United Nation Development Programme<br />
Programme <strong>of</strong> Assistance to the Palestinian People<br />
Rehabilitation <strong>of</strong> Daklia Road<br />
PAL 10-00071488<br />
<strong>Bill</strong> <strong>of</strong> <strong>Quantity</strong> (<strong>BOQ</strong>)
PREAMBLE TO BILL OF QUANTITY (<strong>BOQ</strong>)<br />
1. GENERAL<br />
The nature <strong>of</strong> this contract is re-measured unit price contract and the <strong>Bill</strong> <strong>of</strong> <strong>Quantity</strong><br />
(<strong>BOQ</strong>) shall reflect this fact.<br />
<strong>BOQ</strong> shall be read and construed in conjunction with other Contract Documents.<br />
General directions and description <strong>of</strong> work and material given in the Technical<br />
Specification are not necessarily repeated in the <strong>Bill</strong> <strong>of</strong> <strong>Quantity</strong>. The Technical<br />
Specification forms an integral part <strong>of</strong> the <strong>Bill</strong> <strong>of</strong> <strong>Quantity</strong>.<br />
The Tenderer is obliged to check the number <strong>of</strong> the pages <strong>of</strong> the <strong>Bill</strong> <strong>of</strong> <strong>Quantity</strong> and<br />
should any be found missing or duplicated or the figures <strong>of</strong> writing indistinct, the Tenderer<br />
must notify the Employer/Engineer at once and have the matter rectified before the Tender<br />
is submitted. No liability whatsoever will be accepted in respect <strong>of</strong> any claim for errors in<br />
the Tenderer’s <strong>of</strong>fer resulting from failure to comply with the fore-going.<br />
The Tenderer is deemed to have visited the site/s and fully acquainted himself as to the<br />
location <strong>of</strong> each <strong>of</strong> the items and works to be carried out and to all conditions which may<br />
affect the performance <strong>of</strong> the works, including but not limited to:<br />
Access for the storing dump site and <strong>UNDP</strong> crushing site as well as access to<br />
required services<br />
Restrictions applicable to working in GAZA Strip area.<br />
All safety regulations and employer site safety procedures.<br />
All Palestinian regulations.<br />
The Tenderer is also deemed to have surveyed the actual condition <strong>of</strong> the site and buildings<br />
and made his own assessment <strong>of</strong> the type and extent <strong>of</strong> the works prior to submitting his<br />
<strong>of</strong>fer.<br />
2. QUANTITIES<br />
Although practical care was exercised in preparing the <strong>BOQ</strong>, all quantities given herein<br />
shall be deemed to be estimated quantities <strong>of</strong> the work to be done. They are not to be taken<br />
as actual and correct quantities <strong>of</strong> the work to be executed and they do not absolve the<br />
contractor <strong>of</strong> his obligations under the Contract. At any time, the actual quantities increase<br />
or decrease, hence, it is understood that the actual quantities increase or decrease is<br />
expected risk and no claim whatsoever will be taken into consideration for extra cost in<br />
that respect by employer. Any claim whatsoever submitted for cost or extra expenses<br />
incurred from such increase or decrease will not be accepted by Employer/Engineer except<br />
where else stipulated in the Contract.<br />
3. MATERIALS<br />
All materials used are to be <strong>of</strong> the best new available, subject to the Employer/Engineer<br />
approval, durable nature, guaranteed, not liable to any base exchange and manufactured<br />
Contractor’s signature and stamp Page 2
according to applicable BS, ASTM or DIN Standards. Execution also is subject to<br />
approval <strong>of</strong> Employer/Engineer and shall be in conformance <strong>of</strong> the best available common<br />
practice in engineering codes at the time <strong>of</strong> execution.<br />
Items that contain materials or products <strong>of</strong> special make with names <strong>of</strong> manufacturers are<br />
to be taken as samples <strong>of</strong> what will be required. Subject to the Employer/Engineer<br />
approval, the Contractor may, at his discretion, <strong>of</strong>fer similar products <strong>of</strong> other make if the<br />
equivalent quality <strong>of</strong> the specified materials is obtained. In this case, the Contractor shall<br />
