and 5). The primary stormwater conveyance systems in the watersheds are channelized ditches with various lining material. While<br />
the PPWMD is unable to create flood protection ordinances, the primary goal of the PPWMD is to improve and maintain the<br />
stormwater management system to contain the 25-year, 24-hour storm event within channel banks and to limit flooding during the<br />
100-year, 24-hour storm event to the streets and yards where possible.<br />
A recent effort was untaken by the PPWMD in conjunction with the City of Pinellas Park in which revisions were made and<br />
accepted by the Federal Emergency <strong>Management</strong> Agency for the Flood Insurance Rate Maps of Channels 1, 2, 3 and 4.<br />
Additionally, the PPWMD employs staff and owns specialized equipment that are dedicated to maintaining the channels within the<br />
PPWMD boundary.<br />
Funding Source<br />
Prior Funding<br />
FY2013<br />
Budget<br />
FY2014<br />
Budget<br />
Future<br />
Funding<br />
Total Funding<br />
Applicant Share 750,000 750,000<br />
Pinellas Anclote 750,000 750,000<br />
Total 1,500,000 1,500,000<br />
Matching Fund Reduction<br />
Check here if requesting a reduction in matching funds requirement pursuant to s.288.06561, F.S.<br />
Timelines<br />
Channel 1C Renewal<br />
Milestone<br />
Projected Date<br />
Final Design and Permitting Kickoff 10/01/2013<br />
Design and Permitting Complete 02/01/2014<br />
Advertise, Receive Bids and Award Contract Complete 03/15/2014<br />
Construction Complete 09/30/2014<br />
138