Cabinet Office<br />
To:<br />
COUNCILLOR RAY PUDDIFOOT<br />
LEADER OF THE COUNCIL<br />
Location: 3E/05<br />
Ext: 3472<br />
DDI : 01895 250472<br />
My Ref: SEC<br />
COUNCILLOR JONATHAN BIANCO<br />
CABINET MEMBER FOR FINANCE & BUSINESS<br />
SERVICES<br />
c.c. Councillors Anthony Way and Richard Lewis<br />
Chairmen of Scrutiny and Policy Overview<br />
Committees<br />
c.c. Steve Smith, Facilities Manager<br />
c.c. Christopher Neale, Corporate Director of<br />
Finance<br />
c.c. Conservative, Labour and LibDem Group<br />
Offices, Phase 2<br />
Date: 19 th July 2006<br />
Decision Request Form INDIVIDUAL CABINET MEMBER<br />
CAPITAL EXPENDITURE REQUEST – CIVIC CENTRE MODERNISATION<br />
Attached is a report requesting that a decision be made by you as an individual Cabinet<br />
Member. I can confirm that the decision has been identified in the Forward Plan and it is<br />
therefore in order for you to make a decision. You should take a decision on or after<br />
Thursday 27 th July 2006 in order to meet Constitutional requirements about publication of<br />
decisions that are to be made.<br />
Please indicate your decision on the duplicate memo supplied, and return it to me when you<br />
have made your decision. I will then arrange for the formal notice of decision to be<br />
published. You may wish to discuss the report with the Corporate Director before it is made.<br />
If you do not wish to accept the officers recommendation and the reasons for it, you are<br />
urged to contact the Corporate Director before making this decision.<br />
Please note that your decision may be subject to call-in and will not therefore be<br />
implemented until 5 working days after it has been published.<br />
SUSAN CAME<br />
Cabinet Manager<br />
Title of <strong>Report</strong>: CAPITAL EXPENDITURE REQUEST – CIVIC CENTRE<br />
MODERNISATION<br />
Decision made:<br />
Reasons for your decision : (e.g. as stated in report)<br />
Alternatives considered and rejected : (e.g. as stated in report)<br />
Signed ………………………………………………………Date……………………..<br />
Leader of the Council / Cabinet Member for Finance and Business Services
APPROVAL FOR CAPITAL EXPENDITURE FROM<br />
CAPITAL BUDGET – CIVIC CENTRE<br />
MODERNISATION<br />
SUMMARY<br />
Contact Officer: Steve Smith<br />
Telephone: 01895 250518<br />
This report requests approval to spend the sum of £123k to modernise Committee<br />
Room and Council Chamber facilities in the Civic Centre.<br />
RECOMMENDATION<br />
That Members agree to the sum of £123k being allocated from the Council’s<br />
Modernisation budget (2006/7) to modernise outdated facilities in the Civic Centre<br />
(CR3,5,6 and 7), which will also include the partitioning of Committee Room 3 and<br />
the replacement of the Council Chamber centre doors with automatic sliding doors.<br />
OPTIONS AVAILABLE<br />
Members can defer the Capital Expenditure outlined in the report but this will mean<br />
the continued use of out of date facilities by staff, Members and external visitors<br />
including members of the community.<br />
COMMENTS OF THE OVERVIEW AND SCRUTINY COMMITTEE<br />
None sought at this stage.<br />
INFORMATION<br />
Approval was given last financial year to the refurbishment of Committee rooms 4<br />
and 6, which included electronic facilities permanently installed for presentations, to<br />
facilitate meetings within the Civic Centre for Members, staff and hirers. This also<br />
included electronic multimedia facilities e.g. built in LCD projectors, electronic boards<br />
and associated equipment.<br />
The project also included the subdivision of CR4, which was created by providing an<br />
additional entrance to the facility, and installing a sliding partition.<br />
The programme commenced with the modernisation and partitioning of CR4, which<br />
was completed in November 2005, and the modernisation of CR6, which was<br />
completed in March 2006.<br />
It is proposed to continue the modernisation programme in the current year and<br />
modernise and partition CR3 to the same specification as CR4 undertaken in 2005/6<br />
and CR5 to the same specification as CR6. Furthermore it is also proposed to<br />
replace the external doors of CR5, CR6 and CR7, install split air-conditioning in CR7<br />
as there is currently none and replace the doors to the Council Chamber with<br />
PART 1 – MEMBERS, PUBLIC AND PRESS<br />
Cabinet Member report 19 th July 2006 Page 1
modern automatic doors, which will improve access for staff and visitors with<br />
disabilities as part of the Councils commitment to its DDA obligations. The<br />
installation of split air-conditioning will be run independently of the main system,<br />
therefore providing greater flexibility and control over costs.<br />
The breakdown in costs for this project is as follows:<br />
CR3 Modernisation and Partition £65k<br />
CR6 Modernisation £40k<br />
CR5/6/7 Replacement Doors £6k<br />
CR7 Installation of Split Air Conditioning Unit £6k<br />
Council Chamber Replacement Doors £6k<br />
TOTAL £123K<br />
Works have been provisionally programmed to commence in CR3 on 7 th August<br />
2006 subject to funding approval and a detailed PID is currently being developed<br />
which will cover the total project to ensure completion by the end of the financial<br />
year.<br />
Financial Implications<br />
The Capital programme 2006/2007 includes a budget provision of £225k to fund<br />
further modernisation of the Civic Centre. The £123k works proposed to modernise<br />
CR3, CR5, CR6, CR7 and the Council Chamber replacement doors will be met from<br />
within the £225k capital budget, leaving £102k available for other modernisation<br />
projects.<br />
Further proposals to modernise the Council Chamber will be presented to Members<br />
on completion of detailed feasibility currently in progress.<br />
CORPORATE CONSULTATIONS CARRIED OUT<br />
Finance Comments<br />
This report and its financial implications properly reflect both the direct resource<br />
implications on the service concerned and any wider implications on Council<br />
resources as a whole.<br />
Legal Comments<br />
There are no legal implications arising from the report.<br />
Project Office<br />
The PSO has audited the PIDs for refurbishment of the Committee Rooms (to<br />
include redecoration, carpet replacement and lighting improvements, with addition of<br />
presentation facilities) and is satisfied that the appropriate project management<br />
arrangements are in place to ensure that these projects are delivered within time,<br />
cost and to qualify.<br />
PART 1 – MEMBERS, PUBLIC AND PRESS<br />
Cabinet Member report 19 th July 2006 Page 2
Property Comments<br />
Corporate Property have been involved in this project and fully support the upgrading<br />
of this Committee Room.<br />
Background Documents<br />
Cabinet Meeting 23 February 2006 Council budget 2005/6<br />
PART 1 – MEMBERS, PUBLIC AND PRESS<br />
Cabinet Member report 19 th July 2006 Page 3