28.10.2014 Views

Concept Development - Windward Community College Library

Concept Development - Windward Community College Library

Concept Development - Windward Community College Library

SHOW MORE
SHOW LESS

Create successful ePaper yourself

Turn your PDF publications into a flip-book with our unique Google optimized e-Paper software.

LEARNING RESOURCE CENTER<br />

PROJECT DEVELOPMENT REPORT<br />

VOLUME I: PLANNING & CONCEPT DEVELOPMENT<br />

PROJECT NO. CC-02-6188<br />

APRIL 2004<br />

1357 KAPIOLANI BOULEVARD<br />

HONOLULU, HAWAII 96814


VOLUME I CONTENTS<br />

I. INTRODUCTION<br />

A. PROJECT DESCRIPTION<br />

B. OBJECTIVES OF THE PROJECT DEVELOPMENT REPORT<br />

C. ELEMENTS OF THE PROJECT DEVELOPMENT REPORT<br />

D. PROJECT METHODOLOGY<br />

Figure 1 Existing Land Use<br />

II.<br />

SUMMARY OF GENERAL PLANNING REFERENCES<br />

A. INTRODUCTION<br />

B. PLANNING DOCUMENTS<br />

1. Plan Review Use Resolution<br />

2. Master Plan Report Dated April 22, 1989<br />

3. Urban Design Guidelines Dated November 30, 1995<br />

4. Parking Implementation Plan<br />

5. State Historical Preservation<br />

6. Environmental Assessment<br />

C. WINDWARD COMMUNITY COLLEGE – EXISTING CONDITIONS<br />

1. Overall Campus Land Use<br />

2. Vehicular Circulation and Parking<br />

3. Pedestrian Circulation<br />

4. Landscaping and Open Space<br />

5. Views<br />

6. Site Utilities<br />

Figure II.1<br />

Figure II.2<br />

Figure II.3<br />

Figure II.4<br />

Existing Land Use<br />

Existing Vehicular Pedestrian Circulation<br />

Existing Vegetation & Open Space<br />

Existing Underground Utilities<br />

III.<br />

THE LEARNING RESOURCE CENTER<br />

A. OVERVIEW OF THE PLANNING AND DESIGN PROCESS<br />

B. LIBRARY OF THE FUTURE/VISION


C. PROJECT SUCCESS CRITERIA/GOALS<br />

1. Planning<br />

2. Technology<br />

3. <strong>Library</strong> Environments<br />

D. FACILITIES PROGRAM: Exhibit III.1 – SUMMARY OF SPATIAL<br />

REQUIREMENTS<br />

E. CITY & COUNTY OF HONOLULU LAND USE ORIDNANCE:<br />

PRELIMINARY ZONING INFORMATION<br />

1. Preliminary Zoning Information<br />

2. Exhibit III.2 Parking Stall Summary<br />

3. Exhibit III.3 Parking Stall Calculation<br />

F. PRELIMINARY BUILDING CODE ANALYSIS<br />

1. Applicable Building Code<br />

2. Occupancy Groups<br />

3. Type of Construction<br />

4. Allowable Areas<br />

5. Allowable Building Height<br />

6. Occupancy Separation<br />

7. Fire Resistive Requirements for Building Elements<br />

G. FINAL CONCEPT DESIGN (EARLY SCHEMATICS)<br />

1. Site Analysis<br />

2. Architectural Design <strong>Concept</strong><br />

H. ENVIRONMENTAL ANALYSIS<br />

Figure III.1.1 Topography<br />

Figure III.1.2 Existing Underground Utilities<br />

Figure III.1.3 Sun/Wind<br />

Figure III.1.4 Existing Overhead Utilities<br />

Figure III.1.5 Site Amenities<br />

Figure III.2.1 Aerial Perspective<br />

Figure III.2.2 Site Plan February<br />

Figure III.2.3 First Level Floor Plan<br />

Figure III.2.4 Second Level Floor Plan<br />

Figure III.2.5 Third Level Floor Plan<br />

Figure III.2.6 Site Section Looking North<br />

Figure III.2.7 Building Section A-A Looking South<br />

Figure III.2.8 Building Section B-B Looking North<br />

Figure III.2.9 East Site Elevation<br />

Figure III.2.10 Exterior Building Elevations, West and East<br />

Figure III.2.11 Exterior Building Elevations, North and South


IV.<br />

PRELIMINARY ENGINEERING DESIGN CRITERIA<br />

A. INTRODUCTION<br />

B. SUMMARY OF EXISTING SITE CONDITIONS AND UTILITIES<br />

1. Overview<br />

2. Parking, Circulation and Accessibility<br />

3. Site Grading<br />

4. Geotechnical Survey<br />

5. Water System<br />

6. Wastewater System<br />

7. Storm Drainage System<br />

8. Sustainable Design<br />

C. LANDSCAPE<br />

1. Overview<br />

2. Design Parameters<br />

3. Plant List<br />

4. Irrigation System<br />

D. STRUCTURAL ENGINEERING<br />

1. Overview<br />

2. Design Criteria<br />

E. MECHANICAL ENGINEERING<br />

1. Overview<br />

2. HVAC<br />

3. Plumbing<br />

4. Fire Protection<br />

5. Sustainable Design<br />

F. ELECTRICAL ENGINEERING<br />

1. Overview<br />

2. HECO Requirements<br />

3. Existing Site Conditions<br />

4. On-Site Power & Communications<br />

5. Design Criteria<br />

6. Sustainable Design<br />

Figure IV.1<br />

Figure IV.2<br />

Figure IV.3<br />

Figure IV.4<br />

Figure IV.5<br />

New Parking<br />

Barrier Free <strong>Concept</strong> Plan<br />

Water Supply Proposed Relocation<br />

Proposed Wastewater Relocation<br />

Storm Water Proposed Relocation


V. SUSTAINABLE DESIGN GUIDELINES<br />

A. OVERVIEW<br />

Exhibit V.1 LEED® Certification Summary<br />

VI.<br />

VII.<br />

VIII.<br />

IMPLEMENTATION & STATEMENT OF PROBABLE CONSTRUCTION<br />

COST<br />

Exhibit VI.1 Statement of Probable Construction Cost<br />

REFERENCES<br />

APPENDICES<br />

APPENDIX A:<br />

APPENDIX B:<br />

APPENDIX C:<br />

APPENDIX D:<br />

APPENDIX E:<br />

PLAN REVIEW USE (PRU) ASSESSMENT AND CITY<br />

AND COUNTY OF HONOLULU REVIEW COMMENTS<br />

INTERACTIVE WORKSHOP NOTES AND DOCUMENTS<br />

MEETING NOTES<br />

COPY OF WINDWARD COMMUNITY COLLEGE<br />

ENVIRONMENTAL ASSESSMENT<br />

CORRESPONDENCE – STATE HISTORIC<br />

PRESERVATION including:<br />

1. Alternate Site Plans<br />

2. Rendering of Proposed Building and Its Impact on<br />

Site


The Learning Resource Center at <strong>Windward</strong> <strong>Community</strong> <strong>College</strong><br />

PROJECT DEVELOPMENT REPORT<br />

I. INTRODUCTION<br />

A. Project Description<br />

The Physical Facilities, Planning and Construction Office for the <strong>Community</strong><br />

<strong>College</strong>s of the University of Hawaii has contracted LEO A DALY to prepare a<br />

Project <strong>Development</strong> Report (PDR) for The Learning Resource Center at<br />

<strong>Windward</strong> <strong>Community</strong> <strong>College</strong> in Kaneohe, Hawaii. The proposed facility will<br />

house the <strong>Library</strong>, The Learning Center (TLC), Computing Services, Instructional<br />

Media Services, and administrative and support areas. These departments are<br />

currently located in separate facilities throughout the campus, and will be<br />

integrated into a new single facility which will optimize space and staff through<br />

efficient sharing of common areas.<br />

A Plan Review Use (PRU) application and related Master Plan documents were<br />

approved by a Resolution of the City and County Council of Honolulu in 1994.<br />

The Learning Resource Center is envisioned as a two-three-story structure with<br />

sloped clay tile roofs and a stucco exterior in keeping with the Spanish<br />

Mediterranean architectural style already established on the campus. The<br />

proposed facility is located on the same site designated in the approved Master<br />

Plan for the campus. The proposed net floor area is approximately 63,000<br />

square feet; projected gross floor area is approximately 81,793 square feet.<br />

B. Objectives of the Project <strong>Development</strong> Report<br />

The Project <strong>Development</strong> Report has the following goals:<br />

• to verify, document and refine the space and adjacency requirements<br />

established in the Educational Specifications.<br />

• to prepare an architectural design concept implementing the Program Plan,<br />

which is compliant with guidelines for governmental regulations and<br />

standards for accessibility, as well as compliance with historical, aesthetic,<br />

environmental, sustainable and utility considerations.<br />

• to prepare a preliminary cost estimate for both the design and the<br />

construction of The Learning Resource Center.<br />

• to publish a report documenting the planning and design criteria.<br />

• to accomplish all of the above within the guidelines and provisions of the<br />

approved Plan Review Use resolution and related Five-Year Master Plan and<br />

Urban Design Guidelines for <strong>Windward</strong> <strong>Community</strong> <strong>College</strong>.<br />

C. Elements of the Project <strong>Development</strong> Report<br />

The two-volume Project <strong>Development</strong> Report is organized as follows:<br />

University of Hawaii <strong>Community</strong> <strong>College</strong>s April 2004<br />

Project No. CC-02-6188 I-1


The Learning Resource Center at <strong>Windward</strong> <strong>Community</strong> <strong>College</strong><br />

PROJECT DEVELOPMENT REPORT<br />

Volume I: Planning and <strong>Concept</strong> <strong>Development</strong><br />

• Summary of Documents and Conditions Guiding the Planned Facility<br />

• Summary of Program Planning<br />

• Implications of Land Use Ordinance Requirements<br />

• Preliminary Building Code Analysis<br />

• Early Schematic <strong>Concept</strong> Design of the Facility<br />

• Environmental Analysis of the Facility<br />

• Preliminary Engineering Design Criteria<br />

• Sustainable Design Guidelines<br />

• Implementation Schedule<br />

• Probable Construction Cost<br />

• References<br />

• Appendices<br />

Volume II: Program Planning<br />

• Requirements for the Learning Resource Center and the Campus in General<br />

• Summary of Assignable and Non-Assignable Square Footage Requirements<br />

by Building Function<br />

• Functional Relationship Diagrams Denoting Space Requirements and<br />

Adjacencies<br />

• Program Characteristics with Descriptions of Area Uses, Design<br />

Considerations, and Furniture and Equipment Quantities and Dimensions<br />

D. Project Methodology<br />

The objectives of this Project <strong>Development</strong> Report were accomplished by<br />

following a work plan that included the following events, some of which occurred<br />

sequentially, others in parallel with one another:<br />

Meetings with the <strong>Windward</strong> <strong>Community</strong> <strong>College</strong> Directors/Coordinators of the<br />

four areas comprising the new Learning Resource Center: the <strong>Library</strong>, The<br />

Learning Center (TLC), Computing Services, and Instructional Media Services to<br />

determine the programming requirements of each.<br />

• Compilation of the Educational Specifications for all four areas by the Head<br />

Librarian.<br />

• Site trips to mainland libraries led by LEO A DALY’s expert in the planning and<br />

design of libraries.<br />

• Site studies through photographs and physical measurements.<br />

• Meetings with the Physical Facilities, Planning and Construction Office for the<br />

<strong>Community</strong> <strong>College</strong>s of the University of Hawaii, The State Historic Office of<br />

Preservation, the State OEQC Environmental Assessment Planner, the City<br />

Plan Review Use (PRU) Planner, the Fire Marshall of the City and County of<br />

Honolulu, members of the Outdoor Circle’s Kaneohe, Hawaii Branch.<br />

University of Hawaii <strong>Community</strong> <strong>College</strong>s April 2004<br />

Project No. CC-02-6188 I-2


The Learning Resource Center at <strong>Windward</strong> <strong>Community</strong> <strong>College</strong><br />

PROJECT DEVELOPMENT REPORT<br />

• Three (3) “round table” interactive sessions with representatives of the<br />

University of Hawaii <strong>Community</strong> <strong>College</strong>s, <strong>Windward</strong> <strong>Community</strong> <strong>College</strong><br />

department directors, administrative staff, as well as staff and consultants of<br />

LEO A DALY representing the disciplines of architecture, interior design,<br />

planning, mechanical and electrical engineering. The “round tables” were<br />

facilitated by an architect from LEO A DALY specializing in the planning and<br />

design of libraries.<br />

• The results of this planning and concept development process are<br />

documented in this report.<br />

University of Hawaii <strong>Community</strong> <strong>College</strong>s April 2004<br />

Project No. CC-02-6188 I-3


The Learning Resource Center at <strong>Windward</strong> <strong>Community</strong> <strong>College</strong><br />

PROJECT DEVELOPMENT REPORT<br />

II.<br />

SUMMARY OF GENERAL PLANNING REFERENCES<br />

A. Introduction<br />

In accordance with the City and County of Honolulu, Land Use Ordinance,<br />

Sections 3.160 and 8.30, the Department of Accounting and General Services,<br />

State of Hawaii, applied for a Plan Review Use to construct new buildings,<br />

renovate existing buildings and develop related infrastructure improvements at<br />

<strong>Windward</strong> <strong>Community</strong> <strong>College</strong>. The campus is approximately 64 acres and<br />

located in Kaneohe, Oahu, Hawaii. The Tax Map Key is 4-5-23: portion of 2.<br />

The Plan Review Use Application included the Plan Review Use for a Five Year<br />

Master Plan, the Master Plan Report, Urban Design Plan and Guidelines,<br />

Landscape Plan, Signage Plan, Lighting Plan and Parking Implementation Plan.<br />

The City & County of Honolulu, City Council approved the PRU application on<br />

May 4, 1994.<br />

The Project <strong>Development</strong> Report acknowledges the provisions of the PRU<br />

resolution/Master Plan guidelines in the development of a comprehensive facility<br />

program and the architectural design concept for The Learning Resource Center<br />

at <strong>Windward</strong> <strong>Community</strong> <strong>College</strong>. These general planning documents and<br />

contents are referenced but not attached with this report.<br />

B. Planning Documents<br />

1. Plan Review Use Resolution<br />

The Plan Review Use (PRU) documents consist of two volumes: Volume<br />

1 and Volume 2 associated with a Five-Year Master Plan for <strong>Windward</strong><br />

<strong>Community</strong> <strong>College</strong>. The documents where prepared by Okita, Kunimitsu<br />

& Associates, Inc. in May 1992. The Plan Review Use (PRU) establishes<br />

the development and master planning guidelines for <strong>Windward</strong><br />

<strong>Community</strong> <strong>College</strong> (WCC) campus as required by the City & County of<br />

Honolulu, Land Use Ordinance.<br />

Volume 1<br />

Part 1 Application Information<br />

Part 2 Narrative Description<br />

Part II-A Project Description<br />

Part II-B Applicant’s Justifications<br />

Part II-C Infrastructure Requirements<br />

Part II-D Environmental Requirements<br />

Part II-E Impacts<br />

Part II-F Social Impact Requirements<br />

University of Hawaii <strong>Community</strong> <strong>College</strong>s April 2004<br />

Project No. CC-02-6188<br />

II-1


The Learning Resource Center at <strong>Windward</strong> <strong>Community</strong> <strong>College</strong><br />

PROJECT DEVELOPMENT REPORT<br />

Appendices<br />

A Transportation Study Report<br />

B Environmental Assessment for <strong>Windward</strong> <strong>Community</strong> <strong>College</strong><br />

Master Plan<br />

Volume 2<br />

Appendix A Transportation Study<br />

<strong>Windward</strong> <strong>Community</strong> <strong>College</strong> Master Plan Report<br />

I. Introduction<br />

A. Objectives<br />

B. Guidelines and Standards<br />

C. Methodology<br />

D. Site Information<br />

II. Planning Criteria<br />

A. Educational Specifications<br />

B. Governmental Requirements<br />

III. Planning <strong>Development</strong><br />

A. Introduction<br />

B. Site Utilization Schemes<br />

C. Alternative Site Plans<br />

D. Ultimate Site Plan<br />

E. Ultimate Civil Plan<br />

F. Ultimate Electrical Plan<br />

G. Ultimate Landscape Plan<br />

H. Barrier Free Accessibility Plan<br />

I. Design Considerations<br />

IV. Space Allocation and One-Line Diagrams<br />

A. Introduction<br />

B. Space Allocation<br />

C. One-Line Diagrams<br />

Implementation<br />

A. Incremental Construction<br />

B. Costs<br />

Appendices<br />

A. Summary of Existing Buildings<br />

B. Civil Engineering Analysis<br />

2. Master Plan Report Dated April 22, 1989<br />

The <strong>Windward</strong> <strong>Community</strong> <strong>College</strong> Five-Year Master Plan Report was<br />

prepared by a Joint Venture: Okita Kunimitsu & Associates, Inc./ Ernest<br />

University of Hawaii <strong>Community</strong> <strong>College</strong>s April 2004<br />

Project No. CC-02-6188<br />

II-2


The Learning Resource Center at <strong>Windward</strong> <strong>Community</strong> <strong>College</strong><br />

PROJECT DEVELOPMENT REPORT<br />

Hara and Associates, Inc. on April 22, 1989. The Master Plan Report<br />

provides a comprehensive site and facilities development plan for the<br />

entire <strong>Windward</strong> <strong>Community</strong> <strong>College</strong> (WCC) based on the projected<br />

academic needs and incorporates the following:<br />

I. Introduction<br />

A. Objectives<br />

B. Guidelines and Standards<br />

C. Methodology<br />

D. Site Information<br />

II. Planning Criteria<br />

A. Educational<br />

III. Planning <strong>Development</strong><br />

IV. Space Allocation and One-Line Diagrams<br />

V. Implementation<br />

VI. Appendices<br />

3. Urban Design Guidelines Dated November 30, 1995<br />

The Urban Design Guidelines dated July 15, 1994 were prepared by<br />

Okita Kunimitsu & Associates, Inc. and revised on November 30, 2003.<br />

These guidelines are required by the City Council resolution and<br />

supplement the Plan Review Use for a Five-Year Master Plan. The<br />

Urban Design Guidelines establishes the design parameters to ensure a<br />

cohesive campus character for all future development at <strong>Windward</strong><br />

<strong>Community</strong> <strong>College</strong> (WCC). The contents of this document are as<br />

follows:<br />

I. Introduction<br />

A. Purpose<br />

B. Scope<br />

C. Applicable Codes and Standards<br />

D. Study Area<br />

E. Format<br />

II. Urban Design Principles and Controls<br />

A. <strong>Development</strong> Plan Common Provisions<br />

B. Koolaupoko <strong>Development</strong> Plan Special Provisions<br />

III. Campus <strong>Concept</strong>s and Themes<br />

A. Existing Character<br />

B. Design <strong>Concept</strong>s and Themes<br />

IV. Design Guidelines<br />

A. Architectural Design Guidelines<br />

B. Site <strong>Development</strong> Guidelines<br />

C. Landscape Guidelines<br />

D. Signage Guidelines<br />

E. Lighting Guidelines<br />

University of Hawaii <strong>Community</strong> <strong>College</strong>s April 2004<br />

Project No. CC-02-6188<br />

II-3


The Learning Resource Center at <strong>Windward</strong> <strong>Community</strong> <strong>College</strong><br />

PROJECT DEVELOPMENT REPORT<br />

V. Implementations<br />

A. Phasing<br />

B. Compliance<br />

C. Design Review<br />

D. Amendments<br />

VI. Appendix<br />

4. Parking Implementation Plan<br />

The Parking Implementation Plan report was prepared by Okita Kunimitsu<br />

& Associates, Inc. in October 1995. The Parking Implementation Plan<br />

establishes the number of required parking stalls and a phasing program<br />

to ensure the provision of adequate parking with the projected growth and<br />

development of the campus. The Parking Implementation Plan<br />

incorporates the following:<br />

I. Introduction<br />

A. Purpose and Intent<br />

B. Scope<br />

C. Applicable Codes and Standards<br />

D. Study Area<br />

E. Format<br />

II. Implementation and Phasing<br />

A. Implementation Plan<br />

B. Facilities Implementation<br />

C. Parking and Loading Implementation<br />

D. Existing Parking and Loading<br />

E. Phase 1 Parking and Loading<br />

F. Phase 2 Parking and Loading<br />

G. Phase 3 Parking and Loading<br />

H. Phase 4 Parking and Loading<br />

I. Phase 5 Parking and Loading<br />

5. State Historical Preservation<br />

The <strong>Windward</strong> <strong>Community</strong> <strong>College</strong> Historic Preservation Plan was<br />

prepared by School of Architecture, University of Hawaii, Heritage Center,<br />

by Spencer Leineweber, FAIA, Principle Investigator and Joy Davidson,<br />

AIA, Research Assistant on August 20, 2001. The report provides an<br />

historic assessment and survey of existing buildings on the <strong>Windward</strong><br />

<strong>Community</strong> Campus and includes the following:<br />

I. Project Information<br />

II. Master Plan Information<br />

III. New Construction<br />

IV. Design Guidelines for Structures<br />

University of Hawaii <strong>Community</strong> <strong>College</strong>s April 2004<br />

Project No. CC-02-6188<br />

II-4


The Learning Resource Center at <strong>Windward</strong> <strong>Community</strong> <strong>College</strong><br />

PROJECT DEVELOPMENT REPORT<br />

6. Environmental Assessment<br />

The Environmental Assessment (EA) for <strong>Windward</strong> <strong>Community</strong> <strong>College</strong><br />

Master Plan was prepared by Wilson Okamoto & Associates, Inc. in<br />

October 1987 (see Appendix D). The EA provides the assessment for the<br />

entire master planned campus and four (4) new buildings that include the<br />

<strong>Library</strong>/Learning Resource Center. The EA incorporated the following<br />

information that concluded with a negative declaration, or FONSI, by the<br />

State of Hawaii, Office of Environmental Quality Control:<br />

I. Introduction<br />

II. Description of the Proposed Project<br />

III. Description of the Existing Environment<br />

IV. Socio-Economic Environment<br />

V. Relationship To Plans, Policies, and Controls<br />

VI. Potential Impacts and Mitigation Measures<br />

VII. Alternatives to The Proposed Action<br />

VIII. Agencies, Organizations and Individuals Consulted References<br />

C. <strong>Windward</strong> <strong>Community</strong> <strong>College</strong> – Existing Conditions<br />

1. Overall Campus Land Use<br />

The overall campus land use was originally established in the <strong>Windward</strong><br />

<strong>Community</strong> <strong>College</strong> Master Plan Report prepared April 22, 1989 and<br />

formally defined in the Plan Review Use Application, University of Hawaii<br />

<strong>Windward</strong> <strong>Community</strong> <strong>College</strong> prepared May 1992.<br />

The refined Scheme Four (Ultimate Master Plan) of the 1989 Master Plan<br />

Report consists of the following elements. See Figure II.1 Existing Land<br />

Use.<br />

a. Building Uses<br />

• A Administration Services and Academic Support<br />

• B Media Production<br />

• C <strong>Community</strong> Service (demolish for new parking)<br />

• D General Classrooms, Campus Center/ Student<br />

Activities Center/Student Activities, Food Service,<br />

Bookstore, <strong>Community</strong> Service function<br />

• E Language Arts (demolish for new structure)<br />

• F Social Science Department<br />

• G Business Department (demolish for new structure)<br />

• H <strong>Library</strong> Services, Media Productions Services,<br />

Learning Assistance/ Tutorial Services, and<br />

Computer Facilities. (demolish for new structure)<br />

• I Math Department<br />

University of Hawaii <strong>Community</strong> <strong>College</strong>s April 2004<br />