submit a description and/or drawings showing all technical conditions, characteristics,<br />
make, type and address <strong>of</strong> Manufacturer, etc., <strong>of</strong> the materials <strong>of</strong>fered as alternatives.<br />
4. PRICES AND CURRENCY<br />
The prices given, by the Contract, hereunder in the <strong>BOQ</strong> shall be in United States Dollars<br />
or ILS. Furthermore inflation and escalation or changes whatsoever shall not be subject <strong>of</strong><br />
claim later on.<br />
The Unit Prices entered against the various items in the following <strong>Bill</strong> <strong>of</strong> Quantities<br />
include all operation costs for execution, completion and maintenance <strong>of</strong> the various items<br />
<strong>of</strong> the works finished completely in every respect till the final acceptance as specified or<br />
described in the Tender Documents, with or without modifications, either by way <strong>of</strong><br />
additions or deductions, or alterations as may be <strong>of</strong>fered in writing during the progress <strong>of</strong><br />
the works, and include, without being limited to, all what is deemed necessary particularly<br />
referred to in the Tender Documents.<br />
The Unit Price shall cover all costs <strong>of</strong> every kind whatsoever including, without being<br />
limited to, all charges for additional site installations, relocation, supervision, labor,<br />
transportation and supply <strong>of</strong> materials; the provision, maintenance, use and efficient repair<br />
<strong>of</strong> all plant, equipment and appliance <strong>of</strong> every kind, the construction and maintenance <strong>of</strong><br />
all temporary works, the performance <strong>of</strong> all services and the fulfillment <strong>of</strong> all obligations<br />
and responsibilities herein defined.<br />
The Tenderer shall be deemed to have fully considered all the conditions, obligations, and<br />
requirements <strong>of</strong> the Tender Documents before entering the respective unit price against the<br />
various items <strong>of</strong> the <strong>Bill</strong> <strong>of</strong> Quantities.<br />
The Unit Prices given hereunder the <strong>BOQ</strong> shall also include erection, installation, fixing,<br />
and re-fixing <strong>of</strong> all elements. These prices shall also include taxes, visa for labor, gate<br />
passes, accommodations for the Contractor’s staff and labors, all required insurance and<br />
work permits, guarantees, bonds, traffic plan requirements, safety procedures, etc. and all<br />
requirements necessary to have the work maintained until its final handing over.<br />
The Unit Prices given hereunder in the <strong>Bill</strong> <strong>of</strong> <strong>Quantity</strong> for this work shall also include<br />
overheads, risks, pr<strong>of</strong>it etc. and all other financial matters to have all these civil works<br />
completed.<br />
Contractor’s signature and stamp Page 3
The works, materials or activities listed in the following shall always be considered as<br />
supportive works to be included in the Unit Prices bid for any item in the <strong>Bill</strong> <strong>of</strong><br />
Quantities:<br />
<br />
<br />
<br />
<br />
<br />
<br />
<br />
<br />
<br />
<br />
<br />
<br />
Any measurement for execution and payment <strong>of</strong> the works, including the provision <strong>of</strong><br />
measuring instruments, gauges, setting out marks, marking paint and relevant tools,<br />
labor, etc., the maintenance and preservation <strong>of</strong> gauges and setting-out marks during<br />
the execution <strong>of</strong> the works.<br />
Provision <strong>of</strong> small tackle tools or any other equipment required for the execution <strong>of</strong> the<br />
works.<br />
Supply <strong>of</strong> consumable materials for the Contractor’s equipment.<br />
Removal <strong>of</strong> all contamination (refuse, debris, building rubbish and the like) arising<br />
from or in connection with the Contractor’s work to locations approved by the<br />
engineers<br />
Protection <strong>of</strong> the executed works and <strong>of</strong> the items made available for execution <strong>of</strong> the<br />
works from damage, fire, inclement weather, vandalism and theft etc., until the time <strong>of</strong><br />
