Annual Report 2011 - Roscommon County Council
Annual Report 2011 - Roscommon County Council
Annual Report 2011 - Roscommon County Council
You also want an ePaper? Increase the reach of your titles
YUMPU automatically turns print PDFs into web optimized ePapers that Google loves.
Water Services<br />
North East Regional Water Supply Scheme: The detailed planning in relation to the provision of a new water<br />
treatment plant for the area has been completed. Approval to go to tender for both the treatment plant and rising<br />
main was received in <strong>2011</strong>. The tender for the pipeline element will proceed in February 2012 and the treatment<br />
works will follow, once statutory licences have been agreed. The scheme has an estimated cost of €16 million.<br />
West <strong>Roscommon</strong> Regional Water Supply Scheme: The North <strong>Roscommon</strong> Regional scheme, Castlerea Urban<br />
and Rural schemes and the Ballinlough/Loughglynn scheme will be amalgamated to form the West <strong>Roscommon</strong><br />
Regional Water Supply Scheme. The Preliminary <strong>Report</strong> and recommendations with regard to the upgrading<br />
of the scheme have been submitted to the Department. A Supplementary <strong>Report</strong>, based on a rationalisation<br />
of the scheme, was completed in <strong>2011</strong> and also submitted and approval is awaited. Advance works, including<br />
the provision of a cryptosporidium barrier and a new pipe network at Castlerea, are progressing and will be<br />
completed in 2012.<br />
Water Conservation: Phase Three of the Water Conservation Programme commenced in late 2010. This phase<br />
involves a substantial mains rehabilitation programme with an approved cost of €10.5 million and is to be<br />
completed over a three year period. A contract for the rehabilitation of 30km was begun in <strong>2011</strong> and will be<br />
completed in 2012. A second scheme of 45km was tendered in <strong>2011</strong> and will be awarded in early 2012. The<br />
<strong>Council</strong> carried out an additional 20km of rehabilitation works by direct labour. A 25% overall reduction in water<br />
demand has been achieved at the end of <strong>2011</strong> under the programme. Two full time staff are employed in leak<br />
detection, monitoring and recording of data. Repair of leaks is ongoing.<br />
Non-Domestic Water Metering: Local Authorities are required to meter all non-domestic water connections as<br />
part of the Government’s National Water Pricing Framework. Veolia Water Ireland Ltd. continue to implement this<br />
project on behalf of the <strong>Council</strong>. Water and waste water charges are now charged on a metered basis and over<br />
8,500 meters have been installed at the end of <strong>2011</strong>. A standing charge of €25 per quarter applied in <strong>2011</strong>, with<br />
a charge of €1.22 and €1.50 per cubic metre for water and waste water respectively.<br />
Rural Water Programme<br />
Design Build Operate Project for Water Treatment: Twenty private group schemes were amalgamated into<br />
three new co-operative schemes and were included with two public schemes, Knockcroghery and Lecarrow, in<br />
a Design, Build & Operate project. Six water treatment plants were completed and commissioned in <strong>2011</strong>. They<br />
are operated by Glan Agua Ltd. on behalf of the co-operatives and the <strong>Council</strong>. Total expenditure on the project<br />
in <strong>2011</strong> was €1.9m.<br />
Small Schemes Programme: The <strong>Council</strong> received an allocation of €426,000 from the Department of Environment,<br />
Community and Local Government to upgrade public water and sewerage schemes in <strong>2011</strong>, representing a<br />
contribution of 75% of the cost. A total of €663,000 was expended on completing all outstanding schemes and<br />
commencing works on the <strong>2011</strong> programme..<br />
Take-in-Charge and Connection to the Public Main: €63,120 was claimed for the connection of three Group<br />
Schemes – Greywood, Derrinacartha and Four Roads – to the public supply in <strong>2011</strong>.<br />
Water and Sewer Connections: During <strong>2011</strong>, 76 connection licences were issued for 83 connections to the public<br />
water mains, sewerage, and group water schemes. 49 road opening licences were issued.<br />
Individual Water Supply Grants: Houses that are neither connected to the public mains nor to a private water<br />
scheme may be eligible for a grant to upgrade their supply if their house is more than seven years old. The grant<br />
amounts to 75% of the cost, subject to a maximum payment of €2,031. A total of €15,700 was paid in grants in<br />
<strong>2011</strong> to 8 applicants.<br />
Subsidy towards the Operational Cost of Group Water Supply Schemes: Subsidies are payable to schemes to<br />
help offset costs incurred in the day-to-day provision of a water supply to domestic houses. A total of €426,200<br />
was paid to 11 schemes in respect of claims made during <strong>2011</strong>. The subsidy is recouped from the Department.<br />
66 <strong>Roscommon</strong> <strong>County</strong> <strong>Council</strong>