Project No. CC-02-6188<br />

II-5


The Learning Resource Center at <strong>Windward</strong> <strong>Community</strong> <strong>College</strong><br />

PROJECT DEVELOPMENT REPORT<br />

• J Humanities<br />

• K Science Department<br />

• L Maintenance (demolish for new structure)<br />

• M Automotive Tech (demolish for new structure)<br />

• N Automotive Tech (demolish for new structure)<br />

• O Math/ Science<br />

• P Math/ Science<br />

• Q Health/ Physical Ed.<br />

Of the above building uses the Campus Center and Parking (Hale<br />

Akoakoa), the Arts and Humanities Building (Hale Palanakila), the<br />

Planetarium (Hale Hokulani) and the Science Building (Hale<br />

‘Imiloa) have been designed and constructed.<br />

b. Area uses<br />

• Parking is to be located near the entrance to the campus just<br />

adjacent to Kea‘ahala Road. Other parking is planned for the<br />

area across Banyan Drive near the Humanities Building J.<br />

Additional parking is planned for the mauka side of<br />

Honeysuckle Road.<br />

• Agricultural and Aquaculture Plots are anticipated near<br />

Building ‘P’.<br />

• Shade Houses ‘A’ and ‘B’ are anticipated in the agriculture<br />

plots.<br />

• Building I has an addition in the back of the facility.<br />

2. Vehicular Circulation and Parking<br />

The vehicular entrance to the campus is on Kea‘ahala Road. Banyan<br />

Drive intersects Kea‘ahala Road and continues around the major open<br />

space and campus building to define the perimeter of the campus. The<br />

parking for the campus is located in three primary areas: 1) to the right at<br />

the entrance along Kea‘ahala Road, 2) across Banyan Street in front of<br />

the Hale Palanakila (Humanities Building), and 3) to the southeast of the<br />

student center. There is also parking along Honeysuckle Road and Ilima<br />

Way and around Hale Alaka‘I, Hale Kuhina, and the automotive area.<br />

See Figure II.2 Existing Vehicular & Pedestrian Circulation.<br />

3. Pedestrian Circulation<br />

The pedestrian circulation is comprised of the existing network of<br />

walkways interior to the campus and along Banyan Drive on the east side<br />

on the campus. See Figure II.2 Existing Vehicular & Pedestrian<br />

Circulation.<br />

University of Hawaii <strong>Community</strong> <strong>College</strong>s April 2004<br />

Project No. CC-02-6188<br />

II-6


The Learning Resource Center at <strong>Windward</strong> <strong>Community</strong> <strong>College</strong><br />

PROJECT DEVELOPMENT REPORT<br />

The comprehensive network of curvilinear walkways is defined in the<br />

Master Plan of <strong>Windward</strong> <strong>Community</strong> <strong>College</strong>. This proposed network is<br />

being incrementally developed in conjunction with the implementation of<br />

individual facilities that are planned for the campus.<br />

4. Landscaping and Open Spaces<br />

5. Views<br />

a. Central Campus Landscaping<br />

Trees and Palms: The major open space consists of a sloped<br />

grass area with 20 banyan trees within the major open space.<br />

Two of the banyan trees are in need of special attention; these are<br />

the two just to the southeast of the site. There are a very limited<br />

number of palm trees within the major open space and these are<br />

located very close to the existing buildings, not in the major open<br />

space area.<br />

Ground Covers: The major open space area is entirely grassed<br />

with a small amount of different types of ground cover that tends<br />

to integrate the buildings into the landscape areas.<br />

Plant types and irrigation requirements are further discussed in<br />

Section IV, Item C Landscape.<br />

b. Open Space<br />

‘Ilima Way defines the major open space on the north and the<br />

buildings fronting Banyan Drive and Honeysuckle Drive define this<br />

space on the southeast and west. The master plan mandates the<br />

retention of this openness on the southeast sector of campus.<br />

The open space to the southeast is much more of a “passive open<br />

space” while the open space to the northwest is potentially more<br />

active due to the pedestrian activity generated by the classrooms<br />

in both the Humanities Building and the Science Center. See<br />

Figure II.3 Existing Vegetation & Open Spaces.<br />

The Koolau Mountains are viewed from most locations on the campus.<br />

The two views that are identified in the Urban Design Plan are the views<br />

to the south and to the west, page 11 Figure 2 Campus Views and Open<br />

Space; <strong>Windward</strong> <strong>Community</strong> <strong>College</strong> Urban Design Plan and Design<br />

Guidelines July 1994. The lower image views from the campus are<br />

limited to a certain degree by the campus buildings themselves on the<br />

north-north west, west, southwest, east, northeast, and north. The view<br />

to the south-southeast is open at grade level and to the mountains. See<br />

Figure II.3.<br />

University of Hawaii <strong>Community</strong> <strong>College</strong>s April 2004<br />

Project No. CC-02-6188<br />

II-7


The Learning Resource Center at <strong>Windward</strong> <strong>Community</strong> <strong>College</strong><br />

PROJECT DEVELOPMENT REPORT<br />

6. Site Utilities<br />

The existing Site Utilities are shown on Figure II.4, Underground Utilities<br />

as a general reference. The assessment and proposed improvements<br />

are discussed in Section IV Preliminary Engineering Design Criteria.<br />

University of Hawaii <strong>Community</strong> <strong>College</strong>s April 2004<br />

Project No. CC-02-6188<br />

II-8


The Learning Resource Center at <strong>Windward</strong> <strong>Community</strong> <strong>College</strong><br />

PROJECT DEVELOPMENT REPORT<br />

III.<br />

THE LEARNING RESOURCE CENTER<br />

A. Overview of the Planning and Design Process<br />

In the summer of 2003, the programming and design team began a pre-design<br />

analysis for the new Learning Resource Center at <strong>Windward</strong> <strong>Community</strong> <strong>College</strong>.<br />

The purpose of this report is to focus on the new Learning Resource Center<br />

building and define its future potential which will combine five currently separate<br />

campus functions: 1) <strong>Library</strong>; 2) The Learning Center; 3) Instructional Media<br />

Services; 4) Computing Services and Computer Laboratory; and 5) LRC<br />

Administration. This analysis includes a recommended final site selection, a final<br />

space needs program, a new building design concept, and a conceptual<br />

construction cost estimate.<br />

It is important to note that this is only a preliminary schematic design study and<br />

the related code analysis, engineering criteria and cost data are conceptual in<br />

nature.<br />

The design study team was comprised of University of Hawaii <strong>Community</strong><br />

<strong>College</strong> Facilities Planning Staff, <strong>Windward</strong> <strong>Community</strong> <strong>College</strong><br />

Staff/Administrators and the architectural firm of LEO A DALY. Through the<br />

summer and fall of 2003, a series of work sessions, tours and conference calls<br />

were conducted to address the vision and goals for the project. The current uses<br />

and organization of The Learning Resource Center components were toured and<br />

quantified. Proposed space needs were identified and summarized in a program<br />

matrix. The systems and infrastructure of the existing facilities were reviewed<br />

and a variety of issues identified. A site plan, floor plans, building sections,<br />

elevations study models, a perspective rendering, and cost models were<br />

developed to determine the overall budget.<br />

To help identify the vision of a 21 st century library/learning resource center,<br />

members of the <strong>Windward</strong> staff along with LEO A DALY design team members<br />

toured three libraries, all with Information Commons serving as the “living room<br />

for the campus.” Libraries visited were the new Lied <strong>Library</strong> at UNLV (University<br />

of Nevada at Las Vegas), the renovated campus <strong>Library</strong> at the University of<br />

Arizona (Tucson), and the new <strong>Library</strong> at Mesa <strong>Community</strong> <strong>College</strong> in Phoenix.<br />

These tours proved very valuable, providing both insight and confirmation of the<br />

emerging concept layout for the new Learning Resource Center.<br />

LEO A DALY would like to thank the University of Hawaii <strong>Community</strong> <strong>College</strong>s, the<br />

<strong>Windward</strong> <strong>Community</strong> <strong>College</strong> Administration and the entire <strong>Library</strong> staff for their<br />

valuable input, understanding, and willingness to explore and invest in the future.<br />

B. <strong>Library</strong> of the Future/Vision<br />

Academic libraries are known as leaders among their peers in the delivery of<br />

scholarly information services to a diverse and global community. These libraries<br />

University of Hawaii <strong>Community</strong> <strong>College</strong>s April 2004<br />

Project No. CC-02-6188<br />

III-1


The Learning Resource Center at <strong>Windward</strong> <strong>Community</strong> <strong>College</strong><br />

PROJECT DEVELOPMENT REPORT<br />

also are known for their efficient use of state-of-the-art information technologies,<br />

innovative management practices, and faculty focused on leading-edge<br />

professional directions. The libraries’ reputation for partnership-building and<br />

consortium leadership is widely recognized, and is known for its client-focused<br />

and learner-centered approach to librarianship. The challenge now is to create a<br />

new library/learning resource center paradigm within an aesthetically rich and<br />

dynamic physical environment. It is time to combine and transform these aging<br />

facilities to meet the challenges and expectations of a new, collaborative,<br />

learning environment, and to develop The Learning Resource Center at<br />

<strong>Windward</strong> into a facility that is the heart of the campus and a vibrant and inspiring<br />

“place” where students are welcomed and nourished.<br />

Recent developments in higher education have prompted a near revolution in<br />

teaching and learning, with libraries eagerly embracing such opportunities as: 1)<br />

the advent of web-enhanced instruction; 2) universal computer-access programs<br />

and the growing seamlessness of the worldwide community of libraries; 3) the<br />

rapid proliferation of full-text electronic research databases; and 4) necessary<br />

reconfiguration, plus growth of the internal geography of libraries and learning<br />

resource centers. These dynamic new campus resource centers are being<br />

realized through new construction or major reconceptualization and renovation of<br />

those structures built in the 1970s or earlier.<br />

Leadership at <strong>Windward</strong> <strong>Community</strong> <strong>College</strong> clearly has accepted these<br />

challenges. As innovators on the state, regional, and national stages, they have<br />

continued to engage their peers in conversations on the future of information<br />

services.<br />

As academic libraries move into the digital age, their role is constantly being<br />

challenged. Obviously, this is affecting library facilities, both existing and<br />

proposed. <strong>Library</strong> space must be designed to accommodate new approaches<br />

toward interaction between technology and fellow information seekers. Many new<br />

services, such as distance learning, are affecting library facility needs, and the<br />

role of the library as a campus cultural center and icon is becoming more<br />

prevalent on many college campuses.<br />

In the midst of these changes, many traditional library services will remain and<br />

continue to place demands on space. Facilities must be able to accommodate<br />

these traditional elements, which are associated with paper format resources, as<br />

this format will continue to play a significant role in library collections for the next<br />

several decades. The essential element in this transition to planning for the<br />

digital age is flexibility of space.<br />

It is incumbent upon the proposed new Learning Resource Center to<br />

architecturally express the importance of space in a learning society, the<br />

changing nature of collections, the effect on the library as a symbolic and<br />

physical place, and the library as a “community place” at the academic center of<br />

University of Hawaii <strong>Community</strong> <strong>College</strong>s April 2004<br />

Project No. CC-02-6188<br />

III-2


The Learning Resource Center at <strong>Windward</strong> <strong>Community</strong> <strong>College</strong><br />

PROJECT DEVELOPMENT REPORT<br />

the university. The new Learning Resource Center facility should be viewed as<br />

the most important, interesting, and popular building on campus.<br />

Even in a difficult economic period, library facility improvements and expansions<br />

appear to be at an all-time high, with many universities viewing their new and<br />

expanded libraries as signature campus buildings, critical to attracting and<br />

retaining excellent students and faculty.<br />

C. Project Success Criteria/Goals<br />

The vision for the new Learning Resource Center is to recognize the role of<br />

<strong>Library</strong> as Central Place on the <strong>Windward</strong> <strong>Community</strong> <strong>College</strong> campus. The<br />

Learning Resource Center building serves as a home for a community of<br />

learners and their materials, a refuge for commuting students, and a collaborative<br />

and scholarly environment for faculty, staff, students and members of the greater<br />

community.<br />

As a guide to the planning team the following goals/criteria were developed:<br />

1. Planning<br />

a. Create a memorable sense of place that welcomes users<br />

b. Enhance the library’s presence on campus, marking these newly<br />

combined Learning Resource Center functions with a distinguished<br />

“landmark” architectural image<br />

c. Creatively combine, under one roof, the five currently separated<br />

departments within open floor plans with visual clarity to the<br />

services provided, allowing users to navigate independently<br />

d. Arrange the collections in a climate-controlled, environmentally<br />

and physically secure, accessible, and space-efficient manner<br />

e. Increase the needed future collection growth space and reader<br />

seating programmed requirements within a flexible and rearrangeable<br />

environment<br />

f. Locate service points and departments in a readily understandable<br />

and functional pattern<br />

g. Provide barrier-free access, both inside and outside the building<br />

h. Incorporate principles of "green" architecture to create a healthy<br />

and forward-looking facility, while ensuring an appropriate.<br />

environment for the preservation of books and other materials by<br />

addressing issues of energy efficiency, recycled and replenishable<br />

resources, and flexible design<br />

i. Strive to achieve LEED® “Silver Certification” based on the U.S.<br />

Green Buildings Council criteria.<br />

j. Invite the <strong>College</strong> faculty to become a more accommodating<br />

presence in the library proper<br />

k. Encourage natural daylight and views to the surrounding natural<br />

beauty at every opportunity<br />

University of Hawaii <strong>Community</strong> <strong>College</strong>s April 2004<br />

Project No. CC-02-6188<br />

III-3


The Learning Resource Center at <strong>Windward</strong> <strong>Community</strong> <strong>College</strong><br />

PROJECT DEVELOPMENT REPORT<br />

l. Retain and emphasize the natural beauty of the <strong>Windward</strong><br />

campus site, paying special attention to the rural and pastoral<br />

ambiance unique to the campus<br />

m. Design the new building to “feel at home” in the campus context of<br />

arches, tile roofs, shaded lanais, and landscape.<br />

2. Technology<br />

a. Provide an Information Commons uniting technology, reference<br />

services, research assistance, instructional media, and The<br />

Learning Center assistance to create a collaborative learning<br />

environment – a campus living room<br />

b. Provide locations for technology-rich information services for<br />

students, faculty, and staff<br />

3. <strong>Library</strong> Environments<br />

a. Create collaborative work environments for both students and staff<br />

b. Improve staff work environments<br />

c. Create a variety of study environments<br />

d. Provide comfortable meeting and gathering spaces, within an<br />

“architecture of interaction”<br />

e. Create large and small group study rooms<br />

f. Create high-technology zones throughout the building, with power<br />

and data access convenient to all reader stations<br />

g. Provide quiet zones<br />

h. Provide a coffee shop cafe and outside covered lanai/patio<br />

i. Be a welcome center to the campus<br />

j. Have a strong exterior visual identity, with the library as landmark<br />

D. Facilities Program – Summary Of Spatial Requirements<br />

The Learning Resource Center (LRC) is envisioned as the center of scholarship<br />

and learning as well as the information and technology center of <strong>Windward</strong><br />

<strong>Community</strong> <strong>College</strong>. It seeks to provide an environment conducive to the<br />

advancement of learning by providing access to comprehensive learning<br />

resources, instructional services, computers, multimedia and high speed<br />

connections, facilitating the integration of new technologies into teaching and<br />

learning, and providing appropriate technological support to the campus.<br />

The Learning Resource Center provides a collection of print, non-print and<br />

electronic resources; maximum access to these resources regardless of location<br />

or format; information and multimedia hardware and software for the general<br />

student use and advanced faculty and student productions; and instruction and<br />

assistance in the use of the various resources and technologies.<br />

University of Hawaii <strong>Community</strong> <strong>College</strong>s April 2004<br />

Project No. CC-02-6188<br />

III-4


The Learning Resource Center at <strong>Windward</strong> <strong>Community</strong> <strong>College</strong><br />

PROJECT DEVELOPMENT REPORT<br />

The following facility program and design concept incorporates new and<br />

traditional functions of the <strong>Library</strong>, Media Production Center, The Learning<br />

Center, and Academic and Administrative Computing. It strives to meet the<br />

general information needs of and to promote lifelong learning among students,<br />

faculty, staff and community users.<br />

This section summarizes the spatial requirements of the facility program, site<br />

analysis, preliminary zoning and building code analyses, the architectural design<br />

concept and the environmental analysis for the development of The Learning<br />

Resource Center.<br />

The facilities program is a comprehensive document that defines the functional,<br />

operational and spatial requirements of the facility that is represented in detail in<br />

a companion document entitled Program Planning. Exhibit III.1 SUMMARY OF<br />

FUNCTIONS – ASSIGNABLE SQUARE FOOTAGE summarizes each function,<br />

the faculty and staff requirements and the assignable square footage.<br />

EXHIBIT III.1 SUMMARY OF FUNCTIONS - ASSIGNABLE SQUARE FOOTAGE<br />

Function<br />

Number Function Description Units<br />

Student<br />

Stations<br />

Fac/Staff<br />

Stations<br />

Initial<br />

ASF Final Difference<br />

I. Administration<br />

1 Director of Information<br />

Technology Services Office 1 1 200 200<br />

2 Institutional Researcher Office 1 1 200 200<br />

3 Secretary Office 1 2 200 175 -25<br />

4 Administrative Storage Room 1 150 0 -150<br />

5 Conference Room 1 700 600 -100<br />

5a Male Restroom 1 0 50 +50<br />

5b Female Restroom 1 0 50 +50<br />

Subtotal 0 4 1,450 1,275 -175<br />

II. <strong>Library</strong><br />

6 Vestibule 1 800 800<br />

7 Information Commons 1 48 2,400 2,700 +300<br />

8 Information Commons<br />

Manager's Office 1 1 150 150<br />

9 Information Reference Desk<br />

Area 1 4 325 425 +100<br />

10 Reference Collection Area 1 16 1,050 1,100 +50<br />

Reference Librarian's Office (4<br />

@ 115) 4 4 480 460 -20<br />

11<br />

12 Reference Librarians<br />

Conference Room 1 200 340 +140<br />

Function<br />

Number Function Description Units<br />

Student<br />

Stations<br />

Fac/Staff<br />

Stations<br />

Initial<br />

ASF Final Difference<br />

University of Hawaii <strong>Community</strong> <strong>College</strong>s April 2004<br />

Project No. CC-02-6188<br />

III-5


The Learning Resource Center at <strong>Windward</strong> <strong>Community</strong> <strong>College</strong><br />

PROJECT DEVELOPMENT REPORT<br />

13 Circulation Service Center 1 4 1,000 1,125 +125<br />

14 Circulation Workroom 1 3 600 735 +135<br />

15 Circulation Manager's Office 1 1 150 145 -5<br />

16 Circulation Storage Room 1 200 200<br />

16a Additional Circulation Storage 1 1 0 135 +135<br />

17 Current Periodicals Area 1 20 925 700 -225<br />

18 Periodicals Backfile Area 1 12 925 700 -225<br />

19 Microforms Area 1 5 540 550 +10<br />

20 Pamphlets Area 1 4 200 155 -45<br />

21 Maps/Art Prints Area 1 4 460 600 +140<br />

22 Listening/Viewing Area 1 8 400 480 +80<br />

23 Study Area A 1 22 720 1,000 +280<br />

24 Hawaiian Collection Room 1 24 1 2,000 1,800 -200<br />

25 Bookstacks Area 1 6,000 5,500 -500<br />

26<br />

Study Area B (shared w/<br />

Learning Center) inc. 6 study<br />

booths 1 110 3,300 4,100 +800<br />

27 Group Viewing Room (1 @ 300<br />

& 2 @ 170) 3 450 640 +190<br />

28 Group Study Room (6 @ 150 &<br />

2 @170) Area B 9 1,150 1,240 +90<br />

29 Technical Services Room 1 4 1,200 1,130 -70<br />

30 Technical Services Librarian's<br />

Office (Tech I) 1 1 150 140 -10<br />

31 <strong>Library</strong> Technician's Office<br />

(Tech II) 1 1 150 130 -20<br />

32 <strong>College</strong> Archives Room 1 600 600<br />

33 Head Librarian's Office 1 1 200 240 +40<br />

34 Secretary Office 1 1 200 195 -5<br />

35 Storage Room 1 200 200<br />

36 Staff Emergency Room and<br />

Lounge 1 800 800<br />

37 Meeting Room with 2 Closets<br />

@ 100 1 1,200 1,220 +20<br />

38 Electronic Classroom 1 24 1 1,200 875 -325<br />

39 Computer Laboratory 1 72 4 3,600 3,670 +70<br />

39a 24-hour Study/Coffee Shop 1 30 1,000 1,500 +500<br />

Subtotal 399 31 34,925 36,480 1,555<br />

III. The Learning Center (TLC)<br />

40 TLC Coordinator's Office 1 1 150 150<br />

41 TLC Manager 1 1 120 120<br />

42 Distribution Center 1 2 340 330 -10<br />

43 Work Room 1 2 320 385 +65<br />

Function<br />

Number Function Description Units<br />

Student<br />

Stations<br />

Fac/Staff<br />

Stations<br />

Initial<br />

ASF Final Difference<br />

University of Hawaii <strong>Community</strong> <strong>College</strong>s April 2004<br />

Project No. CC-02-6188<br />

III-6


The Learning Resource Center at <strong>Windward</strong> <strong>Community</strong> <strong>College</strong><br />

PROJECT DEVELOPMENT REPORT<br />

44 Testing Room 1 25 750 810 +60<br />

45 Quiet Study Area (Merged with<br />

Study Area ‘B’ - <strong>Library</strong> 1 0 5 400 0 -400<br />

46 Resource Teacher Room 2 2 220 220<br />

47 STAAR Reception Area 1 2 200 180 -20<br />

48 STAAR Counselor's Office 3 3 330 330<br />

49 STAAR Clerk-Typist Office 1 1 110 100 -10<br />

50 STAAR Tutors' Office 1 2 220 235 +15<br />

Subtotal 27 19 3,160 2,860 -300<br />

IV. Computing Services<br />

51 Computing Services<br />

Coordinator's Office 1 1 200 215 +15<br />

52 Computing Services Secretary<br />

Office 1 2 200 205 +5<br />

53 Help Desk Room 1 2 260 285 +25<br />

54<br />

Training and Demonstration<br />

Room 1 2 400 440 +40<br />

55 Staff Workroom 1 6 1,000 985 -15<br />

56 Computer Setup and Repair<br />

Room 1 4 800 800<br />

57 Server Area 1 0 200 355 +155<br />

58 Storage Room 1 300 200 -100<br />

58a Bathroom 0 50 +50<br />

Subtotal 0 17 3,360 3,535 +175<br />

V. Instructional Media Services<br />

Reception<br />

59 Area/Counter/Equipment<br />

Check-out 1 3 250 210 -40<br />

60 General Office, Job and<br />

Equipment Intake Room 1 6 450 450<br />

61 Clerk-Typist's Office 1 1 120 125 +5<br />

62 Media Coordinator’s Office 1 1 200 200<br />

63 Storage Room 1 0 230 190 -40<br />

64 Duplication and Copiers Room 1 1 830 610 -220<br />

65 Duplication Storage Room 1 0 220 160 -60<br />

66 Bindery Room 1 3 300 300<br />

67 Duplication Manager's Office 1 1 120 140 +20<br />

68 New Media Laboratory 1 20 1 700 620 -80<br />

69 Instructional <strong>Development</strong><br />

Specialist’s Office 1 1 120 110 -10<br />

70<br />

Media Production Specialist's<br />

Office 1 1 120 120<br />

Function<br />

Number Function Description Units<br />

Student<br />

Stations<br />

Fac/Staff<br />

Stations<br />

Initial<br />

ASF Final Difference<br />

University of Hawaii <strong>Community</strong> <strong>College</strong>s April 2004<br />

