Concept Development - Windward Community College Library
Concept Development - Windward Community College Library
Concept Development - Windward Community College Library
Create successful ePaper yourself
Turn your PDF publications into a flip-book with our unique Google optimized e-Paper software.
LEARNING RESOURCE CENTER<br />
PROJECT DEVELOPMENT REPORT<br />
VOLUME I: PLANNING & CONCEPT DEVELOPMENT<br />
PROJECT NO. CC-02-6188<br />
APRIL 2004<br />
1357 KAPIOLANI BOULEVARD<br />
HONOLULU, HAWAII 96814
VOLUME I CONTENTS<br />
I. INTRODUCTION<br />
A. PROJECT DESCRIPTION<br />
B. OBJECTIVES OF THE PROJECT DEVELOPMENT REPORT<br />
C. ELEMENTS OF THE PROJECT DEVELOPMENT REPORT<br />
D. PROJECT METHODOLOGY<br />
Figure 1 Existing Land Use<br />
II.<br />
SUMMARY OF GENERAL PLANNING REFERENCES<br />
A. INTRODUCTION<br />
B. PLANNING DOCUMENTS<br />
1. Plan Review Use Resolution<br />
2. Master Plan Report Dated April 22, 1989<br />
3. Urban Design Guidelines Dated November 30, 1995<br />
4. Parking Implementation Plan<br />
5. State Historical Preservation<br />
6. Environmental Assessment<br />
C. WINDWARD COMMUNITY COLLEGE – EXISTING CONDITIONS<br />
1. Overall Campus Land Use<br />
2. Vehicular Circulation and Parking<br />
3. Pedestrian Circulation<br />
4. Landscaping and Open Space<br />
5. Views<br />
6. Site Utilities<br />
Figure II.1<br />
Figure II.2<br />
Figure II.3<br />
Figure II.4<br />
Existing Land Use<br />
Existing Vehicular Pedestrian Circulation<br />
Existing Vegetation & Open Space<br />
Existing Underground Utilities<br />
III.<br />
THE LEARNING RESOURCE CENTER<br />
A. OVERVIEW OF THE PLANNING AND DESIGN PROCESS<br />
B. LIBRARY OF THE FUTURE/VISION
C. PROJECT SUCCESS CRITERIA/GOALS<br />
1. Planning<br />
2. Technology<br />
3. <strong>Library</strong> Environments<br />
D. FACILITIES PROGRAM: Exhibit III.1 – SUMMARY OF SPATIAL<br />
REQUIREMENTS<br />
E. CITY & COUNTY OF HONOLULU LAND USE ORIDNANCE:<br />
PRELIMINARY ZONING INFORMATION<br />
1. Preliminary Zoning Information<br />
2. Exhibit III.2 Parking Stall Summary<br />
3. Exhibit III.3 Parking Stall Calculation<br />
F. PRELIMINARY BUILDING CODE ANALYSIS<br />
1. Applicable Building Code<br />
2. Occupancy Groups<br />
3. Type of Construction<br />
4. Allowable Areas<br />
5. Allowable Building Height<br />
6. Occupancy Separation<br />
7. Fire Resistive Requirements for Building Elements<br />
G. FINAL CONCEPT DESIGN (EARLY SCHEMATICS)<br />
1. Site Analysis<br />
2. Architectural Design <strong>Concept</strong><br />
H. ENVIRONMENTAL ANALYSIS<br />
Figure III.1.1 Topography<br />
Figure III.1.2 Existing Underground Utilities<br />
Figure III.1.3 Sun/Wind<br />
Figure III.1.4 Existing Overhead Utilities<br />
Figure III.1.5 Site Amenities<br />
Figure III.2.1 Aerial Perspective<br />
Figure III.2.2 Site Plan February<br />
Figure III.2.3 First Level Floor Plan<br />
Figure III.2.4 Second Level Floor Plan<br />
Figure III.2.5 Third Level Floor Plan<br />
Figure III.2.6 Site Section Looking North<br />
Figure III.2.7 Building Section A-A Looking South<br />
Figure III.2.8 Building Section B-B Looking North<br />
Figure III.2.9 East Site Elevation<br />
Figure III.2.10 Exterior Building Elevations, West and East<br />
Figure III.2.11 Exterior Building Elevations, North and South
IV.<br />
PRELIMINARY ENGINEERING DESIGN CRITERIA<br />
A. INTRODUCTION<br />
B. SUMMARY OF EXISTING SITE CONDITIONS AND UTILITIES<br />
1. Overview<br />
2. Parking, Circulation and Accessibility<br />
3. Site Grading<br />
4. Geotechnical Survey<br />
5. Water System<br />
6. Wastewater System<br />
7. Storm Drainage System<br />
8. Sustainable Design<br />
C. LANDSCAPE<br />
1. Overview<br />
2. Design Parameters<br />
3. Plant List<br />
4. Irrigation System<br />
D. STRUCTURAL ENGINEERING<br />
1. Overview<br />