final acceptance.<br />
Transportation <strong>of</strong> all materials and structural components from the storage places on<br />
site to the points <strong>of</strong> use and return transportation, if required.<br />
Submitting and transporting any samples required.<br />
Carrying out tests on materials and works, etc., that is required by the Engineer.<br />
Fuel and lubricants for operation <strong>of</strong> Contractor’s equipment.<br />
All safety precautions and measures for safeguarding labor as well as securing<br />
surrounding areas.<br />
Lighting <strong>of</strong> the work site.<br />
Maintenance , repair or reconstruct damaged infrastructure resulted by contractor’s<br />
activities<br />
5. RIGHTS OF EMPLOYER<br />
The following rights are reserved to the Employer:<br />
<br />
<br />
<br />
To omit individual items mentioned in the Schedule <strong>of</strong> Prices if not required in the<br />
opinion <strong>of</strong> the Employer and/or to replace them should it be more advantageous to<br />
execute them in another way.<br />
To order execution <strong>of</strong> alternative or provisional items as if they were main items.<br />
To order execution <strong>of</strong> additional works as well as alternatives <strong>of</strong> works, always in<br />
conformity with the conditions outlined in the Contract.<br />
Any order and/or delivery <strong>of</strong> material or equipment by the Contractor for performance <strong>of</strong><br />
the works may only be based on instructions and/or approved execution drawings by the<br />
Employer/Engineer.<br />
Contractor’s signature and stamp Page 4
All equipment and materials for installation and finishing works to be incorporated in this<br />
contract shall prior to ordering and/or delivery by the Contractor, be approved by the<br />
Employer/Engineer both in respect <strong>of</strong> quality and type as well as <strong>of</strong> quantity.<br />
6. SITE ACCESS AND STORAGE<br />
The Tenderer shall visit all sites and ascertain the location <strong>of</strong> required access onto these<br />
sites and the location <strong>of</strong> allowance for complying with the requirements and for the<br />
reinstatement to original condition <strong>of</strong> all roads and areas used or disturbed by the<br />
Contractor to the satisfaction <strong>of</strong> the Engineer.<br />
7. SITE INSTALLATION<br />
All costs <strong>of</strong> labor, works, provisions, materials and equipment for Site Installations<br />
required by the Contractor and stipulated in the Tender Documents shall be included in the<br />
various unit prices <strong>of</strong> the <strong>Bill</strong> <strong>of</strong> Quantities. No extra payment will be allowed by the<br />
Employer for any <strong>of</strong> these activities.<br />
8. DURATION<br />
The total duration <strong>of</strong> the contract is Four (4) calendar months including weekends,<br />
holidays and <strong>of</strong>ficial holidays. Official weekends are Fridays and Saturdays.<br />
9. OTHER CONTRACTOR’S OBLIGATIONS<br />
The Contractor has to submit Detailed Shop Drawings to be approved by the Engineer<br />
before commencement <strong>of</strong> the work, and all required materials should be supplied as<br />
specified and subject to the Engineer approval.<br />
The Contractor has to fix the underground services that may be damaged during his<br />
work.<br />
The Contractor has to maintain the Existing Open Channels flow during construction.<br />
All works has to be done according to the Engineer's instructions, Drawings and<br />
specification.<br />
The Contractor has to repair any damages <strong>of</strong> any services at full satisfaction <strong>of</strong><br />
relevant Service Authority<br />
The contractor has to test on his own expenses, the sub-grade CBR before<br />
commencement <strong>of</strong> work, In case the CBR value less than 15%, then soil replacement<br />
should be applied.<br />
The contractor has to check the upper 30 cm below the top <strong>of</strong> the sub-grade to verify<br />
that they are uniform, and any rubbish material or saturated /wet soil shall be removed<br />
and replaced with suitable material approved by the Engineer ,<br />
NO EXTRA COST SHALL BE PAID FOR SUCH REPLACEMENT<br />
The contractor has to Execute any required side slope according to specifications,<br />