Project No. CC-02-6188<br />

III-7


The Learning Resource Center at <strong>Windward</strong> <strong>Community</strong> <strong>College</strong><br />

PROJECT DEVELOPMENT REPORT<br />

71 Web Master's Office 1 1 160 125 -35<br />

72 Studio Storage Room 1 0 100 110 +10<br />

73 Instructional Video Studio 1 5 750 715 -35<br />

74 Electronic Duplication and<br />

Distribution Room 1 3 500 450 -50<br />

75 Studio Control Room 1 6 300 210 -90<br />

76 Audio Recording Booth 1 2 125 125<br />

77 Electronic Maintenance and<br />

Repair Shop 1 3 745 745<br />

78 Electronic Technician I Office 1 1 120 145 +25<br />

79 Electronic Technician II Office 1 1 120 145 +25<br />

80 Equipment Storage Room 1 1 230 215 -15<br />

81 Graphic Materials Preparation<br />

Room 1 4 4 1,000 850 -150<br />

82 Graphic Artist’s Office 1 1 150 160 +10<br />

83 Graphics Storage Room 1 0 100 115 +15<br />

84 Spray Booth 0 60 70 +10<br />

85 Loading and Receiving/Storage<br />

Room 0 1300 900 -400<br />

85a Bathroom 1 0 0 50 +50<br />

Subtotal 29 42 9,420 8,365 -1,055<br />

Subtotal (Assignable Square<br />

Feet) 455 113 52,315 52,515 +200<br />

VI. Non-Assignable Square Feet/Building Support<br />

86. Atrium 1 3,000 3,500 500<br />

87. Delivery Area/Receiving<br />

1 600 -600<br />

(Merged with #85)<br />

88. Cart Parking Area 1 500 485 -15<br />

89. Trash Area 1 200 250 +50<br />

90. Wiring/Telecommunications 1 400 440 +40<br />

Room (1 @ 400)<br />

91. Wiring/Telecommunications 4 400 415 +15<br />

Subroom (1 @ 85, 1 @ 95, 1<br />

@ 100, 1 @ 135)<br />

92. Janitorial Rooms (1 @ 45, 1 4 200 240 +40<br />

@ 60, 1 @ 65, 1 @ 70)<br />

93. Central Housekeeping 1 200 160 -40<br />

94. Central Mechanical Room 1 3,500 3,090 -410<br />

95. Central Electrical Room 1 400 350 -50<br />

96. Electrical Floor Closets (4 @ 4 320 240 -80<br />

60)<br />

97. Public Toilets (2 @ 280, 2 @ 4 1,200 1,130 -70<br />

285)<br />

98. Student Lockers/Bag Niches 40 400 200 -200<br />

(20 ½ length lockers)<br />

Function<br />

Number Function Description Units<br />

Student<br />

Stations<br />

Fac/Staff<br />

Stations Initial Final Difference<br />

University of Hawaii <strong>Community</strong> <strong>College</strong>s April 2004<br />

Project No. CC-02-6188<br />

III-8


The Learning Resource Center at <strong>Windward</strong> <strong>Community</strong> <strong>College</strong><br />

PROJECT DEVELOPMENT REPORT<br />

Subtotal (Non-Assignable<br />

11,320 10,500 -820<br />

Square Feet) (VI)<br />

Subtotal Assignable<br />

52,315 52,515 +200<br />

Square<br />

Feet (I-V)<br />

Subtotal (I-VI) 63,635 63,015 -620<br />

VII. Horizontal & Vertical Circulation,<br />

Wall Thickness; Duct Shafts &<br />

Overhangs (+29.8%)<br />

15,909 18,778<br />

TOTAL GROSS SQUARE<br />

FEET<br />

79,544<br />

GSF<br />

81,793<br />

GSF<br />

+2,249<br />

E. City & County of Honolulu Land Use Ordinance: Preliminary Zoning<br />

Information<br />

The following data is a summary of the preliminary zoning information for The<br />

Learning Resource Center as defined by the Plan Review Use Application<br />

Resolution No. 94-87, CD-1, dated May 4, 1994.<br />

1. Preliminary Zoning Information<br />

Tax Map Area: 4-5-23:2<br />

Lot Area:<br />

64 Acres<br />

Zoning:<br />

AG-2<br />

Setbacks – Front Yard: Not Applicable<br />

Setbacks – Side & Rear Yards: Not Applicable<br />

Maximum Density:<br />

Not Applicable<br />

Maximum Building Area:<br />

Not Applicable<br />

Actual Building Area:<br />

81,793 Gross Square Feet<br />

Maximum Height:<br />

50 Feet<br />

Actual Height:<br />

Varies from 36.25 Feet to 51.25 Feet<br />

Flood Zone:<br />

Not Applicable<br />

Parking Loading:<br />

See Exhibit III.2<br />

2. Exhibit III.2 Parking Stall Summary<br />

Summary Floor Area L.U.O. Requirement No. of Stalls<br />

Accessory 38,960 0 0<br />

Classrooms 7,450 1 per 10 student @ 39<br />

20 s.f. per student<br />

Conference Rooms 2,100 1 per 75 s.f. 28<br />

Offices 5,020 1 per 400 s.f. 13<br />

Learning Resource 53,530 80<br />

Center Subtotal<br />

3. Exhibit III.3 Parking Stall Calculation<br />

University of Hawaii <strong>Community</strong> <strong>College</strong>s April 2004<br />

Project No. CC-02-6188<br />

III-9


The Learning Resource Center at <strong>Windward</strong> <strong>Community</strong> <strong>College</strong><br />

PROJECT DEVELOPMENT REPORT<br />

Functions Floor Area L.U.O. Requirement No. of Stalls<br />

Administration<br />

Accessory 150 0 0<br />

Meeting Rooms 700 1 per 75 s.f. 9<br />

Offices 600 1 per 400 s.f. 2<br />

Administration<br />

Subtotal<br />

1,450 11<br />

<strong>Library</strong><br />

Accessory 24,645 0 0<br />

Classrooms 6,300 1 per 10 student @ 20 32<br />

s.f. per student<br />

Conference Rooms 1,400 1 per 75 s.f. 19<br />

Offices 1,480 1 per 400 s.f. 4<br />

<strong>Library</strong> Subtotal 33,825 55<br />

The Learning Center<br />

Accessory 3,780 0 0<br />

Classrooms 750 1 per 10 student @ 20 4<br />

s.f. per student<br />

Offices 930 1 per 400 s.f. 2<br />

Learning Center<br />

Subtotal<br />

5,460 6<br />

Computing Services<br />

Accessory 2,560 0 0<br />

Training Room 400 1 per 10 student @ 20 3<br />

s.f. per student<br />

Offices 400 1 per 400 s.f. 1<br />

Computing<br />

Services Subtotal<br />

3,360 4<br />

Instructional<br />

Media Services<br />

Accessory 7,825 0 0<br />

Offices 1,610 1 per 400 s.f. 4<br />

Instructional Media<br />

Subtotal<br />

9,435 4<br />

Learning<br />

Resource Center<br />

Net Floor Area 53,530<br />

Required Parking<br />

Stalls 80<br />

University of Hawaii <strong>Community</strong> <strong>College</strong>s April 2004<br />

Project No. CC-02-6188<br />

III-10


The Learning Resource Center at <strong>Windward</strong> <strong>Community</strong> <strong>College</strong><br />

PROJECT DEVELOPMENT REPORT<br />

F. Preliminary Building Code Analysis<br />

The following data represents preliminary building code information for The<br />

Learning Resource Center:<br />

1. Applicable Building Code: 1997 Uniform Building Code with City &<br />

County of Honolulu Amendments<br />

2. Occupancy Groups: Reading Rooms: A-3<br />

Offices: B<br />

3. Type of Construction: Type II – F.R., Sprinklered<br />

4. Allowable Areas:<br />

Allowable Area – Group A-3<br />

Basic Allowable Area:<br />

3-Side Yard Separation:<br />

Fire Sprinkler:<br />

Total Allowable Area<br />

Actual Area:<br />

29,900 S.F.<br />

x2 Max.<br />

(2.5% x 40Ft,)<br />

x3<br />

179,400 S.F.<br />

10,020 S.F.<br />

Allowable Area – Group B<br />

Basic Allowable Area:<br />

3-Side Yard Separation:<br />

Fire sprinkler:<br />

Total Allowable Area:<br />

Actual Area:<br />

39,900 S.F.<br />

x2 Max.<br />

(2.55 x 40 Ft.)<br />

x3<br />

219,400 S.F.<br />

179,400 S.F.<br />

Total Allowable Area<br />

10,020sf/179,400sf + 43,510sf/219,400sf = 0.06 + 0.20 = 0.26 < 1 (OK)<br />

5. Allowable Building Height:<br />

In Stories:<br />

6. Occupancy Separation:<br />

Between A-3 & B:<br />

2 Stories per PRU/Master Plan<br />

None; No Requirements for Fire Resistance<br />

7. Fire Resistive Requirements for Building Elements:<br />

Bearing Walls – Exterior:<br />

Bearing Walls – Interior:<br />

4 Hrs<br />

2 Hrs<br />

University of Hawaii <strong>Community</strong> <strong>College</strong>s April 2004<br />

Project No. CC-02-6188<br />

III-11


The Learning Resource Center at <strong>Windward</strong> <strong>Community</strong> <strong>College</strong><br />

PROJECT DEVELOPMENT REPORT<br />

Non-Bearing Walls – Exterior:<br />

Structural Frame:<br />

Partitions – Permanent:<br />

Shaft Enclosures:<br />

Floor and Floor – Ceilings:<br />

Floor and Roof – Ceilings:<br />

4 Hrs<br />

2 Hrs<br />

1 Hr<br />

2 Hrs<br />

2 Hrs<br />

1 Hr<br />

G. Final <strong>Concept</strong> Design (Early Schematics)<br />

1. Site Analysis<br />

a. Topography and Existing Features<br />

The site for The Learning Resource Center (LRC) is located at the<br />

northwest corner of the major open space of the campus as<br />

established by the Plan Review Use resolution and the master<br />

plan documents. The site for The Learning Resource Center<br />

slopes from an approximate elevation of 250 on the southwest to<br />

an approximate elevation of 240 to the northeast, i.e., on the<br />

mauka side of the Hale Mana‘opono Building. The LRC site has<br />

three mature banyan trees on the west, two mature banyan trees<br />

to the south of the site and one monkey pod tree on the eastern<br />

portion of the site. There are two Hong Kong orchid trees mauka<br />

of the site, three Hong Kong orchid trees makai of the site and one<br />

palm tree makai of the site and one mauka of the site.<br />

The Hale Manaleo building is currently on the site and will be<br />

removed for the construction of the new facility. The topography<br />

is characterized by a drainage pattern that followed the old<br />

streambed in the area just to the north of the site. This drainage<br />

pattern now consists of catch basins that are connected to an<br />

underground storm water system.<br />

Ilima Way vehicular access to the south of the site will be partially<br />

removed facilitating a more contiguous open space pattern with<br />

the existing campus. This area will be integrated with the major<br />

open space and The Learning Resource Center. The accessible<br />

parking associated with Ilima Way will be relocated toward the<br />

entrance of the building. The vehicular handicap access to the<br />

site will be via the fire access lane that is adjacent to the Hale<br />

Na‘auao and Hale Mana‘opono.<br />

b. Site Amenities<br />

The site has several significant amenities, which include the<br />

expansive open space, dramatic views to the Koolau’s and<br />

prominent banyan trees. There are potentially a few strategic<br />

University of Hawaii <strong>Community</strong> <strong>College</strong>s April 2004<br />

Project No. CC-02-6188<br />

III-12


The Learning Resource Center at <strong>Windward</strong> <strong>Community</strong> <strong>College</strong><br />

PROJECT DEVELOPMENT REPORT<br />

views and vistas that need to be considered to take full advantage<br />

for the beauty of the mountain views. Another significant site<br />

amenity is the mature banyan trees on site with specific attention<br />

to approximately 20 banyan trees within the major open space.<br />

The large expansive open space is a very unique site amenity.<br />

The general aggregation of Spanish Mediterranean architecture<br />

provides a unity to the campus that is a site amenity. The similar<br />

materials of stucco and red tile roofs are a dominant and unifying<br />

feature of the campus.<br />

Additional campus amenities that increase the quality of<br />

environment are: ocean breezes, dense area vegetation,<br />

abundant sunshine, abundant light rain, looped campus vehicular<br />

circulation and pedestrian zones without vehicles.<br />

c. Building Placement<br />

The Learning Resource Center Facility site was established in the<br />

PRU resolution and Master Plan documents. The placement of<br />

the building is constrained by the existing banyan tree canopies to<br />

the south and west and a monkey pod tree to the east. In the<br />

interest of saving these trees and as many Hong Kong orchid<br />

trees as possible, the building was placed on both the north south<br />

axis and the east west axis. The building is also placed vertically<br />

at an elevation that is equidistant as possible between the grades<br />

of the Hale La‘akea and the Hale Mana‘opono building to facilitate<br />

the handicap access to the proposed facility.<br />

After comparative analysis of several locations, the best site is a<br />

highly used central location at the north end of the Central Green.<br />

This site optimally places the new Learning Resource Center<br />

(LRC) at a convenient crossroads/hub for campus pedestrian<br />

traffic moving between the Student Center, Humanities Building,<br />

Science Complex, classroom buildings and parking. By using a 2-<br />

story rectangular form, the new building fits between the major<br />

trees on the site, saving all the banyan trees, the monkey pod,<br />

and most of the Hong Kong orchid trees in this area. The actual<br />

preservation of the monkey pod and orchids requires further<br />

evaluation due to the proximity of the building. The existing onestory<br />

Hale Manaleo classroom building will be demolished.<br />

This site is intended to provide great student convenience and<br />

potentially create an exciting outside lanai/plaza/amphitheater to<br />

the north to generate new prominence, energy and exposure to<br />

the spaces between the Humanities, Theater, and Science<br />

facilities. An exciting new “sense of place” is anticipated for<br />

<strong>Windward</strong> <strong>Community</strong> <strong>College</strong>.<br />

University of Hawaii <strong>Community</strong> <strong>College</strong>s April 2004<br />

Project No. CC-02-6188<br />

III-13


The Learning Resource Center at <strong>Windward</strong> <strong>Community</strong> <strong>College</strong><br />

PROJECT DEVELOPMENT REPORT<br />

d. Site Related <strong>Concept</strong> Plans<br />

The “site-fit” of The Learning Resource Center with respect to<br />

existing topography, site utilities, and amenities and constraints<br />

are represented in Figures III.1.1 – III.1.5, inclusive.<br />

2. Architectural Design <strong>Concept</strong><br />

Critical to fulfilling the vision and goals for the new Learning Resource<br />

Center (LRC) is the creation of a one-stop shop with a warm and<br />

welcoming building exterior, prominently located, and at-home within the<br />

existing architectural language of <strong>Windward</strong> <strong>Community</strong> <strong>College</strong> campus.<br />

The interior environment of the new combined-use facility housing the five<br />

relocated functions of the <strong>Library</strong>, The Learning Center (TLC),<br />

Instructional Media Services, Computing Services and LRC<br />

Administration will be spatially united as one facility, yet with each of<br />

these functions being visually identified and land marked within.<br />

The combining volume and heart will be a central, open, vertical atrium<br />

space over the Information Commons that unites the first and second<br />

levels. Located on a sloping site, the building entries are placed to invite<br />

convenient access to the lower level from the east and north, and access<br />

to the upper level from the higher grades to the west. As one enters the<br />

new building, way finding will be visually clear, with the pathways obvious<br />

and easy to see destinations.<br />

The open, invitational stairways, located at the edge of the oval-shaped<br />

atrium, are designed to encourage frequent use, thereby minimizing the<br />

use of the public elevators. Thus, all of the primary functions within this<br />

new LRC facility will be easily accessible and spatially connected.<br />

Key to the successful library is a dynamic, central and open hightechnology<br />

Information Commons surrounded and energized by<br />

collaborative study and learning opportunities, and within easy access to<br />

books, technology and staff assistance. Furniture will be comfortable,<br />

and a coffee cafe will provide friendly amenities designed to invite and<br />

encourage lingering in the LRC. The objective of this architecture of<br />

interaction is to embrace research, collaborative study (for student and<br />

faculty) and individual quiet study as well.<br />

Staff workstations and offices are efficiently and flexibly laid out close to<br />

the service points. Key resource-staffed service points will be placed to<br />

optimize the dual function of user assistance as well as building security.<br />

Electronic security gates will be placed at each of the three exterior<br />

entries.<br />

University of Hawaii <strong>Community</strong> <strong>College</strong>s April 2004<br />

Project No. CC-02-6188<br />

III-14


The Learning Resource Center at <strong>Windward</strong> <strong>Community</strong> <strong>College</strong><br />

PROJECT DEVELOPMENT REPORT<br />

The vertical zoning of key functions within the new LRC is as follows:<br />

Level One:<br />

Level Two:<br />

Level Three:<br />

East Entry (Main Entry) and North Entry (Coffee Cafe<br />

Entry) <strong>Library</strong> Information Commons<br />

New Periodicals<br />

Reference Area<br />

<strong>Library</strong> Technical Services<br />

Coffee Shop<br />

Group Study Rooms<br />

<strong>Library</strong> Collection and Study Area A<br />

Computer Lab<br />

Computing Services<br />

<strong>College</strong> Archives<br />

Hawaiian Room<br />

West Entry (upper level grade access to the west)<br />

Primary <strong>Library</strong> Collection Area<br />

<strong>Library</strong> Study Area B<br />

The Learning Center (TLC)<br />

Large Conference Room<br />

Instructional Media Services<br />

Electronic Classroom<br />

Duplicating and Copy Center<br />

Group Study Room<br />

Service Entry and Dock to the west<br />

LRC Administration<br />

Mechanical space<br />

An important vertical volume and visual connector will<br />

be the two-story atrium. A stonewall that begins at the<br />

north entry and continues through the facility to the<br />

south end is located to the west of the atrium. This<br />

wall provides key way finding by emphasis of the northsouth<br />

axis within the building. This warm-toned and<br />

textured wall, perhaps built of local stone, provides<br />

opportunities for art display and locally rich historic<br />

symbolism, as well as a great setting for the Hawaiian<br />

Room.<br />

Friendly, indirect natural lighting minimizes the need for<br />

artificial light. Natural light will enter the building<br />

through large energy-conscious glass windows utilizing<br />

light deflecting mullions and automatic shades.<br />

Translucent gabled-skylights, placed along the top roof<br />

ridge, and clerestory windows along and under the<br />

eaves of the east-west raised roof will provide diffused,<br />

University of Hawaii <strong>Community</strong> <strong>College</strong>s April 2004<br />

Project No. CC-02-6188<br />

III-15


The Learning Resource Center at <strong>Windward</strong> <strong>Community</strong> <strong>College</strong><br />

PROJECT DEVELOPMENT REPORT<br />

natural light throughout. Photosensitive controls on<br />

artificial lights will turn off electric lights when not<br />

needed, thereby reducing heat gain. Mechanical<br />

spaces are strategically located within the facility floor<br />

plan for efficient and easy airflow access to all spaces.<br />

The exterior building form and massing for <strong>Windward</strong><br />

<strong>Community</strong> <strong>College</strong> is designed to be a pleasant<br />

human scale, a friendly neighborhood image, and a<br />

contextual tropical architectural vocabulary. Matching<br />

clay tile roofs, off-white stucco walls, and sloped-roof<br />

arcades will be the primary design components that<br />

define the architecture of the new building.<br />

Under the protective banyan trees, the LRC will bring<br />

dynamic new life and architectural dignity to the<br />

campus.<br />

a. Building Massing and Form<br />

The Learning Resource Center facility building massing is an<br />

outgrowth of the function of the building as well as a response to<br />

the site parameters and spatial requirements. As mentioned<br />

above, the building form responds to the major and minor axes as<br />

well as the grades between Hale La’akea and the Hale<br />

Mana’opono. The architectural functions within the building are<br />

expressed in the building massing. The western portion of the<br />

building houses the “back of the house” functions used by the staff<br />

of The Learning Resource Center while the eastern portion relates<br />

to the stack areas and other areas used by the students on a daily<br />

basis.<br />

Roof Design shall conform to hip or gable styles currently used on<br />

campus. Roof slopes shall be 3:12 to 6:12 using S-shape clay tile<br />

system. The design concept uses varying roof and wall planes to<br />

optimize scale and massing with respect to the site.<br />

Balconies/arcades are selectively integrated to further address<br />

scale and massing.<br />

b. Architectural Elements<br />

View Corridors:<br />

The exterior view corridors that were taken into consideration in<br />

the design were: 1) the view down the major mall axis. The<br />

building responds to this view corridor by aligning the wall<br />

separating the two major building functions along that line. The<br />

University of Hawaii <strong>Community</strong> <strong>College</strong>s April 2004<br />

Project No. CC-02-6188<br />

III-16


The Learning Resource Center at <strong>Windward</strong> <strong>Community</strong> <strong>College</strong><br />

PROJECT DEVELOPMENT REPORT<br />

view corridor along that axis is emphasized by the structural and<br />

sculptural wall that runs the full length of the building and<br />

continues past the outer walls. The entry of the building to the<br />

north is along this wall. The users entering the building will be<br />

able to see down this view corridor to the sculpture in the center of<br />

the mall. They will also “feel” the axis of the entire mall. 2) The<br />

view to the Koolau Mountains from the west entry point. The<br />

building takes advantage of the view to the Koolau Mountains<br />

between the two banyan trees just west of the west entrance at<br />

the Second Floor. 3) The view of the existing historic architecture<br />

to the east. The view of Hale Mana‘opono to the east is in direct<br />

alignment with The Learning Resource Center entrance. This<br />

view is along the previously mentioned minor axis.<br />

Architectural Style:<br />

The architectural style from the exterior blends with the existing<br />

campus architecture and could be considered Spanish<br />

Mediterranean in character. The arched openings, hip roofs with<br />

clay tile and the covered arcades or colonnaded walkways are<br />

detail elements of the existing architecture that is integrated into<br />

The Learning Resource Center. The two-story profile from each<br />

of the facades also creates a unity with the existing architecture.<br />

The building massing emphasizes horizontal elements instead of<br />

vertical elements as established by the <strong>Windward</strong> <strong>Community</strong><br />

<strong>College</strong> Urban Design Plan and Design Guidelines 1994. The<br />

building elevations are articulated with changes in planes and<br />

vertical elements, again as requested by the aforementioned<br />

guidelines. The roof design generally conforms to the hip or gable<br />

styles currently found on campus. The main east and west<br />

entrances were emphasized as requested in the design<br />

guidelines.<br />

Building Materials:<br />

The stucco walls and clay tile roofs create a strong sense of visual<br />

unity for the campus. The metal roofing, flashing, gutters and<br />

downspouts will be developed in later design phases. The flat<br />

roofing materials shall be non-reflective and non-glare producing<br />

earth tone colors as requested. The main entrances are<br />

anticipated to be aluminum and glass systems similar to the newer<br />

buildings on campus.<br />

University of Hawaii <strong>Community</strong> <strong>College</strong>s April 2004<br />

Project No. CC-02-6188<br />

III-17


The Learning Resource Center at <strong>Windward</strong> <strong>Community</strong> <strong>College</strong><br />

