WMC EHS Management System <strong>Major</strong> <strong>Hazard</strong> <strong>Standard</strong><br />

<strong>Permit</strong> <strong>to</strong> <strong>Work</strong><br />

• Ensuring copies of all <strong>Work</strong> <strong>Permit</strong>s are<br />

maintained in the <strong>Permit</strong> Office<br />

• Handing-over the control of active <strong>Work</strong><br />

<strong>Permit</strong>s <strong>to</strong> a new shift <strong>Permit</strong> Issuer<br />

• Initiating removal of hazard controls<br />

following hand back of the <strong>Work</strong> <strong>Permit</strong><br />

• Authorising closure of the <strong>Work</strong> <strong>Permit</strong><br />

by signing off on both original and<br />

duplicate copies of the <strong>Work</strong> <strong>Permit</strong><br />

• Filing <strong>Work</strong> <strong>Permit</strong> documentation<br />

originals in compliance with WMC<br />

Resources document retention policy.<br />

8.2 Isola<strong>to</strong>r<br />

Competency required:<br />

• Maintaining a technical and / or<br />

legislative ability <strong>to</strong> be able <strong>to</strong> perform<br />

and prove isolations<br />

• A competent knowledge of the isolation<br />

requirements for specific plant or<br />

equipment<br />

• A general knowledge of the <strong>Permit</strong> <strong>to</strong><br />

<strong>Work</strong> System and a competent<br />

knowledge of the Isolations Procedure.<br />

Is responsible for:<br />

• Establishing isolations of plant or<br />

equipment according <strong>to</strong> the Isolation<br />

Certificate/Instruction <strong>to</strong> prevent<br />

inadvertent re-energisation which may<br />

cause injury <strong>to</strong> others or damage <strong>to</strong> plant<br />

or equipment<br />

Note: In the situation in which the <strong>Permit</strong><br />

Issuer performs the role of the Isolation<br />

Checker, the Isola<strong>to</strong>r shall confirm that<br />

the <strong>Permit</strong> Issuer defined Isolation<br />

Certificate/Instruction is appropriate for<br />

the defined scope of work.<br />

• De-isolating equipment according <strong>to</strong><br />

<strong>Permit</strong> Issuer requirements.<br />

8.3 Isolation Checker<br />

Competency required:<br />

• Achieving the competency of an Isola<strong>to</strong>r.<br />

Is responsible for:<br />

• Confirming that the <strong>Permit</strong> Issuer defined<br />

Isolation Certificate / Isolation Instruction<br />

is appropriate for the defined scope of<br />

work<br />

• Validating that isolation of energies has<br />

been completed according <strong>to</strong> the<br />

requirements of the Isolation<br />

Certificate/Isolation Instruction and the<br />

Isolation Procedure.<br />

8.4 Service Provider / <strong>Permit</strong> Reques<strong>to</strong>r<br />

Competency required:<br />

• A knowledge of the <strong>Permit</strong> <strong>to</strong> <strong>Work</strong><br />

System<br />

• Understanding the work planning<br />

processes.<br />

Is responsible for:<br />

• Developing a clear scope of work<br />

• Making the initial determination of hazard<br />

controls required for work <strong>to</strong> proceed and<br />

initiating <strong>Work</strong> <strong>Permit</strong> documentation.<br />

8.5 <strong>Permit</strong> Accep<strong>to</strong>r<br />

Competency required:<br />

• A competent knowledge of the work <strong>to</strong> be<br />

completed as per the scope of work<br />

• A knowledge of the <strong>Permit</strong> <strong>to</strong> <strong>Work</strong><br />

System<br />

• A competent knowledge of requirements<br />

for Certificates that they will accept.<br />

Is responsible for:<br />

• Signing the permit acceptance on the<br />

<strong>Work</strong> <strong>Permit</strong> once they understand the<br />

extent of hazard controls that have been<br />

established<br />

• Retaining the original of <strong>Work</strong> <strong>Permit</strong><br />

documentation in the <strong>Permit</strong> Control<br />

Board at the work site<br />

WMC-EHS-MHS-007 DocsOpen Ref : 155520 Issued: 23/12/03 Page 12 of 59