2. Design Criteria<br />
E. MECHANICAL ENGINEERING<br />
1. Overview<br />
2. HVAC<br />
3. Plumbing<br />
4. Fire Protection<br />
5. Sustainable Design<br />
F. ELECTRICAL ENGINEERING<br />
1. Overview<br />
2. HECO Requirements<br />
3. Existing Site Conditions<br />
4. On-Site Power & Communications<br />
5. Design Criteria<br />
6. Sustainable Design<br />
Figure IV.1<br />
Figure IV.2<br />
Figure IV.3<br />
Figure IV.4<br />
Figure IV.5<br />
New Parking<br />
Barrier Free <strong>Concept</strong> Plan<br />
Water Supply Proposed Relocation<br />
Proposed Wastewater Relocation<br />
Storm Water Proposed Relocation
V. SUSTAINABLE DESIGN GUIDELINES<br />
A. OVERVIEW<br />
Exhibit V.1 LEED® Certification Summary<br />
VI.<br />
VII.<br />
VIII.<br />
IMPLEMENTATION & STATEMENT OF PROBABLE CONSTRUCTION<br />
COST<br />
Exhibit VI.1 Statement of Probable Construction Cost<br />
REFERENCES<br />
APPENDICES<br />
APPENDIX A:<br />
APPENDIX B:<br />
APPENDIX C:<br />
APPENDIX D:<br />
APPENDIX E:<br />
PLAN REVIEW USE (PRU) ASSESSMENT AND CITY<br />
AND COUNTY OF HONOLULU REVIEW COMMENTS<br />
INTERACTIVE WORKSHOP NOTES AND DOCUMENTS<br />
MEETING NOTES<br />
COPY OF WINDWARD COMMUNITY COLLEGE<br />
ENVIRONMENTAL ASSESSMENT<br />
CORRESPONDENCE – STATE HISTORIC<br />
PRESERVATION including:<br />
1. Alternate Site Plans<br />
2. Rendering of Proposed Building and Its Impact on<br />
Site
The Learning Resource Center at <strong>Windward</strong> <strong>Community</strong> <strong>College</strong><br />
PROJECT DEVELOPMENT REPORT<br />
I. INTRODUCTION<br />
A. Project Description<br />
The Physical Facilities, Planning and Construction Office for the <strong>Community</strong><br />
<strong>College</strong>s of the University of Hawaii has contracted LEO A DALY to prepare a<br />
Project <strong>Development</strong> Report (PDR) for The Learning Resource Center at<br />
<strong>Windward</strong> <strong>Community</strong> <strong>College</strong> in Kaneohe, Hawaii. The proposed facility will<br />
house the <strong>Library</strong>, The Learning Center (TLC), Computing Services, Instructional<br />
Media Services, and administrative and support areas. These departments are<br />
currently located in separate facilities throughout the campus, and will be<br />
integrated into a new single facility which will optimize space and staff through<br />
efficient sharing of common areas.<br />
A Plan Review Use (PRU) application and related Master Plan documents were<br />
approved by a Resolution of the City and County Council of Honolulu in 1994.<br />
The Learning Resource Center is envisioned as a two-three-story structure with<br />
sloped clay tile roofs and a stucco exterior in keeping with the Spanish<br />
Mediterranean architectural style already established on the campus. The<br />
proposed facility is located on the same site designated in the approved Master<br />
Plan for the campus. The proposed net floor area is approximately 63,000<br />
square feet; projected gross floor area is approximately 81,793 square feet.<br />
B. Objectives of the Project <strong>Development</strong> Report<br />
The Project <strong>Development</strong> Report has the following goals:<br />
• to verify, document and refine the space and adjacency requirements<br />
established in the Educational Specifications.<br />
• to prepare an architectural design concept implementing the Program Plan,<br />
which is compliant with guidelines for governmental regulations and<br />
standards for accessibility, as well as compliance with historical, aesthetic,<br />
environmental, sustainable and utility considerations.<br />
• to prepare a preliminary cost estimate for both the design and the<br />
construction of The Learning Resource Center.<br />
• to publish a report documenting the planning and design criteria.<br />