drawings , and Engineer’s instructions<br />
Price will include costs <strong>of</strong> removing and/or relocating <strong>of</strong> all obstacles such as debris,<br />
garbage, trees and existing services in addition to the required materials necessary for<br />
work completion according to engineer's instructions and specifications.<br />
Contractor’s signature and stamp Page 5
The contractor has to coordinate with Municipalities regarding garbage containers<br />
location.<br />
The contractor should include in his price the costs <strong>of</strong> cut and removal <strong>of</strong> trees roots,<br />
backfilling, watering, and compaction in layers with clean sand as specified and<br />
according to the Engineer instructions, the price will also include relocation <strong>of</strong> Power,<br />
Telephone poles and networks to sidewalk.<br />
Price will include costs <strong>of</strong> adjusting the levels <strong>of</strong> existing manholes (in any diameter)<br />
to suit the new situation. Replacing covers, frames, rings if defected and all materials<br />
and work required to complete the task.<br />
The contractor has to remove the existing base coarse during preparation works and<br />
transport it wherever directed by the engineer to the related Municipality.<br />
The price will include costs <strong>of</strong> cutting and removing <strong>of</strong> the existing asphalt pavement<br />
layer and transporting the removed material to a site approved by the Engineer<br />
Prices for excavation item shall include the removal <strong>of</strong> any buried structure not to be<br />
part <strong>of</strong> the proposed roads, including transport <strong>of</strong> excavated, surplus material and<br />
buried structure (not to be part <strong>of</strong> the proposed roads) to a location approved by the<br />
engineer or his representative outside the site, workmanship and anywhere else,<br />
needed, all according to drawings, specifications, conditions and directed instructions<br />
by the Engineer or his representative.<br />
Quantities <strong>of</strong> excavation shall be measured according to the dimensions mentioned in<br />
the drawings(engineering measurements in m 2 )<br />
Back-filling item should be in layers (25cm max. each & compaction test 97%). Prices<br />
shall includes material supply, watering, compacting, transporting, testing and<br />
anywhere else, needed, all according to drawings, specifications, conditions and direct<br />
instructions by the Engineer or his representative.<br />
Suitable clean sand should be used for back-filling in layers (25cm max. each &<br />
compaction test 97%), selected from the approval excavated soil or imported. Prices<br />
shall includes supply, watering, compacting, transporting, testing and anywhere else,<br />
needed, all according to drawings, specifications, conditions and directed instructions<br />
by the Engineer or his representative.<br />
The contractor shall check and ascertain that the Benchmark used by him and its<br />
elevation is accurate and correct in all respects. The contractor shall check the<br />
surveying work. If correction is needed, the contractor has to redo the surveying work<br />
on his own.<br />
Contractor’s signature and stamp Page 6
<strong>Bill</strong> <strong>of</strong> <strong>Quantity</strong> <strong>of</strong> Daklia Road<br />
<strong>Bill</strong> No 1: Roads Works<br />
Rehabilitation <strong>of</strong> Daklia Road<br />
Item<br />
No.<br />
Description Unit Qty.<br />
- The Contractor has to submit Detailed Shop<br />
Drawings to be approved by the Engineer before<br />
commencement <strong>of</strong> the work, and all required<br />
materials should be supplied as specified and subject<br />
to the Engineer approval.<br />
- The Contractor has to fix the under ground services<br />
that may be damaged during his work.<br />
- The Contractor should include in his price the costs<br />
<strong>of</strong> sampling and testing as required and according to<br />
technical specifications and work requirement.<br />
- Price will include costs <strong>of</strong> removing and/or<br />
relocating <strong>of</strong> all obstacles such as debris, garbage,<br />
trees and existing services in addition to the required<br />
materials necessary for work completion according<br />
to engineer's instructions and specifications.<br />