PROJECT DEVELOPMENT REPORT<br />

Fenestration:<br />

The arched openings, hip roofs with clay tile and the covered<br />

arcades or colonnaded walkways are detail elements of the<br />

existing architecture that are incorporated in The Learning<br />

Resource Center.<br />

Colors:<br />

The exterior wall colors shall be off-white/beige to match the<br />

existing buildings. The paint finishes will conform to the design<br />

guidelines.<br />

The glass on the exterior shall be the blue/green tinted glass as<br />

specified in the Design Guidelines.<br />

The flat roofing materials shall be non-reflective and non-glare<br />

producing earth tone colors as requested<br />

Sense of Place:<br />

The sense of place for the building will be captured by its strategic<br />

location within the campus mall location. The facility will act as a<br />

focal building within the campus master plan yet will blend with the<br />

existing massing, fenestration, materials, and color of the existing<br />

architecture.<br />

The interior will also provide a sense of place with the central<br />

atrium at the juncture of the main entrance and the linear open<br />

space within the building. This space will house the Information<br />

Commons and define the hub of activity of the complex. The<br />

social sense of place will be further defined by the strategic<br />

placement of the coffee shop at the north end of the facility<br />

overlooking the proposed amphitheater area to the north.<br />

c. Architectural <strong>Concept</strong> Plans<br />

H. Environmental Analysis<br />

The architectural concept for The Learning Resource Center is<br />

represented by Figures III.2.1 – III.2.11, inclusive.<br />

1. Description of technical, economic, social and environmental<br />

characteristics of the new facility.<br />

The building location for The Learning Resource Center works well within<br />

the campus master plan because the proposed building site is centrally<br />

University of Hawaii <strong>Community</strong> <strong>College</strong>s April 2004<br />

Project No. CC-02-6188<br />

III-18


The Learning Resource Center at <strong>Windward</strong> <strong>Community</strong> <strong>College</strong><br />

PROJECT DEVELOPMENT REPORT<br />

located within the most active area of the campus. Students will be able<br />

to quickly get to the facility for studying between classes.<br />

This northwest end of the major open space could potentially function as<br />

the center of activity for the campus. The facility just fits within the large<br />

banyan and monkey pod tree canopies. The large open space to the<br />

northwest of the facility between the Humanities Building (Hale<br />

Palanakila) and the Science Building (Hale ‘Imiloa) acts as one of the<br />

main entrances to the facility. The proposed walkway system has been<br />

integrated with the site development of The Learning Resource Center<br />

and is intended to conform to the campus master plan.<br />

The scale of the facility, articulation of the façade, and the choice of<br />

materials are intended to reflect the Spanish-Mediterranean architecture<br />

and respect the rural and pastoral feeling unique to the campus.<br />

Even in difficult economic periods, many universities commit to library<br />

facilities improvements and expansions and view their new and expanded<br />

libraries as “signature” campus buildings, critical to attracting and<br />

retaining excellent students and facility.<br />

The 81,793 gross square foot new Learning Resource Center for<br />

<strong>Windward</strong> <strong>Community</strong> <strong>College</strong> will be a state-of-the-art library with<br />

learning center, instructional media services, and computing services that<br />

are inspiring, functional and cost effective. The focus will be to provide<br />

the appropriate technology for a community college that will inspire the<br />

students and still be cost sensitive.<br />

2. Summarization of the affected environment, including suitable and<br />

adequate location and site maps.<br />

Every effort has been made to integrate the facility with its environment.<br />

The use of tile roofs, arches, and stucco finish will help to make the<br />

facility more congruous within its campus environment. The facility will<br />

make good use of the ocean breezes, natural day lighting and selected<br />

views of the Koolau’s. The facility is positioned within the large Banyan<br />

tree canopies and will act as a transitional element between the<br />

Humanities Building (Hale Palanakila) and the Science Facility (Hale<br />

‘Imiloa).<br />

The minor open space that is defined by these three buildings has the<br />

potential to be a focal activity area and to create the social synergy<br />

between activities and uses associated with Hale Palanakila, Hale ‘Imiloa<br />

and The Learning Resource Center.<br />

University of Hawaii <strong>Community</strong> <strong>College</strong>s April 2004<br />

Project No. CC-02-6188<br />

III-19


The Learning Resource Center at <strong>Windward</strong> <strong>Community</strong> <strong>College</strong><br />

PROJECT DEVELOPMENT REPORT<br />

3. Identification and summarization of major impacts and alternatives<br />

considered, if any.<br />

The site analysis for the facility defined critical site considerations that<br />

were integrated into the final site solution. Two site location alternatives<br />

were studied: 1) at the southeast of the major open space and 2) at the<br />

northwest of the major open space. The northwest site was designated in<br />

the master plan and selected as the site for the following reasons: a) it<br />

conformed to the original site proposed in the master plan, b) it is close to<br />

the concentration of student activity and could potentially provide an<br />

activity node for the north end of campus, and c) the other site was<br />

considered too remote for ease of circulation and access.<br />

<strong>Development</strong> of proposed mitigation measures, if any. Two (2) other site<br />

factors were important and required mitigation: 1) the fact of having to<br />

remove the existing building (Hale Manaleo) on the site. After conferring<br />

with the State Historical Society, the appropriate mitigation for this<br />

building removal from the point of view of the state Historical Society was<br />

the desire to renovate the three existing facilities around Hale Manaleo:<br />

A) Hale Mana‘opono, B) Hale La‘akea, and C) Hale No‘eau. 2) The<br />

second stakeholder issue was related to the trees that fall within the<br />

proposed building footprint. These trees within the footprint of the<br />

proposed Learning Resource Center will be removed: two palm trees, and<br />

two clusters of Hong Kong orchids (three on the makai side and two on<br />

the mauka side).<br />

4. The following major site factors were analyzed with respect to the<br />

Learning Resource Center: 1) open space, 2) pedestrian circulation,<br />

3) vehicular circulation, 4) and vegetation.<br />

a. Open Space<br />

The major open space in conjunction with the existing and<br />

planned location of buildings around the mall establishes a strong<br />

visual identity for the campus. The location of The Learning<br />

Resource Center acknowledges the suggested major and minor<br />

axes with respect to the open space and the existing buildings and<br />

conforms to the site designated in the Plan Review Use/Master<br />

Plan documents for <strong>Windward</strong> <strong>Community</strong> <strong>College</strong>.<br />

b. Pedestrian Circulation<br />

Important to any master plan are the pedestrian, vehicular and<br />

service circulation systems. The design team continues to work<br />

with the development of pedestrian circulation consistent with the<br />

master plan.<br />

University of Hawaii <strong>Community</strong> <strong>College</strong>s April 2004<br />

Project No. CC-02-6188<br />

III-20


The Learning Resource Center at <strong>Windward</strong> <strong>Community</strong> <strong>College</strong><br />

PROJECT DEVELOPMENT REPORT<br />

c. Vehicular Circulation<br />

The vehicular master plan centers on the loop road system.<br />

Vehicles, service and fire access come off of the loop system and<br />

penetrates only a short way in towards the major open space and<br />

typically adjacent to a building. The vehicular, service, and fire<br />

access functions would be integrated to minimize the impact on<br />

the campus. The access for vehicles, service and fire access will<br />

be short cul-de-sacs, specific, and adjacent to a building.<br />

d. Vegetation<br />

The placement, massing and building form respects the existing<br />

banyan trees to the south and west and the monkey pod tree to<br />

the south east of The Learning Resource Center. The<br />

development of the design concept will continue to respect the<br />

preservation of banyan trees as prescribed in the PRU resolution<br />

and the master plan documents. Any need to remove other trees,<br />

or landscaping will be supplemented either by relocation/<br />

replanting or with the inclusion of new trees.<br />

5. The preparation and determination of findings and reasons<br />

supporting determination.<br />

The facility is located in the prescribed location shown in the existing<br />

master plan and the approved PRU resolution by the City and County of<br />

Honolulu. The primary site factor regarding the placement of the facility<br />

was the close proximity to the greatest pedestrian need – the northwest<br />

portion of the mall. The Humanities Building (Hale Palanakila) and the<br />

Science Building (Hale ‘Imiloa) generate the most pedestrian traffic. The<br />

students can quickly go from their classrooms to the library all close<br />

together in the northwest portion of the mall.<br />

The architectural character will conform to the Spanish-Mediterranean<br />

architecture that is well established for the campus with the inclusion of<br />

the prescribed roof tiles, exterior wall finishes, colors and textures. Also<br />

incorporated are exterior arcades, variation in roof planes and articulated<br />

facades to optimize the scale and massing of the building.<br />

The Environmental Analysis was prepared to consolidate related data into<br />

a comprehensive document that clearly defines the analysis, constraints,<br />

assets and outcomes related to the development of The Learning<br />

Resource Center.<br />

University of Hawaii <strong>Community</strong> <strong>College</strong>s April 2004<br />

Project No. CC-02-6188<br />

III-21


The Learning Resource Center at <strong>Windward</strong> <strong>Community</strong> <strong>College</strong><br />

PROJECT DEVELOPMENT REPORT<br />

IV.<br />

PRELIMINARY ENGINEERING DESIGN CRITERIA<br />

A. Introduction<br />

The preliminary engineering design criteria is intended to integrate site and utility<br />

systems improvements on a conceptual basis. Similarly, design criteria is<br />

introduced for structural, landscape, mechanical and electrical engineering to<br />

supplement the proposed architectural design concept for the Learning Resource<br />

Center.<br />

B. Summary Of Existing Site Conditions And Utilities<br />

1. Overview<br />

This section covers civil engineering criteria related to parking, circulation,<br />

handicap accessibility, site grading, water service, sewer service, and<br />

storm drainage. The sustainable attributes for the civil engineering are<br />

described under Section V.<br />

a. Parking: (4) handicap spaces and (75) regular spaces are<br />

provided plus (18) relocated handicapped parking spaces.<br />

b. Circulation: Access to parking is provided from the Banyan Drive<br />

loop road system. The fire access is provided from the vehicular<br />

access south of the Humanities Building, the west portion of Ilima<br />

Way (reconfigured), and the east portion of Ilima Way<br />

(reconfigured).<br />

c. Accessibility: Handicap accessibility is provided from the parking<br />

to the building. An accessible route is also provided to the front of<br />

the building for drop off and entrance into the building via the fire<br />

access area to the southeast. Accessible routes from the green<br />

mall area walkway system are also provided.<br />

d. Site Grading: The First Floor of the Learning Resource Center is<br />

approximately at elevation 228; the Second Floor at elevation 242.<br />

The grading will provide for access from the west at the Second<br />

Floor and from the east at the First Floor. The grading around the<br />

building will be adjusted to meet the aforementioned criteria and<br />

accommodate handicap access to both entry points as well as the<br />

entrance to the north. The north portion of the site is stepped to<br />

provide amphitheater seating to create a public area that would be<br />

contiguous with the Planetarium and the Arts/Humanities Building.<br />

e. Geotechnical Survey: To be furnished by the owner.<br />

University of Hawaii <strong>Community</strong> <strong>College</strong>s April 2004<br />

Project No. CC-02-6188<br />

IV-1


The Learning Resource Center at <strong>Windward</strong> <strong>Community</strong> <strong>College</strong><br />

PROJECT DEVELOPMENT REPORT<br />

f. Water Service: The water system will service the proposed<br />

Learning Resource Center from the 6” water main located near<br />

Ilima Way. The new facility will contain a fire sprinkler system<br />

similar to other buildings on campus since the water pressure is<br />

not 2000 psi. A sustainable water service system approach will<br />

reduce the potable water demand.<br />

g. Sewer System: The sewer system is in the process of being<br />

upgraded building by building. The existing sewer system needs<br />

maintenance due to settlement and root problems. The<br />

Department of Planning and Permitting (DPP), Site <strong>Development</strong><br />

Division, confirmed that the moratorium on plumbing fixture units<br />

imposed by 92 / PRU-3, condition 4, limiting development to a<br />

one-to-one replacement until the Kaneohe Sewage Treatment<br />

Plant is expanded, was lifted in the mid 1990s. DPP, Site<br />

<strong>Development</strong> Division will determine if the number of plumbing<br />

fixtures is within the sewer system capacity for each project on a<br />

case-by-case basis. A sustainable storm sewer system approach<br />

will reduce the flow rate.<br />

h. Storm Drainage System: The drainage anticipated for the<br />

Learning Resource Center will utilize drainage lines on either side<br />

of the site. There is a 36” drainage main to the north-northwest<br />

and a 24” drainage main to the south and southeast. Both of<br />

these mains flow to the east where they both have outlet<br />

structures that flow into an open drainage ditch. A sustainable<br />

storm drainage approach will reduce the storm drainage off of the<br />

site.<br />

2. Parking, Circulation and Accessibility<br />

a. Parking:<br />

1) Handicap Parking: There are four (4) handicap parking<br />

spaces provided for the facility. The proposed design will<br />

meet the current state and federal requirements related to<br />

the Americans with Disabilities Act (ADA) Accessibility<br />

Guidelines for Buildings and Facilities and the Architectural<br />

Barriers Act (ABA).<br />

2) Regular Parking: A new parking lot to include 80 parking<br />

spaces will be located directly across Hale Mana‘opono<br />

with access from Banyan Drive. The spaces will be 8’ – 6”<br />

x 22’ – 0”.<br />

3) Loading Areas: The loading area for the facility is located<br />

in the southwest portion of the facility. There are two (2)<br />

University of Hawaii <strong>Community</strong> <strong>College</strong>s April 2004<br />

Project No. CC-02-6188<br />

IV-2


The Learning Resource Center at <strong>Windward</strong> <strong>Community</strong> <strong>College</strong><br />

PROJECT DEVELOPMENT REPORT<br />

b. Circulation:<br />

loading areas for the facility. One space needs to be 12’<br />

wide by x 35’ long with a vertical clearance of at least 14’.<br />

The second loading area shall have minimum dimensions<br />

of 8’-6” wide by 19’ long with a vertical clearance of at least<br />

10 feet.<br />

1) Pedestrian Circulation: Pedestrian circulation to the site is<br />

from the parking via the sidewalk that is parallel to Banyan<br />

Drive and will be integrated with the overall campus<br />

walkway system.<br />

2) Vehicular Circulation: The vehicular circulation is primarily<br />

via the loop roadway system (Banyan Drive, Honeysuckle<br />

Road, and Maile Way). Vehicular access to the parking<br />

will be via the loop road network.<br />

3) Service Circulation: The service circulation to the building<br />

is via the west end of the modified Ilima Way. This access<br />

also doubles as a fire access approach to the building.<br />

4) Fire Access Circulation: The fire access to the building is<br />

via the (a) existing fire access south of the Humanities<br />

Building, (b) modified west portion of Ilima Way, and (c)<br />

modified east portion of Ilima Way.<br />

c. Accessibility:<br />

1) Handicap Accessibility from Parking: There are four (4)<br />

handicap accessible spaces for the Learning Resource<br />

Center located in the parking area east of Banyan Drive.<br />

There are (8) existing Handicap Accessible parking spaces<br />

that have been relocated from Ilima Way.<br />

2) Handicap Accessibility between Buildings: The following<br />

are handicap accessible routes adjacent to the Learning<br />

Resource Center: a) the sidewalk from the Student Center<br />

that is located east of Hale No‘eau and Hale La‘akea, b)<br />

the sidewalk that connects Hale La‘akea and the proposed<br />

Learning Resource Center, c) the sidewalk connecting<br />

Hale Palanakila and The Learning Resource Center, d) the<br />

sidewalk west of Hale Na‘auao and Hale Mana‘opono, e)<br />

The Learning Resource Center entrance walkway to the<br />

east of the building, f) the walkway running east and west<br />

between Hale Mana‘opono and Hale ‘Imiloa, and the<br />

University of Hawaii <strong>Community</strong> <strong>College</strong>s April 2004<br />

Project No. CC-02-6188<br />

IV-3


The Learning Resource Center at <strong>Windward</strong> <strong>Community</strong> <strong>College</strong><br />

PROJECT DEVELOPMENT REPORT<br />

3. Site Grading<br />

covered walkway from the vehicle dropoff area to the north<br />

of Hale Hokulani to Hale ‘Imiloa.<br />

3) See Figure IV-2.<br />

a. Existing Grading:<br />

The existing grading of the western portion of the proposed<br />

Learning Resource Center slopes from a high point near the Hale<br />

La‘akea building at the elevation of approximately 250 to the<br />

Existing Hale Manaleo building elevation of approximately 236.<br />

The existing grading continues to slope downward from the Hale<br />

Manaleo to both the Hale Mana‘opono and the Science Facility<br />

(Hale ‘Imiloa) at approximately 220. The site also slopes down to<br />

the Hale Hokulani elevation of approximately 226.<br />

b. Proposed Grading:<br />

The proposed first floor of The Learning Resource Center is at<br />

approximately 228. The second floor elevation is at approximately<br />

elevation 242. The western face of the building would have the<br />

exterior grade at approximately 241. This would facilitate the<br />

removal of ground water from the area around the building. This<br />

configuration would reduce the potential adverse affects of water<br />

against the west wall of the lowest floor. The grading of the<br />

southeastern side of the facility needs to accommodate the<br />

pedestrian walkway as well as the banyan tree root structure.<br />

Due to the extensive change in grade, the handicap accessibility<br />

will need to be handled in the eastern, western and northern<br />

portions of the facility.<br />

The northwestern portion of the site has been configured to<br />

accommodate an outdoor seating area/amphitheater between The<br />

Learning Resource Center and the Planetarium (Hale Hokulani).<br />

The stepped seating area permits the transition from the grade of<br />

the north entrance to The Learning Resource Center at<br />

approximately elevation 228 to the grade southeast outside of the<br />

Planetarium (Hale Hokulani) at approximately elevation 224.<br />

4. Geotechnical Survey<br />

A geotechnical survey of the site is typically furnished by the Owner and<br />

is required to define the subsurface conditions associated with The<br />

Learning Resource Center. The structural engineer should be consulted<br />

University of Hawaii <strong>Community</strong> <strong>College</strong>s April 2004<br />

Project No. CC-02-6188<br />

IV-4


The Learning Resource Center at <strong>Windward</strong> <strong>Community</strong> <strong>College</strong><br />

PROJECT DEVELOPMENT REPORT<br />

regarding the quantity and location of soil borings required for the<br />

proposed structural system. The geotechnical data should be available at<br />

the start of the design process.<br />

5. Water System<br />

a. Existing Water System:<br />

1) Current Water System Description: Due to the age and<br />

high maintenance of the system, the applicant proposes to<br />

develop a new system for installation throughout the<br />

campus. Water is supplied by the Board of Water Supply<br />

(BWS). The applicant has obtained approval from the State<br />

Department of Land and Natural Resources for a water<br />

allocation of 120,000 gallons per day (gpd).<br />

Director’s Report, PRU WCC 1994<br />

2) Existing Condition: The existing water distribution system<br />

to the campus buildings for the most part has been up<br />

graded. The piping within the buildings is older and has<br />

not been replaced.<br />

3) Design Rate of Use: 4,000 gallons per acre = 285,000<br />

gallons per day<br />

WCC MPR 1989 Page 72<br />

4) Calculated Use by Function: 2000 students x 60 gallons<br />

per day = 120,000 gallons per day. WCC has received<br />

approval to use 120,000 gallons per day (gpd) based on<br />

projected demand. WCC submitted a water master plan in<br />

August 1993.<br />

WCC MPR 1989 Page 71<br />

5) Fire Department Water Flow Rate: The Fire Department of<br />

the City and County of Honolulu requires a flow rate of<br />

2000 gallons per minute (gpm) with a 20 pounds per<br />

square inch (psi) residual pressure. The present system is<br />

only capable of providing 1,100 gallons per minute (gpm).<br />

The Fire Department responded to the applicant’s proposal<br />

to install sprinklers in combination with fire hydrants by<br />

stating “…we have no objections to the proposal providing<br />

that the existing 1,100 gallons per day (gpd) water<br />

availability is supplemented with a combined building<br />

sprinkler and hydrant system that is in compliance with<br />

University of Hawaii <strong>Community</strong> <strong>College</strong>s April 2004<br />

Project No. CC-02-6188<br />

IV-5


The Learning Resource Center at <strong>Windward</strong> <strong>Community</strong> <strong>College</strong><br />

PROJECT DEVELOPMENT REPORT<br />

National Fire Protection Association13, Uniform Fire Code<br />

Article 10 and Board of Water Supply Standards.”<br />

Directors Report PRU WCC 1994 page 22<br />

6) Water System Construction (Science Facility):<br />

The water service that was part of the Science Facility<br />

(Hale ‘Imiloa) project consisted of 8” service in the adjacent<br />

Banyan Drive and the roadway to the Banyan Drive portion<br />

northwest of the Science Facility. The construction also<br />

included an 8” service to the new facility. The water<br />

service construction included a connection to Board of<br />

Water Supply (BWS) 16” main. The connection also<br />

included a pressure-reducing valve near the connection to<br />

the BWS main.<br />

7) Water System Construction (Humanities Building): In 1996<br />

the water service was extended from the 8” service that<br />

was constructed prior to the juncture of Banyan Drive and<br />

Honeysuckle Road and prior to the Science Facility.<br />

8) Water System Construction (Student Center): The water<br />

main construction in the area of the Student Center (Hale<br />

Akoakoa) was completed in the 2002 time frame. The 8”<br />

water main was constructed along Honeysuckle Road,<br />

Maile Way, and Banyan Drive (near Hale Kuhina and Hale<br />

Alakai). This work included the abandonment of a 4” water<br />

line near Hale Kuhina, a 6” water line near Hale Alakai, 4”<br />

water line along Maile Way, a 4” water line parallel to<br />

Honeysuckle, a 3” water line near Hale La‘Akea, a 4” water<br />

line in Ilima Way, and a 2” water line Hale Mana‘opono.<br />

9) Water System Upgrade (Campus-wide 2002 - 2003): The<br />

water service between buildings has been upgraded.<br />

Currently the water piping between buildings is newer<br />

system piping. The older system that was in need of repair<br />

has been abandoned or replaced.<br />

Refer to Engineering Solutions Inc. drawings T-1 to T-4<br />

and C-1 to C-12 dated 4-19-2002 for the extensive system<br />

upgrades.<br />

b. Proposed Water System (The Learning Resource Center)<br />

1) Proposed Water System Demand<br />

The demand is projected for the campus by using the<br />

number of students at the facility.<br />

University of Hawaii <strong>Community</strong> <strong>College</strong>s April 2004<br />

Project No. CC-02-6188<br />

IV-6


The Learning Resource Center at <strong>Windward</strong> <strong>Community</strong> <strong>College</strong><br />

PROJECT DEVELOPMENT REPORT<br />

2,000 students x 60 gallons per day = 120,000 gallons per<br />

day.<br />

WCC has received approval to use 120,000 gallons per<br />

day (gpd) based on projected demand. Existing<br />

Reservoirs: 100,000 gallons. *<br />

Water Demand for The Learning Resource Center<br />

calculation is as follows:<br />

4,000 gallons per acre or 60 gallons per person.**<br />

Site 1.63 acres x 4,000 gal per acre = 6,520 gallons per<br />

day. 60 gallons per person x 968 people = 34,048 gallons<br />

Say 34,000.<br />

It is anticipated that the actual water demand for The<br />

Learning Resource Center may be reduced by using<br />

LEED® sustainable design techniques. Refer to LEED®<br />

Water Efficiency Credit 3 Water Use Reduction, Section V.<br />

Demand Factor: 1.5 x Average day*<br />

1.5 x 34,000 gallons per day = 51,000 gallons per day =<br />

0.590 gps<br />

Impact to the Existing System: 8” diameter minimum for<br />

the fire loop. Service lateral to the building will likely be 3”<br />

or 4”.<br />

* Water System Design Criteria 2002<br />

** Information from WCC Master Plan 1989<br />

2) Proposed Water System<br />

The water system will service The Learning Resource<br />

Center from the 6” water main located near Ilima Way.<br />

The new facility will contain a fire sprinkler system similar<br />

to other buildings on campus since the water pressure is<br />

below 2000 psi. This provision has been acceptable to the<br />

approving agencies. Since the proposed Learning<br />

Resource Center footprint will be over the existing water<br />

lines, the water lines need to be rerouted. It is<br />

recommended that the new water service be a 3” to 4”<br />

lateral. Any existing older water lines that are outside of<br />

the building and will feed The Learning Resource Center<br />

should be replaced with new lines. See Figure IV.3.<br />

University of Hawaii <strong>Community</strong> <strong>College</strong>s April 2004<br />

