Overview of Cost Increases<br />
4.1 Initial estimates for the cost of constructing Spring Hill and Otago were made as<br />
early as May 2000. However, substantive estimates were not made until late 2003.<br />
These estimates were included as part of the reporting to Ministers in the context of<br />
Budget 04. At that time, the costs associated with Spring Hill and Otago were expected to<br />
be approximately $248 million and $161 million respectively. The estimates indicated as<br />
part of Budget 04 were informed by the tenders submitted for the Northland project.<br />
4.2 The estimates were updated as part of Budget 05 and took account of escalation<br />
since the previous estimates made in 2003. The costs for Spring Hill and Otago reported<br />
as part of Budget 05 were revised upwards to $283 million and $175 million respectively.<br />
4.3 Since Budget 05, costs have risen further. In December 2005, approval was<br />
sought for additional appropriations totalling $140.841 million. This reflected the net effect<br />
of increased construction costs totalling $157.976 million, together with the off-setting<br />
impact of lower than expected expenditure in other areas (e.g. earthworks and<br />
reclassification of some commissioning costs) which totalled $17.135 million (giving a net<br />
increase of $140.841 million).<br />
4.4 The table below summarises the reasons provided to Ministers, as part of the<br />
December 2005 reporting package, behind the significant construction cost increases<br />
between Budget 05 and the numbers reported in December 2005.<br />
Spring Hill<br />
Cost Contributors<br />
($ million)<br />
Market Influences 53.773<br />
Consents and<br />
Regulatory Changes<br />
Escalation 16.640<br />
Labour rates and location 13.123<br />
Margins and overhead 13.570<br />
On-site construction cost increases 10.440<br />
Consents 5.740<br />
Holidays Act, Building Act 1.540<br />
7.280<br />
Design Finalisation 50.650<br />
Changes arising from Northland 13.600<br />
Site works requirements<br />
37.050<br />
• Drainage $11.3<br />
• Ducting $4.6<br />
• Water reticulation $2.9<br />
• Gas reticulation $0.6<br />
• Roading $6.0<br />
• Finishing works & landscaping $10.1<br />
Total Increase 111.703<br />
Key Drivers and Causes of Cost Escalation 14