24.07.2014 Views

NZ Report / Proposal Template - State Services Commission

NZ Report / Proposal Template - State Services Commission

NZ Report / Proposal Template - State Services Commission

SHOW MORE
SHOW LESS

Create successful ePaper yourself

Turn your PDF publications into a flip-book with our unique Google optimized e-Paper software.

outcome of negotiations with relevant local authorities. There were also some changes in<br />

Ministry of Health standards relating to water treatment and waste-water discharge.<br />

4.28 Other regulatory changes related to the Holidays Act. These changes resulted in<br />

additional labour costs. We note that the additional costs stemming from the Holidays Act<br />

should be reflected in the CGPI-NRB and so there is some risk that this element of the<br />

overall cost increase is being captured twice.<br />

Design Finalisation<br />

4.29 According to the advice presented to Cabinet in December 2005, completion of<br />

detailed design works at Spring Hill (which occurred subsequent to the reporting in April<br />

2005) identified a number of additional items, the total cost of which amounted to $37.050<br />

million or roughly 10% of the total project cost. These included:<br />

• site drainage ($11.3 million);<br />

• underground ducting and future proofing ($4.6 million);<br />

• water reticulation and management ($2.9 million);<br />

• gas reticulation ($0.6 million);<br />

• access roads and car parking ($6 million); and<br />

• finishing works and landscaping ($10.1 million).<br />

4.30 This is a significant amount. Although the reason behind these changes is<br />

referred to as being a function of completing detailed design work, we understand that<br />

some of the changes are also a function of the outcome of the consents process. In<br />

particular, the consent process lead to some significant design changes, including moving<br />

building platforms. This had flow-on consequences for infrastructural services such as<br />

drainage and utilities reticulation. A general difficulty facing the Department is that when<br />

such changes are being discussed/negotiated as part of the consents process, the cost<br />

impact is not necessarily known with any degree of precision.<br />

4.31 As far as we are aware, Ministers were not advised of these additional costs until<br />

the December 2005 report to Cabinet. In our view, the prospect of additional costs in<br />

these areas would have been known at the time of Budget 05 even though the scale of<br />

cost would not have been known at that stage. Given the scale of the additional cost,<br />

more forewarning of Ministers could have occurred.<br />

Summary<br />

4.32 Many factors have contributed to the increase in costs over and above those<br />

reported as part of Budget 05. The underlying drivers of these can be summarised as<br />

follows:<br />

• the heated nature of the construction market which resulted in higher input costs<br />

(materials and labour);<br />

• international trends for the price of steel;<br />

• the remote location of the sites which has given rise to additional allowances;<br />

Key Drivers and Causes of Cost Escalation 20

Hooray! Your file is uploaded and ready to be published.

Saved successfully!

Ooh no, something went wrong!