Project No. CC-02-6188<br />

IV-7


The Learning Resource Center at <strong>Windward</strong> <strong>Community</strong> <strong>College</strong><br />

PROJECT DEVELOPMENT REPORT<br />

6. Wastewater System<br />

a. Existing Sewer System:<br />

1) Current Sewer System Description: The sewer system is<br />

in the process of being upgraded building by building. The<br />

existing sewer system needs maintenance due to<br />

settlement and root problems.<br />

2) Capacity: Mr. Nishimura, Department of Planning and<br />

Permitting (DPP), Site <strong>Development</strong> Division, confirmed<br />

that the moratorium on plumbing fixture units imposed by<br />

92 / PRU-3, condition 4, i.e. limiting development to a oneto-one<br />

replacement until the Kaneohe Sewage Treatment<br />

Plant is expanded, was lifted in the mid 1990s. DPP, Site<br />

<strong>Development</strong> Division will determine if the number of<br />

plumbing fixtures is within the sewer system capacity for<br />

each project on a case-by-case basis.<br />

DPP confirmed that the master application form may be<br />

downloaded from their website, i.e., Site <strong>Development</strong><br />

Division, Master Application form, sewer portion. If the<br />

proposed project’s plumbing fixture unit count exceeds the<br />

sewer system’s capacity, DPP will work with the applicant<br />

on a solution to meet capacity.<br />

3) Existing Condition: “The applicant proposes to phase the<br />

installation of a new system of sewer lines throughout the<br />

campus for connection to the City sewer system.”<br />

Director’s Report, PRU WCC 1994, page 22.<br />

“The current system maintenance staff has indicated that<br />

the existing system must be constantly maintained, with<br />

settlement and root problems being common. Based on<br />

the high maintenance requirements and age of the system,<br />

installation of new sewer lines and laterals throughout the<br />

campus is recommended. The existing lines can be<br />

abandoned in-place, except where they interfere with new<br />

construction. The existing sanitary manholes should be<br />

removed to approximately two feet below grade and<br />

backfilled, with complete removal in new facility locations.”<br />

Plan Review Use for a Five Year Master Plan for the University of<br />

Hawaii, <strong>Windward</strong> <strong>Community</strong> <strong>College</strong> 1992<br />

University of Hawaii <strong>Community</strong> <strong>College</strong>s April 2004<br />

Project No. CC-02-6188<br />

IV-8


The Learning Resource Center at <strong>Windward</strong> <strong>Community</strong> <strong>College</strong><br />

PROJECT DEVELOPMENT REPORT<br />

4) Master Plan <strong>Concept</strong>: The plan is to have minimum sewer<br />

size of 6” for all lines other than building laterals.<br />

5) Sewer Construction (Science Facility): At the Science<br />

Facility (Hale ‘Imiloa) a 4” lateral was connected to a new<br />

6” which connects to sewer lines leading to the main sewer<br />

line in Kea‘ahala Road<br />

6) Sewer Construction (Humanities Building): At the<br />

Humanities Building (Hale Palanakila) a 6” lateral sewer<br />

service that turns into an 8” line connecting to another 8”<br />

main along Ilima Way. The 8” main flows makai and<br />

eventually to the sewer mains in Kea‘ahala Road.<br />

7) Sewer Construction (Student Center): At the Student<br />

Center (Hale Akoakoa) a number of 6” laterals were<br />

connected to an 8” sewer line that flows toward the<br />

Humanities Building (Hale Palanakila). The 8” sewer main<br />

located in the green mall area is flowing toward Diamond<br />

Head.<br />

b. Proposed Sewer System (Learning Resource Center):<br />

1) Sewer System Demand:<br />

Average Wastewater Flow: 25 gal per capita per day<br />

(3)*for schools 25 gpcd x 568 pcd = 14,200 gallons per<br />

day.<br />

Maximum Wastewater Flow: Flow factor = 5 (3)*<br />

5 x 14,200 = 71,000 gal per day<br />

Dry Weather Infiltration: 5 gpcd for above water table (3)*<br />

5 gpcd x 568 p = 2,840 gpd<br />

Design Average Flow: 14,200 gpd + 2,840 gpd = 17,040 gpd<br />

71,000 gpd + 2840 gpd = 73,840 say 74,000 gpd<br />

University of Hawaii <strong>Community</strong> <strong>College</strong>s April 2004<br />

Project No. CC-02-6188<br />

IV-9


The Learning Resource Center at <strong>Windward</strong> <strong>Community</strong> <strong>College</strong><br />

PROJECT DEVELOPMENT REPORT<br />

Wet Weather Infiltration: 1290 gal per acre per day<br />

1290 gad x 1.630 acre = 2,103 gpd<br />

Design Peak Flow: 73,840 gpd + 2038 gpd = 75,878 gpd<br />

Say 76,000 gpd Q=0.88 gals /sec<br />

It is anticipated that the actual sewer system demand for<br />

The Learning Resource Center may be reduced by using<br />

LEED® sustainable design techniques. Refer to LEED®<br />

Water Efficiency Credit 2, Innovative Waste Water<br />

Technologies, Section V.<br />

2) Proposed Sewer Construction (Learning Resource<br />

Center): The sewer connection for The Learning Resource<br />

Center will connect to the existing 8” sewer located<br />

adjacent to Ilima Way. The 8” main flows makai and<br />

eventually to the sewer mains in Kea‘ahala Road.<br />

7. Storm Drainage Sytem<br />

Since a portion of the existing 8” sewer is would be within<br />

the footprint of the proposed Learning Resource Center, a<br />

portion the lines located in Ilima Way proposed for<br />

rerouting to the southeast around the existing Banyan<br />

trees. A portion of the existing 6” sewer serving the<br />

Humanities Building (Hale Palanakila) will need to be<br />

relocated since the existing line falls within the footprint of<br />

the proposed Learning Resource Center. See Figure<br />

IV.4.<br />

a. Existing Storm Drainage System:<br />

1) Current Storm Drainage System Description: “The existing<br />

storm drainage system is composed of a combination of<br />

open ditches and underground drain lines. Most of the<br />

Campus is drained by numerous inlets which intercept runoff<br />

along the roadway area. This runoff is then piped through<br />

the drainage system and outlet along the outskirts of the<br />

Campus property. Toward the northeastern side of the<br />

campus, there is an open drainage ditch which serves as the<br />

main drainage system for that side of the campus. All of the<br />

drainage from WCC eventually goes into two well-defined<br />

natural drainage ditches. These drainage ditches run along<br />

both sides of Kea‘ahala Road.”<br />

Plan Review Use for a Five Year Master Plan for the University of Hawaii,<br />

<strong>Windward</strong> <strong>Community</strong> <strong>College</strong> 1992 page 37.<br />

University of Hawaii <strong>Community</strong> <strong>College</strong>s April 2004<br />

Project No. CC-02-6188<br />

IV-10


The Learning Resource Center at <strong>Windward</strong> <strong>Community</strong> <strong>College</strong><br />

PROJECT DEVELOPMENT REPORT<br />

2) Capacity: “No changes to the existing storm water drainage<br />

system are proposed. Runoff will be intercepted through<br />

inlets within paved areas, piped to the outskirts of the<br />

property for discharge into the City storm drainage system.”<br />

“Renovation and development of WCC will increase peak<br />

runoff produced on the campus. The increased peak runoff<br />

can be detained on-site in open areas located around the<br />

campus and outlet during off-peak times.”<br />

Plan Review Use for a Five Year Master Plan for the University of Hawaii,<br />

<strong>Windward</strong> <strong>Community</strong> <strong>College</strong> 1992, page 37.<br />

3) Master Plan <strong>Concept</strong>: “The proposed storm drainage system<br />

will continue the same concept, which services the existing<br />

campus. Runoff will be intercepted thru inlets within paved<br />

areas, piped to the outskirts of the property and outlet to<br />

match the existing drainage outlet locations. “<br />

Plan Review Use for a FiveYear Master Plan for the University of Hawaii,<br />

<strong>Windward</strong> <strong>Community</strong> <strong>College</strong> 1992 page 37<br />

4) Storm Drainage Construction (Science Facility): During the<br />

construction of the Science Building (Hale ‘Imiloa) the open<br />

drainage ditch was developed into drain inlets and 12” to 36”<br />

drainage-lines on the mauka and Diamond Head sides of the<br />

Science Center. There were 11 area drainage catch basins<br />

installed as well as a drainage inlet and an outlet structures.<br />

5) Storm Drainage Construction (Humanities Building): The<br />

storm drainage system to the southeast of the Humanities<br />

Building (Hale Palanakila) consists of 24”, 30” and 36” storm<br />

drainage lines connecting to the 36” Storm Drainage Main<br />

that crosses Banyan Drive. There are also storm drainage<br />

lines that cross Banyan Drive adjacent to the Humanities<br />

Building and proceed to the north-northwest to a drainage<br />

outlet structure located beyond the parking structure.<br />

6) Storm Drainage Construction (Student Center): The storm<br />

drainage system for the Student Center (Hale Akoakoa)<br />

consists of 8”, 18”, 24”, and 30” drainage lines connecting to<br />

the 30” main that crosses the Maile Way and proceeds in the<br />

Diamond Head direction.<br />

University of Hawaii <strong>Community</strong> <strong>College</strong>s April 2004<br />

Project No. CC-02-6188<br />

IV-11


The Learning Resource Center at <strong>Windward</strong> <strong>Community</strong> <strong>College</strong><br />

PROJECT DEVELOPMENT REPORT<br />

b. Proposed Storm Drainage System (The Learning Resource<br />

Center)<br />

1) Storm Drainage Demand:<br />

The proposed Learning Resource Center has a roof area of<br />

approximately 56,000 square feet that will contribute to<br />

storm systems. Additional hardscape maybe created with<br />

introduction of the amphitheater/Plaza area to the north of<br />

The Learning Resource Center and with the inclusion of the<br />

fire access and turnarounds that are located along the<br />

existing Ilima Way to the southwest and southeast of The<br />

Learning Resource Center.<br />

It is anticipated that the actual storm drainage system<br />

demand for The Learning Resource Center may be reduced<br />

by using LEED® sustainable design techniques. (Refer to<br />

LEED® Sustainable Sites, Credit 6, Storm Water<br />

Management, Section V.)<br />

2) Storm Drainage Construction: The drainage anticipated for<br />

The Learning Resource Center will utilize drainage lines on<br />

either side of the site. There is a 36” drainage main to the<br />

north-northwest and a 24” drainage main to the south and<br />

southeast. Both of these mains flow to the east where they<br />

both have outlet structures that flow into an open drainage<br />

ditch. See Figure IV.5.<br />

The Learning Resource Center site is in the Storm Drain<br />

Basin B5 which has 9.48 acres and 18.5 cubic feet per<br />

second (CFS) Runoff Flow. The proposed parking<br />

associated with the new facility is anticipated for Storm Drain<br />

Basin B8 which has 9.74 acres and 18.3 cubic feet per<br />

second (CFS) Runoff Flow.*<br />

* Plan Review Use for a Five-Year Master Plan for the University of<br />

Hawaii, <strong>Windward</strong> <strong>Community</strong> <strong>College</strong> 1992, Figure 20 Storm Drain<br />

Basins.7<br />

8. Sustainable Design (Refer to Section V)<br />

C. Landscape<br />

1. Overview<br />

The landscaping concept for The Learning Resource Center shall be in<br />

conformance with the Ultimate Landscape Plan that is part of the Plan<br />

University of Hawaii <strong>Community</strong> <strong>College</strong>s April 2004<br />

Project No. CC-02-6188<br />

IV-12


The Learning Resource Center at <strong>Windward</strong> <strong>Community</strong> <strong>College</strong><br />

PROJECT DEVELOPMENT REPORT<br />

Review Use resolution and the Master Plan for <strong>Windward</strong> <strong>Community</strong><br />

<strong>College</strong>. The landscape plans will be developed in the course of the final<br />

Schematics, Design <strong>Development</strong> and Construction Documents phases.<br />

For purposes of the Project <strong>Development</strong> Report, the Design Parameters<br />

and Plant List are summarized as follows:<br />

2. Design Parameters<br />

a. The landscape plan shall retain the character of the existing<br />

campus.<br />

b. Retain existing banyan trees and remove mango and monkey pod<br />

trees.<br />

c. Pedestrian circulation walks shall generally conform to the<br />

concept established in the master plan.<br />

d. Provide enhanced landscaping adjacent to buildings as defined in<br />

the master plan.<br />

e. Provide one species of flowering tree for parking lot landscaping<br />

and in accordance with the City and County of Honolulu Land Use<br />

Ordinance (recommend matching trees in existing parking lots for<br />

consistency and unity).<br />

3. Plant List<br />

a. Trees<br />

Scientific Name<br />

Acacia confusa<br />

Aleurites moluccana<br />

Bauhinia blakeana<br />

Bauhinia monandra<br />

Fagraea retusa<br />

Ficus Retusa<br />

Lagestroemia speciosa<br />

Lassia J x F ‘Wilhemina Tenny’<br />

Michelia alba<br />

Plumeria sp.<br />

Samanea saman<br />

Tabeuia pentaphylla<br />

Common Name<br />

Formosan Koa<br />

Kukui<br />

Hong Kong Orchid Tree<br />

St. Thomas tree<br />

Pua Kenikeni<br />

Chinese Banyan<br />

Giant Crape Myrtle<br />

Rainbow Shower<br />

Pak Lan<br />

Plumeria<br />

Monkeypod<br />

Pink Tecoma<br />

b. Palms<br />

Archotonophoenix alexandrae<br />

Chrysalipocarpus lutescens<br />

Pritchardia sp.<br />

Ptychosperma macarthurii<br />

Roystonea regia<br />

Alexander Palm<br />

Areca Palm<br />

Lolu Palm<br />

Macarthur Palm<br />

Royal Palm<br />

University of Hawaii <strong>Community</strong> <strong>College</strong>s April 2004<br />

Project No. CC-02-6188<br />

IV-13


The Learning Resource Center at <strong>Windward</strong> <strong>Community</strong> <strong>College</strong><br />

PROJECT DEVELOPMENT REPORT<br />

c. Shrubs<br />

Acalpha w. var. macafeana<br />

Alpina purpurata<br />

Bixa orellana<br />

Breynia nivosa roseo-picta<br />

Brunfelsia latifolia<br />

Cordyline terminalis<br />

Heliconia sp.<br />

Ixoria sp.<br />

Monstera deliciosa<br />

Musseanda sp.<br />

Philodendron<br />

Beefsteak Plant<br />

Red Ginger<br />

Lipstick Plant<br />

Snow Bush<br />

Yesterday-Today-Tomorrow<br />

Ti<br />

Heliconia<br />

Ixoria<br />

Monstera<br />

Musseanda<br />

Philodendron<br />

d. Ground Covers<br />

Asparagus sprengeri<br />

Gardenia radicans<br />

Microsorium scolopendria<br />

Ophiopogon japonicus<br />

Scindapsus<br />

Syngoium sp.<br />

Asperagus Fern<br />

Creeping Gardenia<br />

Laua’e Fern<br />

Mondo Grass<br />

Taro Vine<br />

Syngoium<br />

e. Grasses<br />

Paspalum congugatum<br />

Stenotaphrum secundatum<br />

Hilo Grass<br />

St. Augustine Grass<br />

4. Irrigation<br />

The Master Plan recommends the inclusion of “enhanced landscaping”<br />

adjacent to and surrounding each building. Permanent underground<br />

irrigation will be provided for this area only and integrated with a system<br />

of hose bibs to facilitate hand watering at selected times. The extent of<br />

landscaping will be developed during the subsequent design phases.<br />

D. Structural Engineering<br />

1. Overview<br />

At the time of this writing the code adopted for use in the City and County<br />

of Honolulu is the 1997 Uniform Building Code. The 2000 edition is<br />

pending review and adoption by the City.<br />

University of Hawaii <strong>Community</strong> <strong>College</strong>s April 2004<br />

Project No. CC-02-6188<br />

IV-14


The Learning Resource Center at <strong>Windward</strong> <strong>Community</strong> <strong>College</strong><br />

PROJECT DEVELOPMENT REPORT<br />

2. Design Criteria<br />

For purposes of this report, it is recommended that, as a minimum, the<br />

structural design be consistent with the following criteria:<br />

a. Design Assumptions: Assume concrete shear walls and<br />

concrete frame system, i.e. concrete columns and beams. Walls<br />

may be masonry in place of concrete walls. The structural system<br />

is subject to further evaluation during the design phases.<br />

b. Codes and Standards: Uniform Building Code 1997 edition<br />

c. Design Live Loads:<br />

Roof<br />

Ground Floor<br />

20 psf (reducible)<br />

100 psf (reducible)<br />

d. Design Dead Loads (additional to self-weight):<br />

Roof<br />

Ground Floor<br />

Roof-Mounted Equipment<br />

e. Wind:<br />

10 psf<br />

20 psf partition load<br />

Weight as provided by<br />

equipment manufacturer<br />

Basic Wind Speed<br />

80 mph<br />

Exposure Category<br />

B<br />

Primary Frame Design Method Method 1 (Normal Force<br />

Method)<br />

Building Classification<br />

Enclosed/Unenclosed<br />

Importance Factor 1.0<br />

f. Seismic<br />

E. MECHANICAL ENGINEERING<br />

1. Overview<br />

Lateral Force Procedure<br />

Equivalent Static<br />

Zone<br />

2a<br />

C t<br />

Rw 6.5<br />

Importance Factor 1.0<br />

The following sections summarize the design criteria for heating,<br />

ventilation, air conditioning (HVAC), plumbing and fire protection systems.<br />

University of Hawaii <strong>Community</strong> <strong>College</strong>s April 2004<br />

Project No. CC-02-6188<br />

IV-15


The Learning Resource Center at <strong>Windward</strong> <strong>Community</strong> <strong>College</strong><br />

PROJECT DEVELOPMENT REPORT<br />

2. HVAC<br />

Design Criteria<br />

a. Codes and Standards<br />

Current editions with City and County of Honolulu Amendments<br />

where applicable:<br />

Uniform Building Codes<br />

Uniform Fire Codes<br />

Uniform Mechanical Code<br />

State of Hawaii Elevator and Boiler Safety Code<br />

State of Hawaii Department of Health Title 39<br />

NFPA 90 A and B<br />

NFPA 96<br />

ASHRAE Fundamentals<br />

ASHRAE Standard 55<br />

ASHRAE Standard 62-2001<br />

ASHRAE Standard 90.1<br />

SMACNA Guidelines for Duct Construction<br />

Design Conditions<br />

Indoor Design for all occupied spaces:<br />

75 degrees Fahrenheit dry bulb<br />

Maximum 60 percent relative humidity<br />

Outdoor Design<br />

Per ASHRAE recommendations, use peak moisture conditions for<br />

design of outside air systems.<br />

b. Systems<br />

Descriptions<br />

Condenser water air conditioning systems using packaged air<br />

handling units with integral compressors, condensers and<br />

refrigerant coils. Constant temperature variable air volume air<br />

distribution systems serving all occupied spaces.<br />

Temperature Control Zoning<br />

Temperature control zones based on occupancy, usage and<br />

exposure. Separate zones for corner exposures. Maximum depth<br />

University of Hawaii <strong>Community</strong> <strong>College</strong>s April 2004<br />

Project No. CC-02-6188<br />

IV-16


The Learning Resource Center at <strong>Windward</strong> <strong>Community</strong> <strong>College</strong><br />

PROJECT DEVELOPMENT REPORT<br />

of perimeter zones in open plan areas to be 12 feet. Maximum<br />

size VAV box based on maximum noise criteria (NC) of 30.<br />

Air Handling Units<br />

Size of air handling equipment based on expected occupancy,<br />

hours of operation and usage. Maximum size of air handling unit<br />

to be 14,000 cubic feet per minute (CFM) of air supply. Air<br />

handling units above 2,000 CFM to have variable volume controls.<br />

Air handling units above 5,000 CFM to have variable frequency<br />

drive for fans with mixed-flow characteristic fan wheels.<br />

All air handling units to be located in sound attenuated mechanical<br />

equipment rooms, maximum NC of 35 immediately outside of fan<br />

rooms.<br />

Outside Air Systems<br />

Separate, dedicated outside air systems will serve the entire<br />

building and be sized to provide dehumidification for all air<br />

conditioned spaces and positive building pressurization under all<br />

anticipated exhaust and normal ambient wind conditions.<br />

Units to be all stainless steel construction with all copper coils.<br />

Units to employ refrigerant heat recovery to provide 100 percent of<br />

reheat required to supply neutral air at a temperature of 75<br />

degrees and dew point suitable to maintain a maximum of 60<br />

percent relative humidity in all air conditioned spaces at peak<br />

loads.<br />

Condenser Water System<br />

Distribution to all air handling units will be handled via variable<br />

flow piping system using copper and welded steel piping. Buried<br />

schedule piping from building to remote site cooling tower<br />

location. Two primary and two secondary condenser water pumps<br />

with variable frequency drives, each pump sized for a minimum of<br />

70 percent of full load.<br />

Stainless steel plate-frame heat exchangers between building<br />

distribution system and open tower cooling system. Minimum two<br />

heat exchangers, each sized for 100 percent of full load.<br />

Cooling towers shall be open, induced draft counter flow towers<br />

with all stainless steel construction. Two separate fan motors, one<br />

for full load and one for approximately 40 percent full load.<br />

Minimum of two cells, each sized for 70 percent of full load.<br />

University of Hawaii <strong>Community</strong> <strong>College</strong>s April 2004<br />

Project No. CC-02-6188<br />

IV-17


The Learning Resource Center at <strong>Windward</strong> <strong>Community</strong> <strong>College</strong><br />

PROJECT DEVELOPMENT REPORT<br />

3. Plumbing<br />

a. Design Criteria<br />

Codes and Standards<br />

Current editions with City and County of Honolulu Amendments<br />

Where applicable:<br />

Uniform Building Code<br />

Uniform Plumbing Code<br />

State of Hawaii Elevator and Boiler Safety Code<br />

NFPA Standards<br />

b. Systems Description<br />

Domestic Water<br />

Furnished at street pressure through a pressure reducing valve<br />

stations.<br />

Domestic Hot Water<br />

Domestic hot water generated by air-to-water heat pumps with<br />

electric backup at the storage tanks. Hot water at 140 degrees F<br />

and distributed at 120 degrees F through automatic mixing valve.<br />

Temperature maintenance for domestic hot water systems<br />

provided by re-circulating piping and pumps.<br />

Sanitary Sewer<br />

Waste lines for plumbing fixtures collected and piped by gravity to<br />

site sanitary sewer mains. Provide maximum 1,500 gallon precast<br />

concrete grease interceptor for food service operation.<br />

Confirm final sizing with City and County of Honolulu Division of<br />

Environmental Services.<br />

Roof Drainage<br />

4. Fire Protection<br />

Roof drainage provided by internal, cast iron rain leaders piped to<br />

site mains. Separate overflow rood drains piped to grade.<br />

a. Design Criteria<br />

University of Hawaii <strong>Community</strong> <strong>College</strong>s April 2004<br />