- The Contractor should include in his price the costs<br />
<strong>of</strong> cut and removal <strong>of</strong> trees roots, backfilling,<br />
watering, and compaction in layers with clean sand<br />
as specified and according to the Engineer<br />
instructions, the price will also include relocation <strong>of</strong><br />
Power, Telephone poles and networks to sidewalk.<br />
- Price will include costs <strong>of</strong> adjusting the levels <strong>of</strong><br />
existing manholes (in any diameter) to suit the new<br />
situation. Replacing covers, frames, rings if defected<br />
and all materials and work required to complete the<br />
task.<br />
- The price will include costs <strong>of</strong> cutting and<br />
removing <strong>of</strong> the Existing Asphalt pavement layer<br />
and transporting the removed material to a site<br />
approved by the Engineer<br />
Unit<br />
Price<br />
(US$)<br />
Total<br />
(US$)<br />
1.1<br />
Clean, excavate, cut and fill sidewalks with clean<br />
dune sand from natural ground level to the bottom<br />
<strong>of</strong> the sub-base layer design level for carriageway<br />
and 23cm under the top face <strong>of</strong> the curb stone for<br />
sidewalks including watering, compaction not less<br />
than 97% & CBR not less than 15% ,all according to<br />
drawing and technical specifications .The price<br />
include dismantle existing curbstone if exist and<br />
receive to municipality stores & remove all existing<br />
block fences or others which objected the execution<br />
<strong>of</strong> works in carriageway or sidewalks., all according<br />
to drawing and technical specifications . All tests as<br />
per specifications & Engineer Instructions.<br />
m 2 3300<br />
Contractor’s signature and stamp Page 7
Item<br />
No.<br />
1.2<br />
1.3<br />
1.4<br />
1.5<br />
1.6<br />
Description Unit Qty.<br />
Supply and lay approved sub-base material (<br />
Kurkar) <strong>of</strong> 15 cm thickness for the sidewalks in one<br />
layer with CBR.> 30%, watering and compaction up<br />
to 98% maximum dry density according to modified<br />
proctor test. the work includes all tests as per<br />
specifications & Engineer Instructions<br />
Supply & lay pre-cast concrete curbstones for<br />
sidewalks (15x30x80 cm) including all necessary<br />
excavations, compaction to 98% <strong>of</strong> MDD and<br />
compacted Existing crushed stone 15 cm thick,<br />
B250 plain concrete foundation (27x12cm) under<br />
the curb and (12x21cm) behind, spreading 2 cm<br />
mortar under the curb, filling joints between curbs<br />
with cement mortar and painting with one prime<br />
coat and two finishing coats <strong>of</strong> approved brand<br />
name painting material ,expansion joint every 12 mr<br />
with selotex board and filling 3cm with seka flex<br />
,all according to drawing and technical<br />
specifications.<br />
Supply, install and compact <strong>of</strong> interlock tiles 8 cm<br />
thick, The price include supply and spread dune<br />
sand 5 cm thick under interlock, all the required<br />
tests, all works are according to specifications,<br />
Drawings and Engineer instructions.<br />
Construct reinforced concrete retaining walls, beams<br />
or any structural element as instructed by the<br />
Engineer including all necessary excavations &<br />
filling dune sand to the required level, B300<br />
concrete & expansion joint at 12m interval with<br />
selotex board all in accordance with the<br />
specification & drawings.<br />
Supply and construct storm water collection gullies<br />
with length <strong>of</strong> 3.0m at least, as detailed in drawings<br />
constructed <strong>of</strong> reinforced concrete B300 , including<br />
cast iron grills, benching, excavation and<br />
backfilling with clean sand and compaction, remove<br />
the surplus soil to the tip as shown in the drawings<br />
and according to the specifications and the<br />
engineer’s instructions.<br />
m 2 3300<br />
L.m 1100<br />
m 2 5500<br />
m 3 25<br />
No 6<br />
Unit<br />
Price<br />
(US$)<br />
Total<br />
(US$)<br />
Contractor’s signature and stamp Page 8
Item<br />
No.<br />
1.7<br />
1.8<br />
1.9<br />
1.10<br />
Description Unit Qty.<br />
Supply, install, UPVC pipes 315 mm outside<br />
diameter SN8 with wall thickness 9.20mm for outlet<br />
drain with watertight and flexible joints sealed with<br />
