02.11.2012 Views

THE ECHO - Ferrostaal

THE ECHO - Ferrostaal

THE ECHO - Ferrostaal

SHOW MORE
SHOW LESS

You also want an ePaper? Increase the reach of your titles

YUMPU automatically turns print PDFs into web optimized ePapers that Google loves.

12 <strong>THE</strong> <strong>ECHO</strong> August 2007<br />

13<br />

NEWS<br />

Construction of a compressor station in Thailand<br />

Whenever a new source of fossil fuels is found, the question<br />

arises of how to deliver the gas to consumers<br />

quickly and in a form that meets their needs. It was against<br />

this background that the partially state-run Thai oil and gas<br />

utility PPT Public Company Ltd. commissioned MAN <strong>Ferrostaal</strong><br />

with the construction of a compressor station in Map<br />

Tha Put. Gas turbine compressors are designed to prevent bottlenecks<br />

in supply, and primarily have a storage function.<br />

Timely completion of the compressor station in Map Tha Put<br />

The new compressor station forms part of the Third Transmission<br />

Pipeline Project. This entails linking two newlytapped<br />

offshore gas fields located off the Thai coast with onshore<br />

consumers by means of pipelines. The MAN <strong>Ferrostaal</strong><br />

specialists had a period of only 18 months between the date<br />

the contract came into effect and the mechanical completion<br />

of the plant in December 2006.<br />

The scope of the contract encompassed engineering work and<br />

the delivery of equipment. It also included technical documentation<br />

as well as construction, assembly and commissioning<br />

measures. Having established a “Bangkok Branch” especially<br />

for this project, MAN <strong>Ferrostaal</strong>, in conjunction with<br />

local building contractor IBC, operated as part of an open consortium.<br />

In this regard, 85 per cent of the joint and several<br />

liability was carried by MAN <strong>Ferrostaal</strong> and 15 per cent by IBC.<br />

The contractual obligations of IBC, the consortium partner,<br />

comprised construction and assembly work as well as customer<br />

invoicing. The plant-specific engineering measures<br />

were carried out by the Bangkok-based Worley Parsons Ltd.<br />

under the project leadership of MAN <strong>Ferrostaal</strong>.<br />

In order to ensure that the schedule proceeded smoothly,<br />

the entire MAN <strong>Ferrostaal</strong> Project Task Force was based in<br />

Thailand. They were always located at the relevant project<br />

“hotspot”, that is, Bangkok and later Map Tha Put, thus enabling<br />

the company and IBC to adhere precisely to the deadline<br />

for mechanical completion. The customer assumed<br />

complete control of the entire compressor station subsequent<br />

to a 30-day performance test phase under continuous<br />

operation.<br />

On the basis of work done and the superior levels of constructive<br />

cooperation achieved with our customer PPT, MAN<br />

<strong>Ferrostaal</strong> is confident that the foundation has been set for<br />

further common projects in Thailand.<br />

Specifications<br />

Flow rate: 1,200 MMSCFD<br />

Gas inlet pressure/temperature: 42 bar (g) at +35 °C<br />

Gas outlet<br />

pressure/temperature: 86 bar (g) at < +52 °C<br />

Turbines/compressors: 3 x 21 MW gas turbines RB211<br />

6562 DLE (Rolls-Royce) with RB45<br />

centrifugal compressors (MAN<br />

TURBO); turbines are operated with<br />

gas from import pipeline<br />

Design: 3 compressors (2 in operation, 1 on<br />

standby) with intake-side gas filters<br />

and pressure-side gas coolers as<br />

well as a separate flare system<br />

Energy supply: Transformer in existing sub-station<br />

plus diesel generator for emergency<br />

power<br />

Control system: Digital control system (DCS) and<br />

electrostatic discharge (ESD) with<br />

local operation and remote control<br />

from the control room<br />

Clean air for a radiation-free future<br />

The decommissioning of nuclear<br />

power stations means that we are<br />

faced with a difficult long-term legacy.<br />

After an operational life of 21 years, the<br />

Jülich Experimental Reactor, one of<br />

the first nuclear reactors in Germany,<br />

was finally shut down in 1988. Since<br />

then, the reactor site has gradually<br />

been returned to a greenfield state. The<br />

specially built material lock on the reactor<br />

building plays a central role in<br />

this process. It ensures the safe containment<br />

of radioactively contaminated<br />

reactor components which are<br />

sealed in the lock. The lock’s ventilation<br />

system must be steadily adapted<br />

in keeping with the decommissioning<br />

process.<br />

At the end of 2004, MAN <strong>Ferrostaal</strong><br />

won the contract from the Jülich Experimental<br />

Reactor Consortium to<br />

build new ventilation systems and a<br />

chimney flue with an activity monitoring<br />

system. The contract was worth<br />

around 2.5 million euros. The systems<br />

were delivered to the operator on<br />

schedule at the end of 2006.<br />

The new ventilation systems were deployed<br />

inside the material lock. To this<br />

end, the waste air of the new ventilation<br />

system has been merged with the<br />

rest of the plant’s waste air via parallel<br />

filtering units containing prefilters and<br />

air filters. This is then discharged into<br />

the atmosphere via a newly erected 65metre-high<br />

chimney flue.<br />

Bioshield and water tower; material lock with chimney flue<br />

The chimney flue itself is equipped<br />

with an integrated activity monitoring<br />

system. This system allows isokinetic<br />

samples to be taken and can also be<br />

used to measure the volumetric flow<br />

and continuously monitor and control<br />

the waste air for radioactive particles<br />

such as tritium or C14. MAN <strong>Ferrostaal</strong><br />

also installed all the new instrumenta-<br />

tion and control equipment for the<br />

ventilation systems. All the on-site<br />

work was carried out exclusively by<br />

personnel who had received special<br />

training in radiation protection.

Hooray! Your file is uploaded and ready to be published.

Saved successfully!

Ooh no, something went wrong!