Project No. CC-02-6188<br />

IV-18


The Learning Resource Center at <strong>Windward</strong> <strong>Community</strong> <strong>College</strong><br />

PROJECT DEVELOPMENT REPORT<br />

Codes and Standards<br />

Current editions with City and County of Honolulu Amendments<br />

where applicable:<br />

Uniform Building Code<br />

Uniform Fire Code<br />

State of Hawaii Elevator and Boiler Safety Code<br />

NFPA 13<br />

NFPA 14<br />

NFPA 25<br />

Sprinklers<br />

All areas of the new buildings to be fully protected by wet-type fire<br />

extinguishing systems.<br />

Standpipes<br />

Manual standpipes with hose valve located in all exit stairwell and<br />

interconnected at the base of the building. Standpipe will be precharged<br />

with domestic water.<br />

5. Sustainable Design (Refer to Section V)<br />

F. Electrical Engineering<br />

1. Overview<br />

a. The information below defines a preliminary electrical<br />

infrastructure to The Learning Resource Center, parts of which are<br />

not included at this time; however, the quality level is defined.<br />

2. HECO Requirements<br />

a. Per as-built construction documents of WCC, electric utility service<br />

is provided by Hawaiian Electric Company (HECO) overhead<br />

service at 12,470 volts, 3 phase through two underground service<br />

circuits. The power is primarily metered and controlled in the main<br />

electrical metering and switching vault located at the northeast<br />

corner of the student/public parking lot on Kea‘ahala Road.<br />

Distribution to the various campus electrical distribution handholes<br />

is provided at 12.47 kV through loop underground feeder circuits.<br />

Building utilization voltages shall be 208Y/ 120 volts, 3 phase and<br />

480Y / 277 volts, 3 phase. Secondary feeders from the electrical<br />

University of Hawaii <strong>Community</strong> <strong>College</strong>s April 2004<br />

Project No. CC-02-6188<br />

IV-19


The Learning Resource Center at <strong>Windward</strong> <strong>Community</strong> <strong>College</strong><br />

PROJECT DEVELOPMENT REPORT<br />

distribution handholes to the respective building panels shall be<br />

via underground feeder circuits.<br />

b. Per discussions with HECO, the primary electrical service capacity<br />

is sufficient to support the additional electrical load of The<br />

Learning Resource Center.<br />

3. Existing Site Conditions<br />

a. Hale Manaleo presently occupies the campus site on which The<br />

Learning Resource Center will be built. An electrical improvement<br />

project was recently completed to provide underground electrical<br />

feeders to the building and to disconnect it from the adjacent<br />

overhead electrical service. This new underground electrical<br />

service also feeds Hale Mana‘opono and Hale Na‘auao to the<br />

north.<br />

b. A portion of the original overhead service (electrical, night lighting<br />

circuits, telephone, data, fire alarm, and security) along Ilima Way<br />

remains, which presently feeds Hale Manaleo, Hale La‘akea, and<br />

Hale No‘eau, and crosses Honeysuckle Road to feed the Haloa<br />

and ‘Iolani buildings on the State Hospital site. This overhead<br />

service will be removed to avoid conflict with The Learning<br />

Resource Center. Reconnection of electrical, telephone, data, fire<br />

alarm, and security services to the above listed buildings to<br />

remain shall be considered prior to termination of the overhead<br />

service along Ilima Way.<br />

c. Similar to the electrical utility distribution loop, an underground<br />

communications duct loop distributes night lighting circuits,<br />

telephone, data, fire alarm, and security services to the various<br />

buildings on the campus via communication distribution<br />

handholes, with exception to the above buildings still connected to<br />

overhead services. On-campus telephone, data, fire alarm and<br />

security systems are centrally located in [building(s)]. New<br />

telephone, data, fire alarm, and security cabling shall be provided<br />

from the central distribution location to The Learning Resource<br />

Center within the existing communications duct.<br />

4. On-Site Power & Communications<br />

a. Electrical service to The Learning Resource Center shall be<br />

obtained from existing EHH #12A located at the turnaround on the<br />

east side of Hale Palanakila (Arts & Humanities Building). The<br />

12.47 kV primary electrical service shall be tapped and extended<br />

via underground feeders to a new pad-mounted dry-type<br />

transformer to step down the primary voltage to 480Y/277V, 3-<br />

University of Hawaii <strong>Community</strong> <strong>College</strong>s April 2004<br />

Project No. CC-02-6188<br />

IV-20


The Learning Resource Center at <strong>Windward</strong> <strong>Community</strong> <strong>College</strong><br />

PROJECT DEVELOPMENT REPORT<br />

phase utilization voltage. The transformer shall be located on the<br />

southwest side of the building, preferably adjacent to the<br />

turnaround for maintenance considerations. Secondary electrical<br />

service shall be via underground feeders to a 480Y/277V<br />

switchboard/distribution panel located in the first floor Central<br />

Electrical Room of The Learning Resource Center. The 480/277<br />

voltages shall be primarily utilized for mechanical and lighting<br />

systems. Step-down transformers shall be utilized for 208Y/120<br />

voltages for general power distribution throughout The Learning<br />

Resource Center.<br />

b. Communications services (telephone, data, fire alarm, and<br />

security) shall be obtained from existing CMH #9 adjacent to EHH<br />

#12A. New telephone, data, fire alarm, and security cabling shall<br />

be pulled within the existing communications duct from the central<br />

distribution center located in [building(s)] to existing CMH #9 and<br />

extended to the Central Data Room of The Learning Resource<br />

Center via underground communications conduits. Night lighting<br />

circuits shall also be extended to provide power to site lighting<br />

poles in the area of The Learning Resource Center.<br />

5. Design Criteria<br />

a. Electrical Codes and Standards:<br />

1) NFPA 70 National Electrical Code (NEC)<br />

2) NFPA 101 Life Safety Code<br />

3) IES Lighting Illuminating Engineering Society<br />

Handbook<br />

4) 1997 UBC Uniform Building Code<br />

5) 1997 UFC Uniform Fire Code<br />

b. Power Service<br />

1) Primary power will be extended from the primary circuits(s)<br />

electrical handhole EHH #12A. 15 kV rated primary cables<br />

will tap into the existing circuit(s) and extend via a new<br />

underground primary duct to a new pad mounted<br />

transformer with integral switch. The utilization voltage of<br />

the transformer shall be 480Y/277 volts, 3 phase, 4-wire.<br />

2) An underground secondary duct with secondary cables will<br />

be run from the new transformer to the Main Switchboard.<br />

University of Hawaii <strong>Community</strong> <strong>College</strong>s April 2004<br />

Project No. CC-02-6188<br />

IV-21


The Learning Resource Center at <strong>Windward</strong> <strong>Community</strong> <strong>College</strong><br />

PROJECT DEVELOPMENT REPORT<br />

3) The Main Switchboard will be rated as required and shall<br />

consist of a pull section, check meter section and a main<br />

breaker section and distribution section with breakers for<br />

sub-feeders. Voltage and ampere meters will be provided.<br />

4) Utilization Panels will be located within the Central<br />

Electrical Room and Electrical Closets within the building.<br />

c. Communications Services<br />

1) Communications (telephone, data, fire alarm and security)<br />

services shall be extended from CMH #9 to respective<br />

backboards, enclosures, or panels in the Central Data<br />

Room via an underground duct.<br />

2) All necessary system cabling to connect The Learning<br />

Resource Center to the campus communications<br />

distribution center for the listed systems shall be inclusive<br />

to the project.<br />

3) Cabling within the building shall be distributed via panels,<br />

backboards, and raceways dedicated to each system as<br />

coordinated with the appropriate WCC department.<br />

d. Lighting<br />

1) General illumination shall be provided by fluorescent<br />

luminaires with electronic ballast and T8 (or T5) lamps.<br />

2) Fluorescent lamps shall be low-mercury, TCLP-compliant.<br />

3) Indirect / direct pendant-mounted luminaires shall be<br />

utilized for computer / circulation areas.<br />

4) Parabolic louvers or prismatic lens will be provided as<br />

determined.<br />

5) Recessed downlights, where required, shall have compact<br />

fluorescent lamps with electronic ballast. Lamps shall be<br />

provided with color temperature of 3500K.<br />

6) Zone light switches will be provided for conference/<br />

teaching / learning areas to provide multiple illumination<br />

levels.<br />

University of Hawaii <strong>Community</strong> <strong>College</strong>s April 2004<br />

Project No. CC-02-6188<br />

IV-22


The Learning Resource Center at <strong>Windward</strong> <strong>Community</strong> <strong>College</strong><br />

PROJECT DEVELOPMENT REPORT<br />

7) Corridor illumination shall be pendant, surface, or recessed<br />

mounted luminaires as determined.<br />

8) Photocell switching shall be utilized in areas where<br />

daylighting will be incorporated to minimize energy usage.<br />

9) Emergency exit and egress illumination shall be provided<br />

by integral battery and charger at selected locations in<br />

ceiling luminaires within all areas.<br />

10) EXIT signs will be provided with integral batteries and<br />

chargers for emergency backup. LED lamps selected for<br />

long life.<br />

11) Luminaires for exterior building illumination shall have<br />

compact fluorescent lamps with electronic ballast.<br />

Luminaires shall be wall-mounted for maintenance<br />

considerations. Lamps shall be provided with color<br />

temperature of 3500K.<br />

12) Site (walkway) luminaires shall be provided to match<br />

existing pole lighting with metal-halide lamps.<br />

e. Power Utilization Systems<br />

1) Duplex convenience outlets with isolated ground and<br />

duplex convenience outlets with ground fault interrupt<br />

(GFI) will be installed accordance with the NEC.<br />

2) Faceplates shall be stainless steel for durability.<br />

3) Single/double gang junction boxes, with future circuits will<br />

be provided as required.<br />

4) Special outlets as will be determined, shall be provided.<br />

f. Communications Systems<br />

1) Telephone and data outlets shall be provided where<br />

required.<br />

2) Approximately 300 data outlets will be required in the first<br />

floor circulation and computer areas. Majority of outlets<br />

will be located in floor slab or raised floor, and shall be<br />

recessed, covers shall be flush to floor.<br />

University of Hawaii <strong>Community</strong> <strong>College</strong>s April 2004<br />

Project No. CC-02-6188<br />

IV-23


The Learning Resource Center at <strong>Windward</strong> <strong>Community</strong> <strong>College</strong><br />

PROJECT DEVELOPMENT REPORT<br />

3) Telephone outlets to have individual 1” conduit homerun to<br />

nearest Tech Closet on each floor. Each Telephone outlet<br />

location will be provided with a 4-11/ 16” x 2-1/8” deep<br />

square junction box, double gang collar with blank cover<br />

plate. Outlets and cables shall be furnished and installed<br />

complete.<br />

4) DATA outlets shall include 1” conduit homerun to<br />

backboards within the Tech Closets. System shall include<br />

distribution frame (backboards), as required for connecting<br />

circuits including all cabling. Equipment for an operating<br />

local area network system to be furnished by others. Each<br />

DATA outlet location will be provided a 4-11/ 16” x 2-1/8”<br />

deep square junction box, double gang collar with blank<br />

cover plate. Outlets and cables shall be furnished and<br />

installed complete.<br />

5) Video outlets, if required, will have an individual 1” conduit<br />

homerun to backboards within the Tech Closets. Each<br />

video outlet location will be provided a 4-11/ 16” x 2-1/8”<br />

deep square junction box, double gang collar with blank<br />

cover plate. Outlets and cables shall be furnished and<br />

installed complete. Video distribution shall originate from<br />

the Studio Control room or as determined.<br />

g. Fire Alarm System<br />

1) An addressable type system matching or compatible to the<br />

campus central system, which is compliant to the Life<br />

Safety Code (NFPA 101) and the current Uniform Fire<br />

Code, shall be specified.<br />

2) An annunciator panel shall be provided. Location to be<br />

determined.<br />

3) Devices shall include manual pull stations, audio and<br />

visual devices per ADA criteria, supervision of sprinkler<br />

flow and tamper switches, smoke detectors and automatic<br />

duct smoke detectors.<br />

4) Interface will be provided for remote annunciation and<br />

supervision to the central campus system.<br />

University of Hawaii <strong>Community</strong> <strong>College</strong>s April 2004<br />

Project No. CC-02-6188<br />

IV-24


The Learning Resource Center at <strong>Windward</strong> <strong>Community</strong> <strong>College</strong><br />

PROJECT DEVELOPMENT REPORT<br />

h. Security System<br />

1) A system matching or compatible to the central campus<br />

system shall be specified.<br />

2) An annunciator panel will be provided. Location to be<br />

determined.<br />

3) Devices shall include magnetic door switches, infrared and<br />

ultrasonic motion detectors as determined by the Security<br />

Consultant.<br />

6. Sustainable Design (Refer to Section V)<br />

University of Hawaii <strong>Community</strong> <strong>College</strong>s April 2004<br />

Project No. CC-02-6188<br />

IV-25


The Learning Resource Center at <strong>Windward</strong> <strong>Community</strong> <strong>College</strong><br />

PROJECT DEVELOPMENT REPORT<br />

V. SUSTAINABLE DESIGN GUIDELINES<br />

A. Overview of Sustainability<br />

The pursuit of sustainable building design encompasses a comprehensive set of<br />

design and construction considerations that typically involve owner, architect and<br />

engineers, contractors, manufacturers, maintenance personnel and building<br />

occupants, etc.; i.e., the entire project team from design inception through post<br />

occupancy. The U.S. Green Building Council developed and sponsors the<br />

LEED® (Leadership in Energy and Environmental <strong>Development</strong>) Green Building<br />

Rating System® to evaluate, measure and assign credits for environmental and<br />

system performance of a facility. LEED® addresses the following environmental<br />

categories with prescriptive requirements for each category:<br />

1. Sustainable Sites<br />

2. Water Efficiency<br />

3. Energy & Atmosphere<br />

4. Material & Resources<br />

5. Indoor Environmental Quality<br />

6. Innovation & Design Process<br />

These categories and requirements are summarized in Exhibit V.1 and are<br />

intended for further evaluation for The Learning Resource Center during the<br />

course of design and the preparation of construction documents. The attached<br />

exhibit summarizes the credits that are attainable based on meeting prescriptive<br />

prerequisites and requirements for the above categories. The exhibit identifies<br />

credits that are “reasonably certain” (achievable); credits that are “possible” to<br />

achieve; and additionally, credits that are deemed “not possible” to achieve.<br />

The (33) credits indicated in the Exhibit V.1 represent an initial assessment and<br />

point of departure toward achieving LEED® Certification for The Learning<br />

Resource Center at <strong>Windward</strong> <strong>Community</strong> <strong>College</strong>. The suggested credits<br />

should be evaluated in greater depth with the design team and the University of<br />

Hawaii/<strong>Windward</strong> <strong>Community</strong> <strong>College</strong>.<br />

University of Hawaii <strong>Community</strong> <strong>College</strong>s April 2004<br />

Project No. CC-02-6188 V-1


The Learning Resource Center at <strong>Windward</strong> <strong>Community</strong> <strong>College</strong><br />

PROJECT DEVELOPMENT REPORT<br />

EXHIBIT V.1 LEED® CERTIFICATION SUMMARY<br />

Reference: LEED® Rating System,<br />

Version 2.1<br />

Reasonably<br />

Certain<br />

Possible<br />

Not Possible<br />

Points<br />

Sustainable Sites 14 Possible Points<br />

Prereq 1 Erosion & Sedimentation Control Required<br />

Credit 1 Site Selection 1 1 0 0<br />

Credit 2 Urban Redevelopment 1 0 0 1<br />

Credit 3 Brownfield Redevelopment 1 0 0 1<br />

Credit 4.1 Alternative Transportation, Public Transportation Access 1 0 0 1<br />

Credit 4.2 Alternative Transportation, Bicycle Storage & Changing Rooms 1 1 0 0<br />

Credit 4.3 Alternative Transportation, Alternative Fuel Vehicles 1 1 0 0<br />

Credit 4.4 Alternative Transportation, Parking Capacity 1 1 0 0<br />

Credit 5.1 Reduced Site Disturbance, Protect or Restore Open Space 1 0 0 1<br />

Credit 5.2 Reduced Site Disturbance, <strong>Development</strong> Footprint 1 1 0 0<br />

Credit 6.1 Stormwater Management, Rate and Quantity 1 1 0 0<br />

Credit 6.2 Stormwater Management, Treatment 1 0 0 1<br />

Credit 7.1 Heat Island Effect, Non-Roof 1 1 0 0<br />

Credit 7.2 Heat Island Effect, Roof 1 0 0 1<br />

Credit 8 Light Pollution Reduction 1 1 0 0<br />

Subtotal 8 0 6 14<br />

Water Efficiency 5 Possible Points<br />

Credit 1.1 Water Efficient Landscaping, Reduce by 50% 1 1 0 0<br />

Credit 1.2 Water Efficient Landscaping, No Potable Use or No Irrigation 1 1 0 0<br />

Credit 2 Innovative Wastewater Technologies 1 1 0 0<br />

Credit 3.1 Water Use Reduction, 20% Reduction 1 1 0 0<br />

Credit 3.2 Water Use Reduction, 30% Reduction 1 0 0 1<br />

Subtotal 4 0 1 5<br />

Energy & Atmosphere 17 Possible Points<br />

Prereq 1 Fundamental Building Systems Commissioning Required<br />

Prereq 2 Minimum Energy Performance Required<br />

Prereq 3 CFC Reduction in HVAC&R Equipment Required<br />

Credit 1 Optimize Energy Performance 1–10<br />

15% 1 0 0<br />

20% 1 0 0<br />

25% 0 0 1<br />

30% 0 0 1<br />

35% 0 0 1<br />

40% 0 0 1<br />

45% 0 0 1<br />

50% 0 0 1<br />

University of Hawaii <strong>Community</strong> <strong>College</strong>s April 2004<br />

Project No. CC-02-6188 V-2


The Learning Resource Center at <strong>Windward</strong> <strong>Community</strong> <strong>College</strong><br />

PROJECT DEVELOPMENT REPORT<br />

55% 0 0 1<br />

60% 0 0 1<br />

Credit 2.1 Renewable Energy, 5% 1 0 0 1<br />

Credit 2.2 Renewable Energy, 10% 1 0 0 1<br />

Credit 2.3 Renewable Energy, 20% 1 0 0 1<br />

Credit 3 Additional Commissioning 1 1 0 0<br />

Credit 4 Ozone Depletion 1 0 0 1<br />

Credit 5 Measurement & Verification 1 1 0 0<br />

Credit 6 Green Power 1 0 0 1<br />

Subtotal 4 0 13 17<br />

Materials & Resources 13 Possible Points<br />

Prereq 1 Storage & Collection of Recyclables Required<br />

Credit 1.1 Building Reuse, Maintain 75% of Existing Shell 1 0 0 1<br />

Credit 1.2 Building Reuse, Maintain 100% of Shell 1 0 0 1<br />

Credit 1.3 Building Reuse, Maintain 100% Shell & 50% Non-Shell 1 0 0 1<br />

Credit 2.1 Construction Waste Management, Divert 50% 1 1 0 0<br />

Credit 2.2 Construction Waste Management, Divert 75% 1 0 0 1<br />

Credit 3.1 Resource Reuse, Specify 5% 1 0 0 1<br />

Credit 3.2 Resource Reuse, Specify 10% 1 0 0 1<br />

Credit 4.1 Recycled Content, Specify 5% (p.c. + 1/2 p.i.) 1 1 0 0<br />

Credit 4.2 Recycled Content, Specify 10% (p.c. + 1/2 p.i.) 1 0 0 1<br />

Credit 5.1 Local/Regional Materials, 20% Manufactured Locally 1 0 0 1<br />

Credit 5.2 Local/Regional Materials, of 20% in MRc5.1, 50% Harvested Locally 0 0 1<br />

1 Credit 6 Rapidly Renewable Materials 1 1 0 0<br />

Credit 7 Certified Wood 1 0 0 1<br />

Subtotal 3 0 10 13<br />

Indoor Environmental Quality 15 Possible Points<br />

Prereq 1 Minimum IAQ Performance Required<br />

Prereq 2 Environmental Tobacco Smoke (ETS) Control Required<br />

Credit 1 Carbon Dioxide (CO2 ) Monitoring 1 1 0 0<br />

Credit 2 Ventilation Effectiveness 1 0 0 1<br />

Credit 3.1 Construction IAQ Management Plan, During Construction 1 1 0 0<br />

Credit 3.2 Construction IAQ Management Plan, Before Occupancy 1 1 0 0<br />

Credit 4.1 Low-Emitting Materials, Adhesives & Sealants 1 1 0 0<br />

Credit 4.2 Low-Emitting Materials, Paints 1 1 0 0<br />

Credit 4.3 Low-Emitting Materials, Carpet 1 1 0 0<br />

Credit 4.4 Low-Emitting Materials, Composite Wood 1 1 0 0<br />

Credit 5 Indoor Chemical & Pollutant Source Control 1 1 0 0<br />

Credit 6.1 Controllability of Systems, Perimeter 1 0 0 1<br />

Credit 6.2 Controllability of Systems, Non-Perimeter 1 0 0 1<br />

Credit 7.1 Thermal Comfort, Comply with ASHRAE 55-1992 1 1 0 0<br />

Credit 7.2 Thermal Comfort, Permanent Monitoring System 1 1 0 0<br />

Credit 8.1 Daylight & Views, Daylight 75% of Spaces 1 0 0 1<br />

Credit 8.2 Daylight & Views, Views for 90% of Spaces 1 0 0 1<br />

University of Hawaii <strong>Community</strong> <strong>College</strong>s April 2004<br />

Project No. CC-02-6188 V-3


The Learning Resource Center at <strong>Windward</strong> <strong>Community</strong> <strong>College</strong><br />

PROJECT DEVELOPMENT REPORT<br />

Subtotal 10 0 5 15<br />

Innovation & Design Process 5 Possible Points<br />

Credit 1.1 Innovation in Design 1 1 0 0<br />

Credit 1.2 Innovation in Design 1 1 0 0<br />

Credit 1.3 Innovation in Design 1 1 0 0<br />

Credit 1.4 Innovation in Design 1 0 0 1<br />

Credit 2 LEED® Accredited Professional 1 1 0 0<br />

Subtotal 4 0 1 5<br />

LEED® Certification for WCC Learning Resource Center 33<br />

LEED® Possible Additional Credits 0<br />

LEED® Not Possible 36<br />

LEED® Rating System Total Available Credits 69<br />

University of Hawaii <strong>Community</strong> <strong>College</strong>s April 2004<br />

Project No. CC-02-6188 V-4


The Learning Resource Center at <strong>Windward</strong> <strong>Community</strong> <strong>College</strong><br />

PROJECT DEVELOPMENT REPORT<br />

VI.<br />

IMPLEMENTATION AND PROBABLE COST OF CONSTRUCTION<br />

The proposed implementation plan and the probable cost of construction for The<br />

Learning Resource Center comprises three (3) components, i.e., The Learning Resource<br />

Center, Banyan Drive (Loop Road) Improvements and the Hazardous Pipe Removal and<br />

Remediation. The following timeframe represents the projected design and construction<br />

schedule and assumes that these components will be implemented in parallel.<br />

A. Projected Schedule for Planning Purposes<br />

1. Design Phase 10 – 14 months<br />

(Schematic Completion)<br />

(Design <strong>Development</strong>)<br />

(Construction Documents)<br />

2. Building Permit Allow 3 – 4 months<br />

3. Bid Period/Negotiations/Award 3 – 4 months<br />

4. Construction Phase + Fit Out 20 – 24 months<br />

5. Close Out Allow 3 – 4 months<br />

B. The Statement of Probable Construction Cost is conceptually summarized in<br />

Exhibit VI.1 for The Learning Resource Center and related work and assumes a<br />

