NZ Report / Proposal Template - State Services Commission
NZ Report / Proposal Template - State Services Commission
NZ Report / Proposal Template - State Services Commission
Create successful ePaper yourself
Turn your PDF publications into a flip-book with our unique Google optimized e-Paper software.
outcome of negotiations with relevant local authorities. There were also some changes in<br />
Ministry of Health standards relating to water treatment and waste-water discharge.<br />
4.28 Other regulatory changes related to the Holidays Act. These changes resulted in<br />
additional labour costs. We note that the additional costs stemming from the Holidays Act<br />
should be reflected in the CGPI-NRB and so there is some risk that this element of the<br />
overall cost increase is being captured twice.<br />
Design Finalisation<br />
4.29 According to the advice presented to Cabinet in December 2005, completion of<br />
detailed design works at Spring Hill (which occurred subsequent to the reporting in April<br />
2005) identified a number of additional items, the total cost of which amounted to $37.050<br />
million or roughly 10% of the total project cost. These included:<br />
• site drainage ($11.3 million);<br />
• underground ducting and future proofing ($4.6 million);<br />
• water reticulation and management ($2.9 million);<br />
• gas reticulation ($0.6 million);<br />
• access roads and car parking ($6 million); and<br />
• finishing works and landscaping ($10.1 million).<br />
4.30 This is a significant amount. Although the reason behind these changes is<br />
referred to as being a function of completing detailed design work, we understand that<br />
some of the changes are also a function of the outcome of the consents process. In<br />
particular, the consent process lead to some significant design changes, including moving<br />
building platforms. This had flow-on consequences for infrastructural services such as<br />
drainage and utilities reticulation. A general difficulty facing the Department is that when<br />
such changes are being discussed/negotiated as part of the consents process, the cost<br />
impact is not necessarily known with any degree of precision.<br />
4.31 As far as we are aware, Ministers were not advised of these additional costs until<br />
the December 2005 report to Cabinet. In our view, the prospect of additional costs in<br />
these areas would have been known at the time of Budget 05 even though the scale of<br />
cost would not have been known at that stage. Given the scale of the additional cost,<br />
more forewarning of Ministers could have occurred.<br />
Summary<br />
4.32 Many factors have contributed to the increase in costs over and above those<br />
reported as part of Budget 05. The underlying drivers of these can be summarised as<br />
follows:<br />
• the heated nature of the construction market which resulted in higher input costs<br />
(materials and labour);<br />
• international trends for the price of steel;<br />
• the remote location of the sites which has given rise to additional allowances;<br />
Key Drivers and Causes of Cost Escalation 20