• to accomplish all of the above within the guidelines and provisions of the<br />
approved Plan Review Use resolution and related Five-Year Master Plan and<br />
Urban Design Guidelines for <strong>Windward</strong> <strong>Community</strong> <strong>College</strong>.<br />
C. Elements of the Project <strong>Development</strong> Report<br />
The two-volume Project <strong>Development</strong> Report is organized as follows:<br />
University of Hawaii <strong>Community</strong> <strong>College</strong>s April 2004<br />
Project No. CC-02-6188 I-1
The Learning Resource Center at <strong>Windward</strong> <strong>Community</strong> <strong>College</strong><br />
PROJECT DEVELOPMENT REPORT<br />
Volume I: Planning and <strong>Concept</strong> <strong>Development</strong><br />
• Summary of Documents and Conditions Guiding the Planned Facility<br />
• Summary of Program Planning<br />
• Implications of Land Use Ordinance Requirements<br />
• Preliminary Building Code Analysis<br />
• Early Schematic <strong>Concept</strong> Design of the Facility<br />
• Environmental Analysis of the Facility<br />
• Preliminary Engineering Design Criteria<br />
• Sustainable Design Guidelines<br />
• Implementation Schedule<br />
• Probable Construction Cost<br />
• References<br />
• Appendices<br />
Volume II: Program Planning<br />
• Requirements for the Learning Resource Center and the Campus in General<br />
• Summary of Assignable and Non-Assignable Square Footage Requirements<br />
by Building Function<br />
• Functional Relationship Diagrams Denoting Space Requirements and<br />
Adjacencies<br />
• Program Characteristics with Descriptions of Area Uses, Design<br />
Considerations, and Furniture and Equipment Quantities and Dimensions<br />
D. Project Methodology<br />
The objectives of this Project <strong>Development</strong> Report were accomplished by<br />
following a work plan that included the following events, some of which occurred<br />
sequentially, others in parallel with one another:<br />
Meetings with the <strong>Windward</strong> <strong>Community</strong> <strong>College</strong> Directors/Coordinators of the<br />
four areas comprising the new Learning Resource Center: the <strong>Library</strong>, The<br />
Learning Center (TLC), Computing Services, and Instructional Media Services to<br />
determine the programming requirements of each.<br />
• Compilation of the Educational Specifications for all four areas by the Head<br />
Librarian.<br />
• Site trips to mainland libraries led by LEO A DALY’s expert in the planning and<br />
design of libraries.<br />
• Site studies through photographs and physical measurements.<br />
• Meetings with the Physical Facilities, Planning and Construction Office for the<br />
<strong>Community</strong> <strong>College</strong>s of the University of Hawaii, The State Historic Office of<br />
Preservation, the State OEQC Environmental Assessment Planner, the City<br />
Plan Review Use (PRU) Planner, the Fire Marshall of the City and County of<br />
Honolulu, members of the Outdoor Circle’s Kaneohe, Hawaii Branch.<br />
University of Hawaii <strong>Community</strong> <strong>College</strong>s April 2004<br />
Project No. CC-02-6188 I-2
The Learning Resource Center at <strong>Windward</strong> <strong>Community</strong> <strong>College</strong><br />
PROJECT DEVELOPMENT REPORT<br />
• Three (3) “round table” interactive sessions with representatives of the<br />
University of Hawaii <strong>Community</strong> <strong>College</strong>s, <strong>Windward</strong> <strong>Community</strong> <strong>College</strong><br />
department directors, administrative staff, as well as staff and consultants of<br />
LEO A DALY representing the disciplines of architecture, interior design,<br />