5 percent escalation beginning January 2005.<br />

EXHIBIT VI.1: STATEMENT OF PROBABLE CONSTRUCTION COST<br />

THE LEARNING RESOURCE CENTER<br />

1 Site Costs<br />

Parking Spaces<br />

(80) <strong>Library</strong> and Learning Center parking spaces @ $2800 $224,000<br />

(18) Ilima Way relocated parking spaces @ $2800 $50,400<br />

Utilities, utility relocation, site lighting $325,000<br />

Landscaping, walks & plazas $450,000<br />

Retaining walls $100,000<br />

Amphitheater $200,000<br />

Service and Fire Drives $300,000<br />

Demolition of Hale Manaleo $125,000<br />

Subtotal $1,774,400<br />

2 Building Construction Cost $24,528,935<br />

81,793 GSF & 2000 GSF of canopy overhang @ $300 / GSF<br />

3 Furniture and Equipment $2,452,894<br />

10% of Item 2<br />

4 Computers / Technology $1,839,670<br />

7.5% of Item 2<br />

University of Hawaii <strong>Community</strong> <strong>College</strong>s April 2004<br />

Project No. CC-02-6188<br />

VI-1


The Learning Resource Center at <strong>Windward</strong> <strong>Community</strong> <strong>College</strong><br />

PROJECT DEVELOPMENT REPORT<br />

5 Construction Contingency $2,630,334<br />

10% of Items 1 & 2<br />

Subtotal Project Cost $33,226,232<br />

6 A / E Fees (Assume 10% of Project Cost) $3,322,623<br />

Total Project Cost $36,548,855<br />

BANYAN DRIVE - LOOP ROAD DESIGN & CONSTRUCTION<br />

1 Site Costs<br />

Roadway $180,000<br />

Fill Material $100,000<br />

Retaining Wall $100,000<br />

Utility Pole Relocation & Related Work $150,000<br />

Fence Relocation $20,000<br />

Subtotal $550,000<br />

2 Construction Contingency $55,000<br />

10% of Item 1<br />

3 A / E Fees (Assume 10% of 1+2) $60,500<br />

Subtotal Project Cost $665,500<br />

HAZARDOUS PIPE REMOVAL AND REMEDIATION<br />

1 Scope Not Determine (Allowance) $150,000<br />

2 Construction Contingency $15,000<br />

10% of Item 1.<br />

3 A / E Fees (Assume 10% of 1+2) $16,500<br />

Subtotal Project Cost $181,500<br />

SUSTAINABLE DESIGN STRATEGIES (LEED)®<br />

1 Additional Costs (Assume 6% of LRC Cost) $1,461,954<br />

2 Construction Contingency $146,195<br />

10% of Item 1.<br />

3 A/E Fee (Assume 10% of Items 1+2) $160,815<br />

Subtotal Project Cost $1,768,965<br />

Grand Total $39,164,820<br />

Notes:<br />

1. The Grand Total cost is in current dollars. Escalation to the midpoint of<br />

the future construction is required. Escalation is "assumed" @ 5% per year.<br />

University of Hawaii <strong>Community</strong> <strong>College</strong>s April 2004<br />

Project No. CC-02-6188<br />

VI-2


The Learning Resource Center at <strong>Windward</strong> <strong>Community</strong> <strong>College</strong><br />

PROJECT DEVELOPMENT REPORT<br />

ESCALATION<br />

Grand Total escalated to January of 2005 @ 5% $41,123,061<br />

Grand Total escalated to January of 2006 @ 5% $43,179,214<br />

Grand Total escalated to January of 2007 @ 5% $45,338,175<br />

Grand Total escalated to January of 2008 @ 5% $47,605,083<br />

Grand Total escalated to January of 2009 @ 5% $49,985,338<br />

Grand Total escalated to January of 2010 @ 5% $52,484,604<br />

Grand Total escalated to January of 2011 @ 5% $55,108,835<br />

University of Hawaii <strong>Community</strong> <strong>College</strong>s April 2004<br />

Project No. CC-02-6188<br />

VI-3


The Learning Resource Center at <strong>Windward</strong> <strong>Community</strong> <strong>College</strong><br />

PROJECT DEVELOPMENT REPORT<br />

VII.<br />

REFERENCES<br />

1. City and County of Honolulu, Resolution No. 94-87, CD-I, May 4, 1994<br />

2. Joint Venture/Okita Kunimitsu & Associates, Inc./Ernest Hara and Associates,<br />

Inc., <strong>Windward</strong> <strong>Community</strong> <strong>College</strong> Master Plan Report, April 22, 1989.<br />

3. Okita Kunimitsu & Associates, Inc., Plan Review Use for a Five Year Master Plan<br />

for the University of Hawaii <strong>Windward</strong> <strong>Community</strong> <strong>College</strong>, Volumes 1 & 2, May<br />

1992<br />

4. Okita Kunimitsu & Associates, Inc., <strong>Windward</strong> <strong>Community</strong> <strong>College</strong> Urban Design<br />

Plan and Design Guidelines, July 15, 1994, Revised November 30, 1995.<br />

5. Wilson Okamoto & Associates, Inc., Environmental Assessment for <strong>Windward</strong><br />

<strong>Community</strong> <strong>College</strong> Master Plan, October 28, 1987.<br />

6. City and County of Honolulu, Dept. of Planning & Permitting, Land Use<br />

Ordinance, April 1995.<br />

7. 1997 Uniform Building Code<br />

8. Drawings<br />

Description Job Number Date Project<br />

Water lines<br />

Accessible ramps,<br />

Minor storm drains<br />

at Hale Manaleo<br />

Site Utilities<br />

Storm sewer<br />

DAGS<br />

CC-00-6152<br />

DAGS<br />

12-31-4135<br />

DAGS<br />

12-31-6180<br />

01-18-02 WCC – Connect Existing<br />

buildings to new main campus<br />

water distribution system<br />

3-4-02 Architectural Barrier<br />

Removal<br />

2-7-04 Building K<br />

Natural Sciences C-13<br />

Site Utilities DAGS 12-31-<br />

4100<br />

Utility Plan DAGS 12-31-<br />

4056<br />

April 2001<br />

April 2000<br />

Fire Safety Improvements<br />

E-1, E-2, E-3, E-4<br />

Building D<br />

Campus Center C-5, C-6<br />

Exterior<br />

Elevations<br />

Storm Drains,<br />

Lines and Roads<br />

12-31-4027 9-15-98 Building J<br />

12-31-4002 4-22-96 New Campus <strong>Development</strong>,<br />

Phase I<br />

University of Hawaii <strong>Community</strong> <strong>College</strong>s April 2004<br />

Project No. CC-02-6188<br />

VII-1


The Learning Resource Center at <strong>Windward</strong> <strong>Community</strong> <strong>College</strong><br />

PROJECT DEVELOPMENT REPORT<br />

9. Federal Register<br />

Architectural and Transportation Barriers Compliance Board<br />

36 CFR Parts 1190 and 1191<br />

Americans with Disabilities Act (ADA)<br />

Accessibility Guidelines for Buildings and Facilities;<br />

Architectural Barriers Act (ABA) Accessibility Guidelines for Proposed Rule.<br />

10. LEED® Reference Guide and Rating System Version 2.0, June 2001<br />

University of Hawaii <strong>Community</strong> <strong>College</strong>s April 2004<br />

Project No. CC-02-6188<br />

VII-2


PROJECT DEVELOPMENT REPORT<br />

VOLUME I: PLANNING & CONCEPT DEVELOPMENT<br />

APPENDIX A<br />

PLAN REVIEW USE (PRU) ASSESSMENT AND CITY<br />

AND COUNTY OF HONOLULU REVIEW COMMENTS<br />

PROJECT NO. CC-02-6188<br />

APRIL 2004<br />

1357 KAPIOLANI BOULEVARD<br />

HONOLULU, HAWAII 96814


<strong>Windward</strong> <strong>Community</strong> <strong>College</strong><br />

Hale Manaleo


<strong>Windward</strong> <strong>Community</strong> <strong>College</strong><br />

Hale Manaleo


The Learning Resource Center at <strong>Windward</strong> <strong>Community</strong> <strong>College</strong><br />

PROGRAM PLANNING<br />

SUMMARY OF FUNCTIONS - ASSIGNABLE SQUARE FOOTAGE<br />

Function<br />

Number Function Description Units<br />

Student<br />

Stations<br />

Fac/Staff<br />

Stations<br />

Pre-Final<br />

I. Administration<br />

1 Director of Information Technology Services<br />

Office 1 1 200<br />

2 Institutional Researcher Office 1 1 200<br />

3 Secretary Office 1 2 175<br />

4 Administrative Storage Room 1 0<br />

5 Conference Room 1 600<br />

5a Male Restroom 1 50<br />

5b Female Restroom 1 50<br />

Subtotal 0 4 1,275<br />

II. <strong>Library</strong><br />

6 Vestibule 1 800<br />

7 Information Commons 1 48 2,700<br />

8 Information Commons Manager's Office 1 1 150<br />

9 Information Reference Desk Area 1 4 425<br />

10 Reference Collection Area 1 16 1,100<br />

11 Reference Librarian's Office (4 @ 115) 4 4 460<br />

12 Reference Librarians Conference Room 1 340<br />

13 Circulation Service Center 1 4 1,125<br />

14 Circulation Workroom 1 3 735<br />

15 Circulation Manager's Office 1 1 145<br />

16 Circulation Storage Room 1 200<br />

17 Current Periodicals Area 1 20 700<br />

18 Periodicals Backfile Area 1 12 700<br />

19 Microforms Area 1 5 550<br />

20 Pamphlets Area 1 4 155<br />

21 Maps/Art Prints Area 1 4 600<br />

22 Listening/Viewing Area 1 8 480<br />

23 Study Area A 1 22 1,000<br />

24 Hawaiian Collection Room 1 24 1 1,800<br />

25 Bookstacks Area 1 5,500<br />

26 Study Area B (shared w/ Learning Center) inc.<br />

6 study booths 1 110 4,100<br />

27 Group Viewing Room (1 @ 300 & 2 @ 170) 3 640<br />

28 Group Study Room (6 @ 150 & 2 @170) Area<br />

B 9 1,240<br />

29 Technical Services Room 1 4 1,130<br />

30 Technical Services Librarian's Office (Tech I) 1 1 140<br />

31 <strong>Library</strong> Technician's Office (Tech II) 1 1 130<br />

32 <strong>College</strong> Archives Room 1 600<br />

32a Circulation Storage Room 1 135<br />

33 Head Librarian's Office 1 1 240<br />

34 Secretary Office 1 1 195<br />

University of Hawaii <strong>Community</strong> <strong>College</strong>s December 2003<br />

Project No. CC-02-6188 1 PRE-FINAL


The Learning Resource Center at <strong>Windward</strong> <strong>Community</strong> <strong>College</strong><br />

PROGRAM PLANNING<br />

SUMMARY OF FUNCTIONS - ASSIGNABLE SQUARE FOOTAGE<br />

Function<br />

Number Function Description Units<br />

Student<br />

Stations<br />

Fac/Staff<br />

Stations<br />

Pre-Final<br />

35 Storage Room 1 200<br />

36 Staff Emergency Room and Lounge 1 800<br />

37 Meeting Room with 2 Closets @ 100 1 1,220<br />

38 Electronic Classroom 1 24 1 875<br />

39 Computer Laboratory 1 72 4 3,670<br />

39a 24-hour Study/Coffee Shop 1 30 1,500<br />

Subtotal 399 31 36,480<br />

III. The Learning Center (TLC)<br />

40 TLC Coordinator's Office 1 1 150<br />

41 TLC Manager 1 1 120<br />

42 Distribution Center 1 2 330<br />

43 Work Room 1 2 385<br />

44 Testing Room 1 25 810<br />

45 Quiet Study Area (Merged with Study Area ‘B’ -<br />

<strong>Library</strong> 1 0 5 0<br />

46 Resource Teacher Room 2 2 220<br />

47 STAAR Reception Area 1 2 180<br />

48 STAAR Counselor's Office 3 3 330<br />

49 STAAR Clerk-Typist Office 1 1 100<br />

50 STAAR Tutors' Office 1 2 235<br />

Subtotal 27 19 2,860<br />

IV. Computing Services<br />

51 Computing Services Coordinator's Office 1 1 215<br />

52 Computing Services Secretary Office 1 2 205<br />

53 Help Desk Room 1 2 285<br />

54 Training and Demonstration Room 1 2 440<br />

55 Staff Workroom 1 6 985<br />

56 Computer Setup and Repair Room 1 4 800<br />

57 Server Area 1 0 355<br />

58 Storage Room 1 200<br />

58a Bathroom 50<br />

Subtotal 0 17 3,535<br />

V. Instructional Media Services<br />

59 Reception Area/Counter/Equipment Check-out 1 3 210<br />

60 General Office, Job and Equipment Intake<br />

Room 1 6 450<br />

61 Clerk-Typist's Office 1 1 125<br />

62 Media Coordinator’s Office 1 1 200<br />

63 Storage Room 1 0 190<br />

64 Duplication and Copiers Room 1 1 610<br />

65 Duplication Storage Room 1 0 160<br />

66 Bindery Room 1 3 300<br />

University of Hawaii <strong>Community</strong> <strong>College</strong>s December 2003<br />

Project No. CC-02-6188 2 PRE-FINAL


The Learning Resource Center at <strong>Windward</strong> <strong>Community</strong> <strong>College</strong><br />

PROGRAM PLANNING<br />

SUMMARY OF FUNCTIONS - ASSIGNABLE SQUARE FOOTAGE<br />

Function<br />

Number Function Description Units<br />

Student<br />

Stations<br />

Fac/Staff<br />

Stations<br />

Pre-Final<br />

67 Duplication Manager's Office 1 1 140<br />

68 New Media Laboratory 1 20 1 620<br />

69 Instructional <strong>Development</strong> Specialist’s Office 1 1 110<br />

70 Media Production Specialist's Office 1 1 120<br />

71 Web Master's Office 1 1 125<br />

72 Studio Storage Room 1 0 110<br />

73 Instructional Video Studio 1 5 715<br />

74 Electronic Duplication and Distribution Room 1 3 450<br />

75 Studio Control Room 1 6 210<br />

76 Audio Recording Booth 1 2 125<br />

77 Electronic Maintenance and Repair Shop 1 3 745<br />

78 Electronic Technician I Office 1 1 145<br />

79 Electronic Technician II Office 1 1 145<br />

80 Equipment Storage Room 1 1 215<br />

81 Graphic Materials Preparation Room 1 4 4 850<br />

82 Graphic Artist’s Office 1 1 160<br />

83 Graphics Storage Room 1 0 115<br />

84 Spray Booth 0 70<br />

85 Loading and Receiving/Storage Room 0 900<br />

85a Bathroom 1 0 50<br />

Subtotal 29 42 8.365<br />

Subtotal (Assignable Square Feet) 455 113 52,515<br />

VI. Non-Assignable Square Feet/Building Support<br />

86. Atrium 1 3,500<br />

87. Delivery Area/Receiving (Merged with #85) 1<br />

88. Cart Parking Area 1 485<br />

89. Trash Area 1 250<br />

90. Wiring/Telecommunications Room (1 @ 1 440<br />

400)<br />

91. Wiring/Telecommunications Subroom (1 @ 4 415<br />

85, 1 @ 95, 1 @ 100, 1 @ 135)<br />

92. Janitorial Rooms (1 @ 45, 1 @ 60, 1 @ 65, 4 240<br />

1 @ 70)<br />

93. Central Housekeeping 1 160<br />

94. Central Mechanical Room 1 3,090<br />

95. Central Electrical Room 1 350<br />

96. Electrical Floor Closets (4 @ 60) 4 240<br />

97. Public Toilets (2 @ 280, 2 @ 285) 4 1,130<br />

98. Student Lockers/Bag Nitches (20 ½ length<br />

lockers)<br />

40 200<br />

University of Hawaii <strong>Community</strong> <strong>College</strong>s December 2003<br />

Project No. CC-02-6188 3 PRE-FINAL


The Learning Resource Center at <strong>Windward</strong> <strong>Community</strong> <strong>College</strong><br />

PROGRAM PLANNING<br />

SUMMARY OF FUNCTIONS - ASSIGNABLE SQUARE FOOTAGE<br />

Function<br />

Number Function Description Units<br />

Student<br />

Stations<br />

Fac/Staff<br />

Stations<br />

Pre-Final<br />

Subtotal (Non-Assignable Square Feet)<br />

10,500<br />

(VI)<br />

Subtotal Assignable Square<br />

52,515<br />

Feet (I-V)<br />

Subtotal (I-VI) 63,015<br />

VII. Horizontal & Vertical Circulation, Wall<br />

Thickness; Duct Shafts & Overhangs (+29.8%)<br />

18,778<br />

TOTAL GROSS SQUARE FEET 81,793<br />

GSF<br />

University of Hawaii <strong>Community</strong> <strong>College</strong>s December 2003<br />

Project No. CC-02-6188 4 PRE-FINAL


PROJECT DEVELOPMENT REPORT<br />

VOLUME I: PLANNING & CONCEPT DEVELOPMENT<br />

APPENDIX B<br />

INTERACTIVE WORKSHOP NOTES AND DOCUMENTS<br />

PROJECT NO. CC-02-6188<br />

APRIL 2004<br />

1357 KAPIOLANI BOULEVARD<br />

HONOLULU, HAWAII 96814


University of Hawaii <strong>Community</strong> <strong>College</strong>s<br />

Plan <strong>Development</strong> Report for<br />

The Learning Resource Center<br />

At <strong>Windward</strong> <strong>Community</strong> <strong>College</strong><br />

Subject: Roundtable #1 (Interactive Workshop) – Facility Programming<br />

Location: <strong>Windward</strong> <strong>Community</strong> <strong>College</strong><br />

Date: July 29, 2003<br />

Participants: See Attached Sign-up Sheet<br />

WORKSHOP NOTES:<br />

1. Summary of New Learning Resource Center by T. Findley<br />

• The Learning Resource Center is intended for social interaction<br />

• WCC confirmed that the users of the <strong>Library</strong> need a “physical” document<br />

to “hold” vs. reading everything electronically<br />

• House books and reference material and plan for expansion<br />

• Integrate computer-based data system<br />

• Provide “raised floor” system, or similar system for functional flexibility;<br />

the Learning Resource Center (<strong>Library</strong>) needs “pathways” for<br />

power, communication and/or data.<br />

• UH/WCC to confirm the budget for the facility.<br />

• Need a topographic survey to site the facility.<br />

2. Significance of the Learning Resource Center<br />

• WCC envisions the Learning Resource Center/<strong>Library</strong> as the Intellectual<br />

Center, and the Technology Center of campus<br />

• Visual identity and presence is important; architectural prominence; a<br />

memorable “sense of place”<br />

• A place for “gathering” and “socializing”<br />

• Impart a friendly and inviting atmosphere<br />

• Need to encourage “group” work; collaboration<br />

• Provide different venues for grouping, i.e., breakout niches, booths, other<br />

interactive spaces, etc.<br />

• Quiet areas for study; high energy areas for collaboration and group<br />

interaction<br />

3. Facility Program<br />

• WCC confirmed that the facility program is for current and future needs<br />

and should be viewed as “realistic” rather than “ideal”<br />

• UH/State will independently review the staffing requirements associated<br />

with the facility program<br />

1


<strong>Library</strong> Program<br />

• N. Heu confirmed that a security system is required for the Hawaiian<br />

Collection Room; need a service/check out counter<br />

Learning Center Functions (Glynnis Kinoshita)<br />

• Handwritten Testing<br />

• Placement Testing<br />

• Distant Educations (from other campuses)<br />

• General Study<br />

• Computer Center for Testing<br />

• Occasional Workshops<br />

• Computer Lab<br />

• Video Tapes for Language Arts (Math faculty not part of this facility)<br />

Computer Center (Michael Tom)<br />

• May need a “shared” computer facility since WCC has experienced<br />

difficulty with the upkeep and/or replacement of computers, i.e., a<br />

“shared” facility would reduce the total number of computers<br />

Staff Offices<br />

• Comment: “built-in furniture is not working”<br />

Instructional Media/Media Center (Elizabeth Ratliff)<br />

• Need “walk-up” counter for “drop-off” service<br />

• Shares staff with Duplication Room (usually students)<br />

• Audio Recording Room<br />

• Studio with Audio Booth<br />

• Multi-media<br />

• Uses specialized, high-end equipment<br />

Audio-Visual (Mike Bowles)<br />

• Computer area needs a “self-help” counter<br />

• A-V staff “troubleshoots” and assists the entire campus<br />

• Close-off computer room<br />

• Need a work area in the delivery dock for a compressor<br />

Site Meeting with the Outdoor Circle<br />

• Confirmed that the banyans are not listed as “exceptional trees,” but<br />

should be preserved; the example at the Campus Center is “acceptable”<br />

with the proper set backs for the retaining wall<br />

2


• Confirmed that the Hong Kong Orchid trees were “old,” however, the<br />

Outdoor Circle did not make any commitments with respect to removal, or<br />

relocation; similarly for the monkey pod<br />

• The Outdoor Circle recommended that we provide proposed plans prior to<br />

any proposed removal or relocation of trees.<br />

3


University of Hawaii <strong>Community</strong> <strong>College</strong>s<br />

Plan <strong>Development</strong> Report for<br />

The Learning Resource Center<br />

At <strong>Windward</strong> <strong>Community</strong> <strong>College</strong><br />

Subject: Roundtable #1 (Interactive Workshop) – Facility Programming<br />

Location: <strong>Windward</strong> <strong>Community</strong> <strong>College</strong><br />

Date: July 30, 2003<br />

Participants: See Attached Sign-up Sheet<br />

WORKSHOP NOTES:<br />

1. Existing Learning Center – Current Functions<br />

• Make-up Testing by subject (non-scheduled; at random)<br />

• Placement testing (Upward Bound)<br />

• Distant Education (some are non-students)<br />

• Quiet Area (as part of larger area) for overflow testing<br />

• Testing area: 25-30 seats for written testing (not computer)<br />

• Lab monitors typically observe testing<br />

• Tutoring: 1-5 concurrent sessions<br />

2. Construction Costs<br />

• UH/WCC directive: LAD to focus on cost of building only and “disregard”<br />

costs for the roadway, parking, infrastructure, renovation of existing<br />

building, etc. UH/WCC will further assess other costs that may be<br />

associated with the facility<br />

3. Other Costs<br />

• WCC anticipates need to relocate classrooms from Hale Manaleo to Hale<br />

No’eau or Hale La’akea. May need to account for these other costs<br />

associated with the development of the Learning Resource Center, if this<br />

is a negotiated point with State Historic Preservation.<br />

4. Facility Program Evaluation<br />

• See attached Block Diagrams<br />

5. Site Assessment<br />

• Participants evaluated the site at Hale Manaleo (north) and also another<br />

site at the south end of the “open space/quad”<br />

• Participants selected the site at the north end for the following reasons:<br />

- The north site is the designated location of the Learning<br />

Resource Center in the Plan Review Use Application and<br />

the Master Plan<br />

1


- The site at the south end “infringes” on the established<br />

open space and may require modification and re-approval<br />

of the PRU by the City<br />

- This location is closest to the existing and future<br />

classrooms<br />

- In proximity to the major parking areas<br />

- Has the potential to “synergize” the north end of the<br />

campus with the Theatre and Science facilities.<br />

2


University of Hawaii <strong>Community</strong> <strong>College</strong>s<br />

Plan <strong>Development</strong> Report for<br />

The Learning Resource Center<br />

At <strong>Windward</strong> <strong>Community</strong> <strong>College</strong><br />