approved gasket rubber ring including dewatering,<br />
excavation in any ground, shoring, shuttering, safety<br />
measures, testing, providing specified bedding<br />
backfilling .The pipe should be bedded and covered<br />
with at least 20 cm <strong>of</strong> clean dune sand around and at<br />
the top and bottom <strong>of</strong> the pipe . The kurkar will be<br />
used for backfilling the rest <strong>of</strong> the trench in layers<br />
not exceeding 20cm, with compaction not less than<br />
98 % , up to the design leveling <strong>of</strong> the roads,<br />
leveling the roads after backfilling, leveling <strong>of</strong> the<br />
roads after backfilling, take away the surplus soil to<br />
tip and all other accessories, trial trenches to locate<br />
the existing services supporting them as necessary<br />
all as specified.<br />
Adjust level <strong>of</strong> existing Line or Manholes (Sewer,<br />
Water, Telephone, Storm water, etc.) to the required<br />
level. The work includes decreasing the height <strong>of</strong><br />
manholes by demolishing the extra parts or<br />
increasing the height by supplying & installing<br />
precast concrete ring B300, in cast the height more<br />
than 30 cm, otherwise casting <strong>of</strong> concrete may be<br />
used, also include( if need) cast iron cover 25 ton<br />
with the word sewer in English & Arabic) and all<br />
required materials. The work also includes cleaning<br />
<strong>of</strong> existing manholes & lines.<br />
Supply and cast concrete B250 for poles base<br />
Dimension (110x110x100 cm) the work include<br />
excavation , shuttering , supplying and installing hot<br />
galvanized steel pole base for 12 m poles, the work<br />
include supplying and fixing a 3" sharshori conduits<br />
with a rope inside it in the base ,nuts , wishers and<br />
all required accessories required to complete the job,<br />
all according to drawings, specifications and<br />
engineer instructions.<br />
Supply and install 3" sharshori conduit with a rope<br />
inside it , the work include Excavation ,backfilling<br />
on layers 20 cm thick <strong>of</strong> dune sand with compacting<br />
to 98 % MDD. The price including for any depth<br />
excavation( at least 1.0 m from the face <strong>of</strong> sidewalk<br />
pavement), laying and re-back filling with suitable<br />
Materials also included electrical warning tape.<br />
Total Roads Works<br />
L.m 200<br />
Unit 40<br />
Unit 28<br />
L.M 1100<br />
Unit<br />
Price<br />
(US$)<br />
Total<br />
(US$)<br />
Contractor’s signature and stamp Page 9
<strong>Bill</strong> No 2: Water works<br />
Item<br />
No. Description Unit Qty.<br />
2<br />
_All works must be coordinated with the water<br />
department at the Municipality and all testes need<br />
to be included.<br />
_ All executed works must be documented in as<br />
Built Drawings, connected By Total station with<br />
sample presented <strong>of</strong> GIS municipality department,<br />
also observe all existing points coordination. ( This<br />
mission will be finished by Approval Surveying<br />
<strong>of</strong>fice).<br />
_The price includes the cost <strong>of</strong> excavation to depth<br />
indicated in drawings using retaining shuttering,<br />
shoring according to instructions <strong>of</strong> Engineer,<br />
bedding <strong>of</strong> 20 cm clean dune sand under around<br />
and above the pipe with compaction, backfilling the<br />
rest <strong>of</strong> the trench up to design level with kurkar in<br />
layers 20cm thick each with compaction 98% MDD<br />
and all required tests.<br />
_The work includes removal <strong>of</strong> the surplus<br />
materials outside the site to places as instructed by<br />
the Engineer.<br />
_Supply and installation <strong>of</strong> elbows with any angles,<br />
Tees, Flanges, joints, metallic warning tap, and<br />
other accessories and thrust blocks according to<br />
details.<br />
The covers <strong>of</strong> manholes are made <strong>of</strong> cast iron with<br />
diameter 60 cm engraved by the word " Water " in<br />
English and Arabic. the ring is from cast iron<br />
square shaped with 70*70 cm dimensions. the<br />
concrete which used around the ring is B350 and<br />
should have a Basalts layer <strong>of</strong> 2 cm above the<br />