planning, mechanical and electrical engineering. The “round tables” were<br />
facilitated by an architect from LEO A DALY specializing in the planning and<br />
design of libraries.<br />
• The results of this planning and concept development process are<br />
documented in this report.<br />
University of Hawaii <strong>Community</strong> <strong>College</strong>s April 2004<br />
Project No. CC-02-6188 I-3
The Learning Resource Center at <strong>Windward</strong> <strong>Community</strong> <strong>College</strong><br />
PROJECT DEVELOPMENT REPORT<br />
II.<br />
SUMMARY OF GENERAL PLANNING REFERENCES<br />
A. Introduction<br />
In accordance with the City and County of Honolulu, Land Use Ordinance,<br />
Sections 3.160 and 8.30, the Department of Accounting and General Services,<br />
State of Hawaii, applied for a Plan Review Use to construct new buildings,<br />
renovate existing buildings and develop related infrastructure improvements at<br />
<strong>Windward</strong> <strong>Community</strong> <strong>College</strong>. The campus is approximately 64 acres and<br />
located in Kaneohe, Oahu, Hawaii. The Tax Map Key is 4-5-23: portion of 2.<br />
The Plan Review Use Application included the Plan Review Use for a Five Year<br />
Master Plan, the Master Plan Report, Urban Design Plan and Guidelines,<br />
Landscape Plan, Signage Plan, Lighting Plan and Parking Implementation Plan.<br />
The City & County of Honolulu, City Council approved the PRU application on<br />
May 4, 1994.<br />
The Project <strong>Development</strong> Report acknowledges the provisions of the PRU<br />
resolution/Master Plan guidelines in the development of a comprehensive facility<br />
program and the architectural design concept for The Learning Resource Center<br />
at <strong>Windward</strong> <strong>Community</strong> <strong>College</strong>. These general planning documents and<br />
contents are referenced but not attached with this report.<br />
B. Planning Documents<br />
1. Plan Review Use Resolution<br />
The Plan Review Use (PRU) documents consist of two volumes: Volume<br />
1 and Volume 2 associated with a Five-Year Master Plan for <strong>Windward</strong><br />
<strong>Community</strong> <strong>College</strong>. The documents where prepared by Okita, Kunimitsu<br />
& Associates, Inc. in May 1992. The Plan Review Use (PRU) establishes<br />
the development and master planning guidelines for <strong>Windward</strong><br />
<strong>Community</strong> <strong>College</strong> (WCC) campus as required by the City & County of<br />
Honolulu, Land Use Ordinance.<br />
Volume 1<br />
Part 1 Application Information<br />
Part 2 Narrative Description<br />
Part II-A Project Description<br />
Part II-B Applicant’s Justifications<br />
Part II-C Infrastructure Requirements<br />
Part II-D Environmental Requirements<br />
Part II-E Impacts<br />
Part II-F Social Impact Requirements<br />
University of Hawaii <strong>Community</strong> <strong>College</strong>s April 2004<br />
Project No. CC-02-6188<br />
II-1
The Learning Resource Center at <strong>Windward</strong> <strong>Community</strong> <strong>College</strong><br />
PROJECT DEVELOPMENT REPORT<br />
Appendices<br />
A Transportation Study Report<br />
B Environmental Assessment for <strong>Windward</strong> <strong>Community</strong> <strong>College</strong><br />
Master Plan<br />
Volume 2<br />
Appendix A Transportation Study<br />
<strong>Windward</strong> <strong>Community</strong> <strong>College</strong> Master Plan Report<br />
I. Introduction<br />
A. Objectives<br />
B. Guidelines and Standards<br />
C. Methodology<br />
D. Site Information<br />
II. Planning Criteria<br />
A. Educational Specifications<br />
B. Governmental Requirements<br />
III. Planning <strong>Development</strong><br />
A. Introduction<br />
B. Site Utilization Schemes<br />
