annual Report 2011 - Roscommon County Council

SHOW MORE
SHOW LESS

You also want an ePaper? Increase the reach of your titles

YUMPU automatically turns print PDFs into web optimized ePapers that Google loves.

Water Services<br />

North East Regional Water Supply Scheme: The detailed planning in relation to the provision of a new water<br />

treatment plant for the area has been completed. Approval to go to tender for both the treatment plant and rising<br />

main was received in <strong>2011</strong>. The tender for the pipeline element will proceed in February 2012 and the treatment<br />

works will follow, once statutory licences have been agreed. The scheme has an estimated cost of €16 million.<br />

West <strong>Roscommon</strong> Regional Water Supply Scheme: The North <strong>Roscommon</strong> Regional scheme, Castlerea Urban<br />

and Rural schemes and the Ballinlough/Loughglynn scheme will be amalgamated to form the West <strong>Roscommon</strong><br />

Regional Water Supply Scheme. The Preliminary <strong>Report</strong> and recommendations with regard to the upgrading<br />

of the scheme have been submitted to the Department. A Supplementary <strong>Report</strong>, based on a rationalisation<br />

of the scheme, was completed in <strong>2011</strong> and also submitted and approval is awaited. Advance works, including<br />

the provision of a cryptosporidium barrier and a new pipe network at Castlerea, are progressing and will be<br />

completed in 2012.<br />

Water Conservation: Phase Three of the Water Conservation Programme commenced in late 2010. This phase<br />

involves a substantial mains rehabilitation programme with an approved cost of €10.5 million and is to be<br />

completed over a three year period. A contract for the rehabilitation of 30km was begun in <strong>2011</strong> and will be<br />

completed in 2012. A second scheme of 45km was tendered in <strong>2011</strong> and will be awarded in early 2012. The<br />

<strong>Council</strong> carried out an additional 20km of rehabilitation works by direct labour. A 25% overall reduction in water<br />

demand has been achieved at the end of <strong>2011</strong> under the programme. Two full time staff are employed in leak<br />

detection, monitoring and recording of data. Repair of leaks is ongoing.<br />

Non-Domestic Water Metering: Local Authorities are required to meter all non-domestic water connections as<br />

part of the Government’s National Water Pricing Framework. Veolia Water Ireland Ltd. continue to implement this<br />

project on behalf of the <strong>Council</strong>. Water and waste water charges are now charged on a metered basis and over<br />

8,500 meters have been installed at the end of <strong>2011</strong>. A standing charge of €25 per quarter applied in <strong>2011</strong>, with<br />

a charge of €1.22 and €1.50 per cubic metre for water and waste water respectively.<br />

Rural Water Programme<br />

Design Build Operate Project for Water Treatment: Twenty private group schemes were amalgamated into<br />

three new co-operative schemes and were included with two public schemes, Knockcroghery and Lecarrow, in<br />

a Design, Build & Operate project. Six water treatment plants were completed and commissioned in <strong>2011</strong>. They<br />

are operated by Glan Agua Ltd. on behalf of the co-operatives and the <strong>Council</strong>. Total expenditure on the project<br />

in <strong>2011</strong> was €1.9m.<br />

Small Schemes Programme: The <strong>Council</strong> received an allocation of €426,000 from the Department of Environment,<br />

Community and Local Government to upgrade public water and sewerage schemes in <strong>2011</strong>, representing a<br />

contribution of 75% of the cost. A total of €663,000 was expended on completing all outstanding schemes and<br />

commencing works on the <strong>2011</strong> programme..<br />

Take-in-Charge and Connection to the Public Main: €63,120 was claimed for the connection of three Group<br />

Schemes – Greywood, Derrinacartha and Four Roads – to the public supply in <strong>2011</strong>.<br />

Water and Sewer Connections: During <strong>2011</strong>, 76 connection licences were issued for 83 connections to the public<br />

water mains, sewerage, and group water schemes. 49 road opening licences were issued.<br />

Individual Water Supply Grants: Houses that are neither connected to the public mains nor to a private water<br />

scheme may be eligible for a grant to upgrade their supply if their house is more than seven years old. The grant<br />

amounts to 75% of the cost, subject to a maximum payment of €2,031. A total of €15,700 was paid in grants in<br />

<strong>2011</strong> to 8 applicants.<br />

Subsidy towards the Operational Cost of Group Water Supply Schemes: Subsidies are payable to schemes to<br />

help offset costs incurred in the day-to-day provision of a water supply to domestic houses. A total of €426,200<br />

was paid to 11 schemes in respect of claims made during <strong>2011</strong>. The subsidy is recouped from the Department.<br />

66 <strong>Roscommon</strong> <strong>County</strong> <strong>Council</strong>

Hooray! Your file is uploaded and ready to be published.

Saved successfully!

Ooh no, something went wrong!