concrete and around the cover rings. According to<br />
drawings, specifications and Engineer’s instruction.<br />
_Depth <strong>of</strong> trench is 1.4 m in carriage way and 1.1m<br />
in shoulders.<br />
_The price includes cutting the existing asphalt (if<br />
any) in suitable width using machine and reinstate<br />
the road to its original condition using two layers <strong>of</strong><br />
base coarse 15 cm each, supply and spread prime<br />
coat layer (MCO) under the new asphalt layer, and<br />
spread RC2 between the new and the existing<br />
asphalt and the asphalt layer shall be 6 cm thick. In<br />
case the existing pavement is interlock tiling items<br />
should include removal and re-tiling interlock<br />
pavement to the original state including all required<br />
material to complete the pavement layers such as<br />
base coarse, interlock and sand ..etc.<br />
_ The price should include the connection <strong>of</strong> the<br />
new pipes to the existing pipes with all needed<br />
fitting and support to complete the work<br />
Unit<br />
Price<br />
(US$)<br />
Total<br />
(US$)<br />
Contractor’s signature and stamp Page 10
2.1<br />
2.2<br />
2.3<br />
successfully.<br />
-The price include putting magnetic water tape<br />
above the water pipes.<br />
Supply, install 110 mm outside diameter<br />
UPVC Pipes with wall thickness 4.2 mm water<br />
pipes PN 10 . The price should include<br />
excavation <strong>of</strong> the trench 1 m from the design<br />
level <strong>of</strong> the sidewalk, the pipe should be<br />
bedded and covered with at least 20 cm <strong>of</strong><br />
clean dune sand around and at the top and<br />
bottom <strong>of</strong> the pipe , The remaining depth <strong>of</strong> the<br />
trench will be filling with kurkar in layers not<br />
exceeding 20cm each, with compaction not<br />
less than 98 % , up to the design leveling <strong>of</strong> the<br />
road or sidewalk .All works are performed<br />
according to the drawings, specifications and<br />
Engineer’s instruction.<br />
Supply and install 125 cm internal diameter<br />
precast circular reinforced concrete water<br />
manholes, complete with B300 cast in place<br />
reinforced concrete base, cast iron cover (25ton<br />
Capacity), Frame, ring's , the concrete which is<br />
to be used around the ring is B350 for at least<br />
30cm width and depth, Basalt layer <strong>of</strong> 2 cm<br />
thick above the concrete and around the cover<br />
to fix the ring should be supplied and installed,<br />
cast iron steps @ 30cm maximum, excavation<br />
in any type <strong>of</strong> soil to any depth , backfilling<br />
with clean dune sand and compaction 98%<br />
MDD up to the design leveling <strong>of</strong> the roads,<br />
drainage opening with aggregate bed, two<br />
external hot bitumen coating (75/25). Price<br />
shall include all required tests. The price<br />
includes supply and install 4" Gate valve 16<br />
bar working pressure including all needed<br />
fittings, nibbles ,reducers, steel Tee's 16 bar<br />
pressure(T8''x8''x4'') and support to complete<br />
the works successfully. Price shall include all<br />
required tests and all work as per drawings,<br />
specification and Engineer instruction<br />
Connect the proposal water network with<br />
existing water network. The price include<br />
Supply & Install all Flanges, 16 bar Pressure<br />
for Steel Tees ( T12''x12''x4''), ( T6''x6''x4'') &<br />
all fittings required. Price shall include all<br />
required tests and all work as per drawings,<br />
specification and Engineer instruction.<br />
Total <strong>of</strong> Water works<br />
L.M 1200<br />
Unit 2<br />
L.S 1<br />
Contractor’s signature and stamp Page 11
Rehabilitation <strong>of</strong> Daklia Road<br />
PAL10-00071488<br />
Summary:<br />
Description<br />
Total (US$)<br />
Total Roads Works<br />
Total <strong>of</strong> Water works<br />
Grand Total (US$) – Not including Value<br />
Added Tax (VAT)<br />
Grand Total (in letters):-------------------------------------------------------------<br />
Contractor’s Name:------------------------------------------------------------------<br />
Signature and Stamp:----------------------------------------------------------------<br />
Date:-------------------------------------------------------------------------------------<br />
Contractor’s signature and stamp Page 12