C. Alternative Site Plans<br />
D. Ultimate Site Plan<br />
E. Ultimate Civil Plan<br />
F. Ultimate Electrical Plan<br />
G. Ultimate Landscape Plan<br />
H. Barrier Free Accessibility Plan<br />
I. Design Considerations<br />
IV. Space Allocation and One-Line Diagrams<br />
A. Introduction<br />
B. Space Allocation<br />
C. One-Line Diagrams<br />
Implementation<br />
A. Incremental Construction<br />
B. Costs<br />
Appendices<br />
A. Summary of Existing Buildings<br />
B. Civil Engineering Analysis<br />
2. Master Plan Report Dated April 22, 1989<br />
The <strong>Windward</strong> <strong>Community</strong> <strong>College</strong> Five-Year Master Plan Report was<br />
prepared by a Joint Venture: Okita Kunimitsu & Associates, Inc./ Ernest<br />
University of Hawaii <strong>Community</strong> <strong>College</strong>s April 2004<br />
Project No. CC-02-6188<br />
II-2
The Learning Resource Center at <strong>Windward</strong> <strong>Community</strong> <strong>College</strong><br />
PROJECT DEVELOPMENT REPORT<br />
Hara and Associates, Inc. on April 22, 1989. The Master Plan Report<br />
provides a comprehensive site and facilities development plan for the<br />
entire <strong>Windward</strong> <strong>Community</strong> <strong>College</strong> (WCC) based on the projected<br />
academic needs and incorporates the following:<br />
I. Introduction<br />
A. Objectives<br />
B. Guidelines and Standards<br />
C. Methodology<br />
D. Site Information<br />
II. Planning Criteria<br />
A. Educational<br />
III. Planning <strong>Development</strong><br />
IV. Space Allocation and One-Line Diagrams<br />
V. Implementation<br />
VI. Appendices<br />
3. Urban Design Guidelines Dated November 30, 1995<br />
The Urban Design Guidelines dated July 15, 1994 were prepared by<br />
Okita Kunimitsu & Associates, Inc. and revised on November 30, 2003.<br />
These guidelines are required by the City Council resolution and<br />
supplement the Plan Review Use for a Five-Year Master Plan. The<br />
Urban Design Guidelines establishes the design parameters to ensure a<br />
cohesive campus character for all future development at <strong>Windward</strong><br />
<strong>Community</strong> <strong>College</strong> (WCC). The contents of this document are as<br />
follows:<br />
I. Introduction<br />
A. Purpose<br />
B. Scope<br />
C. Applicable Codes and Standards<br />
D. Study Area<br />
E. Format<br />
II. Urban Design Principles and Controls<br />
A. <strong>Development</strong> Plan Common Provisions<br />
B. Koolaupoko <strong>Development</strong> Plan Special Provisions<br />
III. Campus <strong>Concept</strong>s and Themes<br />
A. Existing Character<br />
B. Design <strong>Concept</strong>s and Themes<br />
IV. Design Guidelines<br />
A. Architectural Design Guidelines<br />
B. Site <strong>Development</strong> Guidelines<br />
C. Landscape Guidelines<br />
D. Signage Guidelines<br />
E. Lighting Guidelines<br />
University of Hawaii <strong>Community</strong> <strong>College</strong>s April 2004<br />
Project No. CC-02-6188<br />
II-3
The Learning Resource Center at <strong>Windward</strong> <strong>Community</strong> <strong>College</strong><br />
PROJECT DEVELOPMENT REPORT<br />
V. Implementations<br />
A. Phasing<br />
B. Compliance<br />
C. Design Review<br />
D. Amendments<br />
VI. Appendix<br />
4. Parking Implementation Plan<br />
The Parking Implementation Plan report was prepared by Okita Kunimitsu<br />
& Associates, Inc. in October 1995. The Parking Implementation Plan<br />
establishes the number of required parking stalls and a phasing program<br />
to ensure the provision of adequate parking with the projected growth and<br />
development of the campus. The Parking Implementation Plan<br />
incorporates the following:<br />
I. Introduction<br />
A. Purpose and Intent<br />