Subject: Roundtable #2 (Interactive Workshop)<br />

Location: <strong>Windward</strong> <strong>Community</strong> <strong>College</strong> – Hale Akoakoa Rooms 107-109<br />

Date: October 22, 2003, 1:30 PM – 4:30 PM<br />

Participants: See Attached Sign-up Sheet<br />

WORKSHOP NOTES:<br />

1. Core Group Discussion: First Level Floor Plan<br />

• Locate Reference <strong>Library</strong> on outside wall<br />

• Add more seating around Reference Desk<br />

• Tech Services requested a location with exterior wall/daylight<br />

• Combine Computer Services Set-up Room, CS Staff Workroom and CS<br />

Storage; provide entry at each end with direct entry into Data Closet<br />

2. Core Group Discussion: Second Level Floor Plan<br />

• Discussed location of Listening & Viewing at the south end (outside wall<br />

location)<br />

• Instructional Media Service: flip Receptionist Desk to other side of entry<br />

next to Work Room and Copy Room<br />

• Instructional Media Service: locate Control Room adjacent to both<br />

Instructional Video Studio and Audio Recording Studio<br />

• Instructional Media Service: provide double doors for Electric<br />

Maintenance & Repair<br />

• Instructional Media Service: provide door from IDS to Media Lab<br />

• Relocate Hawaiian Room (Second Level) closer to Reference <strong>Library</strong> (on<br />

the First Level)<br />

• Show Service Entry on the Second Level Floor Plan (adjacent to Loading<br />

& Receiving)<br />

• Electronic Classroom location is good, i.e., accessible by IMS and TLC on<br />

the Second Level<br />

3. Engineering - Mechanical<br />

• Confirmed concept for HVAC system with Beall & Associates: a central<br />

plant with chillers; high ceiling; provision of four (4) air handling<br />

equipment/fan rooms.<br />

• Rule of thumb: (1) fan room per 9,000 – 10,000 square feet<br />

• 10,000 sf requires about 25 sf of ductwork<br />

• Prefer water-cooled central plant for chilled water system<br />

• Heat pump system – does not have chilled water piping; the air handling<br />

units would be the heat pump<br />

1


• Use a separate ducted system for outside air<br />

• Need a cooling tower outside<br />

• Discussed raised floor concept with under floor ducting for HVAC: the<br />

entire floor is a plenum – considered more experimental<br />

• Discouraged the use of skylights that produce direct radiation and<br />

increased heat gain<br />

• Discussed need for locating a transformer pad to bring in primary power<br />

2


University of Hawaii <strong>Community</strong> <strong>College</strong>s<br />

Plan <strong>Development</strong> Report for<br />

The Learning Resource Center<br />

At <strong>Windward</strong> <strong>Community</strong> <strong>College</strong><br />

Subject: Roundtable #2 (Interactive Workshop)<br />

Location: <strong>Windward</strong> <strong>Community</strong> <strong>College</strong> – Hale Akoakoa Rooms 107-109<br />

Date: October 23, 2003, 9:00 AM – 4:30 PM<br />

Participants: See Attached Sign-up Sheet<br />

WORKSHOP NOTES:<br />

1. Meeting #1: Computer Services Group (Dave Maxson)<br />

• Provide air conditioning for Server Room<br />

• Raised floor system is acceptable although prefers concrete floor for<br />

static free area<br />

2. Meeting #2: Instructional Media Services (Elizabeth Ratliff)<br />

• Don’t need a wall between the Copy Room and Work Room<br />

• Provide public access to New Media Lab, Instructional Video Lab and<br />

Audio Lab<br />

• Provide compressed air at Service Area<br />

• Provide secured area for two (2) gas-powered service carts<br />

• Related elements near Service Area: trash (dumpster); cooling tower;<br />

transformer<br />

3. Meeting #3: <strong>Library</strong> (Nancy Heu)<br />

• Confirmed provision of windows for Tech Services; relocate group to<br />

Ground Level southeast corner<br />

• Include office spaces for Head Librarian, Reference Librarians, Secretary<br />

and Conference Room<br />

• Fill-in area over Coffee Shop for 60,000 sf Collections<br />

• Move electronic Classroom closer to center of floor plan<br />

3. Commentary Meeting Input<br />

• Discussion regarding large meeting room<br />

• School newspaper requested jpeg image of color rendering<br />

(libby@hawaii.edu)<br />

1


4. Exit Meeting Summary<br />

Confirmed the following with UH CC (Maynard Young):<br />

• Pursue LEED Silver Certification for WCC Learning Resource Center<br />

• Include costs associated with LEED Certification<br />

• Design team may need to include a “sustainability” consultant for the<br />

LEED requirements<br />

• Include the following work in the project cost estimate: 1) Loop Road<br />

improvements at the north end of campus, i.e., clearing, retaining walls,<br />

paving/widening, street lighting, etc. 2) the plaza/amphitheater at the<br />

north end of the site; 3) the proposed parking area at the northeast end of<br />

campus has some old asbestos pipes; include cost of removal and<br />

disposal<br />

• As a reference the earliest availability for design funds is June 2005; the<br />

earliest UH can begin construction is June 2006<br />

• Provide cost estimate for base year June 2004 and assume a 4%<br />

escalation.<br />

Other Comments:<br />

• Science professor likes the amphitheater for viewing of the night-time<br />

activities associated with the Planetarium; project should ensure<br />

minimizing “light pollution” from the <strong>Library</strong>/Learning Resource Center<br />

onto the Planetarium<br />

2


University of Hawaii <strong>Community</strong> <strong>College</strong>s<br />

Plan <strong>Development</strong> Report for<br />

The Learning Resource Center<br />

At <strong>Windward</strong> <strong>Community</strong> <strong>College</strong><br />

Subject: Roundtable #3 (Interactive Workshop)<br />

Location: <strong>Windward</strong> <strong>Community</strong> <strong>College</strong> – Hale Akoakoa Rooms 107-109<br />

Date: November 19, 2003, 1:30 PM – 4:30 PM<br />

Participants: See Attached Sign-up Sheet<br />

WORKSHOP NOTES:<br />

1. Overview<br />

• LAD presented a PowerPoint overview of the revised concept plans<br />

• Presentation included Site Plan, Floor Plans, Site/Building Sections,<br />

Exterior Building Elevations and an Aerial Perspective<br />

• Incorporated input from Roundtable #2<br />

• Latest concept includes a 3 rd Floor for mechanical rooms, staff lounge<br />

and Director’s Office<br />

• Tech Services located on southeast corner of First Level<br />

• Hawaiian Room located adjacent to Circ Desk at First Level<br />

• Consolidated Group Study Rooms eastside of Second Level<br />

• TLC located on northeast quadrant of Second Level<br />

• Electronic Classroom centrally located on Second Level along major entry<br />

way<br />

TLC Comments:<br />

• Add door to patio from Staff Room (Third Level Floor Plan)<br />

• Flip Coordinator’s and Manager’s Offices<br />

IMS Comments:<br />

• Add back doors into New Media Lab and Electronic Classroom<br />

• Flip-flop location of Graphics, etc. with General Office, Intake, Media<br />

Coordinator, Clerk and Reception Desk<br />

• Incorporate vestibules at each entry, i.e, air locks<br />

2. Tomorrow’s (11/20/03) Meeting Schedule<br />

• 9:00 – 9:45 Computer Services<br />

• 9:45 – 10:30 <strong>Library</strong><br />

• 10:30 – 11:15 IMS<br />

• 11:15 – 12:00 Open<br />

• 1:00 - 1:45 TLC<br />

• 2:00 Core Group Exit Meeting<br />

1


University of Hawaii <strong>Community</strong> <strong>College</strong>s<br />

Plan <strong>Development</strong> Report for<br />

The Learning Resource Center<br />

At <strong>Windward</strong> <strong>Community</strong> <strong>College</strong><br />

Subject: Roundtable #3 (Interactive Workshop)<br />

Location: <strong>Windward</strong> <strong>Community</strong> <strong>College</strong> – Hale Akoakoa Room 201<br />

Date: November 20, 2003, 9:30 AM – 4:30 PM<br />

Participants: See Attached Sign-up Sheet<br />

WORKSHOP NOTES:<br />

1. 9:00 – 9:45 Computer Services Group (Dave Maxson, Brian Tokuda)<br />

• Combine Computer Set-up & Repair/Staff Room/Storage Room all into<br />

one room<br />

• Move Sec Room to C.S. Coordinator location and move C.S. Coordinator<br />

to Storage location; provide niche/access in the back of the Help Desk,<br />

i.e., at the former Sec Room location<br />

2. 9:45 – 10:30 <strong>Library</strong> Staff (Nancy Heu, Tara Severns)<br />

• Rotate four (4) functions at the Reference area, i.e., New Periodicals,<br />

Back File Periodicals, Listen/View and Reference Collection.<br />

• The solid north-south wall feature could incorporate see-through displays,<br />

windows or petroglyphs<br />

• Some discussion about State of Hawaii provision for artwork that is<br />

equivalent to 1% of the construction budget<br />

3. 10:30 – 11:15 Instructional Media Service (Elizabeth Ratliff, Michael<br />

Bowles)<br />

• Second Level layout is OK<br />

• Requested a sink in the Electronic Repair Shop<br />

3. 1:00 – 1:45 TLC (Aileen Yim, Jerry Levinson)<br />

• Discussion regarding testing room<br />

• Preliminary confirmation for (15) computers and (2) test seats<br />

4. 2:00 Exit Meeting<br />

• Comment made to revise plans to indicate “deeper” stairwells to include<br />

refuge area and out-swing doors<br />

• LAD to verify number of toilets and fixture count; add toilet (unisex) at<br />

southwest quadrant on First Level<br />

• Delete cooling tower designation at the Service Area and address remote<br />

location in the PDR narrative<br />

1


• Discuss raised floor system and locations in the narrative<br />

• Re-evaluate/relocate public elevator for better access by Circ Staff and<br />

acoustics (machine room noise)<br />

• Include following in cost estimate: 1) base building; 2) north end -<br />

perimeter road; 3) asbestos pipe clean-up; 4) LEED Certification<br />

(sustainable design); 4) demolition of Hale Manaleo<br />

• UH CC (M. Young) confirmed NOT to include any costs associated with<br />

Hale Noe’au or Hale La’akea<br />

• UH CC requested documentation of any meetings with State Historic<br />

Preservation regarding demolition of Hale Manaleo<br />

• UH CC indicated need for EA for this project and requested a fee<br />

proposal (LAD indicated that a preliminary meeting with OEQC confirmed<br />

that an EA is NOT required for the Learning Resource Center)<br />

• LAD anticipates DRAFT of Project <strong>Development</strong> Report on, or about<br />

December 15, 2003<br />

2


PROJECT DEVELOPMENT REPORT<br />

VOLUME I: PLANNING & CONCEPT DEVELOPMENT<br />

APPENDIX C<br />

MEETING NOTES<br />

PROJECT NO. CC-02-6188<br />

APRIL 2004<br />

1357 KAPIOLANI BOULEVARD<br />

HONOLULU, HAWAII 96814


M E M O R A N D U M<br />

PLANNING<br />

ARCHITECTURE<br />

ENGINEERING<br />

INTERIORS<br />

DATE<br />

TO<br />

FROM<br />

September 24, 2003<br />

Project File<br />

Sam Ustare<br />

PROJECT NO.<br />

810802-00<br />

EST. 1915<br />

ATLANTA<br />

AUSTIN<br />

BERLIN<br />

DALLAS<br />

HONG KONG<br />

HONOLULU<br />

HOUSTON<br />

LAS VEGAS<br />

LOS ANGELES<br />

MADRID<br />

OMAHA<br />

ORLANDO<br />

PHOENIX<br />

SAN ANTONIO<br />

WASHINGTON, DC<br />

PROJECT<br />

SUBJECT<br />

<strong>Windward</strong> <strong>Community</strong> <strong>College</strong><br />

Learning Resource Center<br />

Sewer System - Confirmation<br />

of Moratorium<br />

Telecom with Dennis Nishimura (ph: 527-6064) - Planner at DPP, Site <strong>Development</strong><br />

Division:<br />

1. Was referred to by Mr. Kevin Nakamura, District Engineer at Kaneohe Sewage<br />

Treatment Plant, ph: 254-4063.<br />

2. Mr. Nishimura confirmed that the moratorium on plumbing fixture units imposed by 92<br />

/ PRU-3, condition 4, limiting development to a one-to-one replacement until the<br />

Kaneohe Sewage Treatment Plant is expanded, was lifted in the mid 1990s.<br />

3. DPP, Site <strong>Development</strong> Division will determine if the number of plumbing fixtures is<br />

within the sewer system capacity for each project on a case-by-case basis.<br />

4. Applicant can download application on DPP website, Site <strong>Development</strong> Division,<br />

Master Application form, sewer portion.<br />

5. Send application to:<br />

City & County of Honolulu<br />

Department of Planning and Permitting<br />

Site <strong>Development</strong> Division<br />

650 South King Street, Honolulu<br />

Hawaii, HI 96814<br />

Attention Mr. Dennis Nishimura.<br />

6. A response will be provided within 2 working days. If the proposed project’s plumbing<br />

fixture unit count exceeds the sewer system’s capacity, DPP will work with the<br />

applicant on a solution to meet capacity.<br />

AMERICAN SAVINGS BUILDING<br />

SUITE 1230<br />

1357 KAPIOLANI BOULEVARD<br />

HONOLULU, HI 96814-4537<br />

TEL 808.521.8889<br />

FAX 808.521.3757<br />

www.leoadaly.com


PROJECT DEVELOPMENT REPORT<br />

VOLUME I: PLANNING & CONCEPT DEVELOPMENT<br />

APPENDIX D<br />

COPY OF ENVIRONMENTAL ASSESSMENT FOR<br />

WINDWARD COMMUNITY COLLEGE MASTER PLAN<br />

PROJECT NO. CC-02-6188<br />

APRIL 2004<br />

1357 KAPIOLANI BOULEVARD<br />

HONOLULU, HAWAII 96814


PROJECT DEVELOPMENT REPORT<br />

VOLUME I: PLANNING & CONCEPT DEVELOPMENT<br />

APPENDIX E<br />

CORRESPONDENCE – STATE HISTORIC PRESERVATION<br />

PROJECT NO. CC-02-6188<br />

APRIL 2004<br />

1357 KAPIOLANI BOULEVARD<br />

HONOLULU, HAWAII 96814


The Learning Resource Center at <strong>Windward</strong> <strong>Community</strong> <strong>College</strong><br />

PROGRAM PLANNING<br />

SUMMARY OF FUNCTIONS - ASSIGNABLE SQUARE FOOTAGE<br />

Function<br />

Number Function Description Units<br />

Student<br />

Stations<br />

Fac/Staff<br />

Stations<br />

Pre-Final<br />

I. Administration<br />

1 Director of Information Technology Services<br />

Office 1 1 200<br />

2 Institutional Researcher Office 1 1 200<br />

3 Secretary Office 1 2 175<br />

4 Administrative Storage Room 1 0<br />

5 Conference Room 1 600<br />

5a Male Restroom 1 50<br />

5b Female Restroom 1 50<br />

Subtotal 0 4 1,275<br />

II. <strong>Library</strong><br />

6 Vestibule 1 800<br />

7 Information Commons 1 48 2,700<br />

8 Information Commons Manager's Office 1 1 150<br />

9 Information Reference Desk Area 1 4 425<br />

10 Reference Collection Area 1 16 1,100<br />

11 Reference Librarian's Office (4 @ 115) 4 4 460<br />

12 Reference Librarians Conference Room 1 340<br />

13 Circulation Service Center 1 4 1,125<br />

14 Circulation Workroom 1 3 735<br />

15 Circulation Manager's Office 1 1 145<br />

16 Circulation Storage Room 1 200<br />

17 Current Periodicals Area 1 20 700<br />

18 Periodicals Backfile Area 1 12 700<br />

19 Microforms Area 1 5 550<br />

20 Pamphlets Area 1 4 155<br />

21 Maps/Art Prints Area 1 4 600<br />

22 Listening/Viewing Area 1 8 480<br />

23 Study Area A 1 22 1,000<br />

24 Hawaiian Collection Room 1 24 1 1,800<br />

25 Bookstacks Area 1 5,500<br />

26 Study Area B (shared w/ Learning Center) inc.<br />

6 study booths 1 110 4,100<br />

27 Group Viewing Room (1 @ 300 & 2 @ 170) 3 640<br />

28 Group Study Room (6 @ 150 & 2 @170) Area<br />

B 9 1,240<br />

29 Technical Services Room 1 4 1,130<br />

30 Technical Services Librarian's Office (Tech I) 1 1 140<br />

31 <strong>Library</strong> Technician's Office (Tech II) 1 1 130<br />

32 <strong>College</strong> Archives Room 1 600<br />

32a Circulation Storage Room 1 135<br />

33 Head Librarian's Office 1 1 240<br />

34 Secretary Office 1 1 195<br />

University of Hawaii <strong>Community</strong> <strong>College</strong>s December 2003<br />

Project No. CC-02-6188 1 PRE-FINAL


The Learning Resource Center at <strong>Windward</strong> <strong>Community</strong> <strong>College</strong><br />

PROGRAM PLANNING<br />

SUMMARY OF FUNCTIONS - ASSIGNABLE SQUARE FOOTAGE<br />

Function<br />

Number Function Description Units<br />

Student<br />

Stations<br />

Fac/Staff<br />

Stations<br />

Pre-Final<br />

35 Storage Room 1 200<br />

36 Staff Emergency Room and Lounge 1 800<br />

37 Meeting Room with 2 Closets @ 100 1 1,220<br />

38 Electronic Classroom 1 24 1 875<br />

39 Computer Laboratory 1 72 4 3,670<br />

39a 24-hour Study/Coffee Shop 1 30 1,500<br />

Subtotal 399 31 36,480<br />

III. The Learning Center (TLC)<br />

40 TLC Coordinator's Office 1 1 150<br />

41 TLC Manager 1 1 120<br />

42 Distribution Center 1 2 330<br />

43 Work Room 1 2 385<br />

44 Testing Room 1 25 810<br />

45 Quiet Study Area (Merged with Study Area ‘B’ -<br />

<strong>Library</strong> 1 0 5 0<br />

46 Resource Teacher Room 2 2 220<br />

47 STAAR Reception Area 1 2 180<br />

48 STAAR Counselor's Office 3 3 330<br />

49 STAAR Clerk-Typist Office 1 1 100<br />

50 STAAR Tutors' Office 1 2 235<br />

Subtotal 27 19 2,860<br />

IV. Computing Services<br />

51 Computing Services Coordinator's Office 1 1 215<br />

52 Computing Services Secretary Office 1 2 205<br />

53 Help Desk Room 1 2 285<br />

54 Training and Demonstration Room 1 2 440<br />

55 Staff Workroom 1 6 985<br />

56 Computer Setup and Repair Room 1 4 800<br />

57 Server Area 1 0 355<br />

58 Storage Room 1 200<br />

58a Bathroom 50<br />

Subtotal 0 17 3,535<br />

V. Instructional Media Services<br />

59 Reception Area/Counter/Equipment Check-out 1 3 210<br />

60 General Office, Job and Equipment Intake<br />

Room 1 6 450<br />

61 Clerk-Typist's Office 1 1 125<br />

62 Media Coordinator’s Office 1 1 200<br />

63 Storage Room 1 0 190<br />

64 Duplication and Copiers Room 1 1 610<br />

65 Duplication Storage Room 1 0 160<br />

66 Bindery Room 1 3 300<br />

University of Hawaii <strong>Community</strong> <strong>College</strong>s December 2003<br />

Project No. CC-02-6188 2 PRE-FINAL


The Learning Resource Center at <strong>Windward</strong> <strong>Community</strong> <strong>College</strong><br />

PROGRAM PLANNING<br />

SUMMARY OF FUNCTIONS - ASSIGNABLE SQUARE FOOTAGE<br />

Function<br />

Number Function Description Units<br />

Student<br />

Stations<br />

Fac/Staff<br />

Stations<br />

Pre-Final<br />

67 Duplication Manager's Office 1 1 140<br />

68 New Media Laboratory 1 20 1 620<br />

69 Instructional <strong>Development</strong> Specialist’s Office 1 1 110<br />

70 Media Production Specialist's Office 1 1 120<br />

71 Web Master's Office 1 1 125<br />

72 Studio Storage Room 1 0 110<br />

73 Instructional Video Studio 1 5 715<br />

74 Electronic Duplication and Distribution Room 1 3 450<br />

75 Studio Control Room 1 6 210<br />

76 Audio Recording Booth 1 2 125<br />

77 Electronic Maintenance and Repair Shop 1 3 745<br />

78 Electronic Technician I Office 1 1 145<br />

79 Electronic Technician II Office 1 1 145<br />

80 Equipment Storage Room 1 1 215<br />

81 Graphic Materials Preparation Room 1 4 4 850<br />

82 Graphic Artist’s Office 1 1 160<br />

83 Graphics Storage Room 1 0 115<br />

84 Spray Booth 0 70<br />

85 Loading and Receiving/Storage Room 0 900<br />

85a Bathroom 1 0 50<br />

Subtotal 29 42 8.365<br />

Subtotal (Assignable Square Feet) 455 113 52,515<br />

VI. Non-Assignable Square Feet/Building Support<br />

86. Atrium 1 3,500<br />

87. Delivery Area/Receiving (Merged with #85) 1<br />

88. Cart Parking Area 1 485<br />

89. Trash Area 1 250<br />

90. Wiring/Telecommunications Room (1 @ 1 440<br />

400)<br />

91. Wiring/Telecommunications Subroom (1 @ 4 415<br />

85, 1 @ 95, 1 @ 100, 1 @ 135)<br />

92. Janitorial Rooms (1 @ 45, 1 @ 60, 1 @ 65, 4 240<br />

1 @ 70)<br />

93. Central Housekeeping 1 160<br />

94. Central Mechanical Room 1 3,090<br />

95. Central Electrical Room 1 350<br />

96. Electrical Floor Closets (4 @ 60) 4 240<br />

97. Public Toilets (2 @ 280, 2 @ 285) 4 1,130<br />

98. Student Lockers/Bag Nitches (20 ½ length<br />

lockers)<br />

40 200<br />

University of Hawaii <strong>Community</strong> <strong>College</strong>s December 2003<br />

Project No. CC-02-6188 3 PRE-FINAL


The Learning Resource Center at <strong>Windward</strong> <strong>Community</strong> <strong>College</strong><br />

PROGRAM PLANNING<br />

SUMMARY OF FUNCTIONS - ASSIGNABLE SQUARE FOOTAGE<br />

Function<br />

Number Function Description Units<br />

Student<br />

Stations<br />

Fac/Staff<br />

Stations<br />

Pre-Final<br />

Subtotal (Non-Assignable Square Feet)<br />

10,500<br />

(VI)<br />

Subtotal Assignable Square<br />

52,515<br />

Feet (I-V)<br />

Subtotal (I-VI) 63,015<br />

VII. Horizontal & Vertical Circulation, Wall<br />

Thickness; Duct Shafts & Overhangs (+29.8%)<br />

18,778<br />

TOTAL GROSS SQUARE FEET 81,793<br />

GSF<br />

University of Hawaii <strong>Community</strong> <strong>College</strong>s December 2003<br />

Project No. CC-02-6188 4 PRE-FINAL


<strong>Windward</strong> <strong>Community</strong> <strong>College</strong><br />

Hale Manaleo


<strong>Windward</strong> <strong>Community</strong> <strong>College</strong><br />

Hale Manaleo

Hooray! Your file is uploaded and ready to be published.

Saved successfully!

Ooh no, something went wrong!