B. Scope<br />
C. Applicable Codes and Standards<br />
D. Study Area<br />
E. Format<br />
II. Implementation and Phasing<br />
A. Implementation Plan<br />
B. Facilities Implementation<br />
C. Parking and Loading Implementation<br />
D. Existing Parking and Loading<br />
E. Phase 1 Parking and Loading<br />
F. Phase 2 Parking and Loading<br />
G. Phase 3 Parking and Loading<br />
H. Phase 4 Parking and Loading<br />
I. Phase 5 Parking and Loading<br />
5. State Historical Preservation<br />
The <strong>Windward</strong> <strong>Community</strong> <strong>College</strong> Historic Preservation Plan was<br />
prepared by School of Architecture, University of Hawaii, Heritage Center,<br />
by Spencer Leineweber, FAIA, Principle Investigator and Joy Davidson,<br />
AIA, Research Assistant on August 20, 2001. The report provides an<br />
historic assessment and survey of existing buildings on the <strong>Windward</strong><br />
<strong>Community</strong> Campus and includes the following:<br />
I. Project Information<br />
II. Master Plan Information<br />
III. New Construction<br />
IV. Design Guidelines for Structures<br />
University of Hawaii <strong>Community</strong> <strong>College</strong>s April 2004<br />
Project No. CC-02-6188<br />
II-4
The Learning Resource Center at <strong>Windward</strong> <strong>Community</strong> <strong>College</strong><br />
PROJECT DEVELOPMENT REPORT<br />
6. Environmental Assessment<br />
The Environmental Assessment (EA) for <strong>Windward</strong> <strong>Community</strong> <strong>College</strong><br />
Master Plan was prepared by Wilson Okamoto & Associates, Inc. in<br />
October 1987 (see Appendix D). The EA provides the assessment for the<br />
entire master planned campus and four (4) new buildings that include the<br />
<strong>Library</strong>/Learning Resource Center. The EA incorporated the following<br />
information that concluded with a negative declaration, or FONSI, by the<br />
State of Hawaii, Office of Environmental Quality Control:<br />
I. Introduction<br />
II. Description of the Proposed Project<br />
III. Description of the Existing Environment<br />
IV. Socio-Economic Environment<br />
V. Relationship To Plans, Policies, and Controls<br />
VI. Potential Impacts and Mitigation Measures<br />
VII. Alternatives to The Proposed Action<br />
VIII. Agencies, Organizations and Individuals Consulted References<br />
C. <strong>Windward</strong> <strong>Community</strong> <strong>College</strong> – Existing Conditions<br />
1. Overall Campus Land Use<br />
The overall campus land use was originally established in the <strong>Windward</strong><br />
<strong>Community</strong> <strong>College</strong> Master Plan Report prepared April 22, 1989 and<br />
formally defined in the Plan Review Use Application, University of Hawaii<br />
<strong>Windward</strong> <strong>Community</strong> <strong>College</strong> prepared May 1992.<br />
The refined Scheme Four (Ultimate Master Plan) of the 1989 Master Plan<br />
Report consists of the following elements. See Figure II.1 Existing Land<br />
Use.<br />
a. Building Uses<br />
• A Administration Services and Academic Support<br />
• B Media Production<br />
• C <strong>Community</strong> Service (demolish for new parking)<br />
• D General Classrooms, Campus Center/ Student<br />
Activities Center/Student Activities, Food Service,<br />
Bookstore, <strong>Community</strong> Service function<br />
• E Language Arts (demolish for new structure)<br />
• F Social Science Department<br />
• G Business Department (demolish for new structure)<br />
• H <strong>Library</strong> Services, Media Productions Services,<br />
Learning Assistance/ Tutorial Services, and<br />
Computer Facilities. (demolish for new structure)<br />
• I Math Department<br />
University of Hawaii <strong>Community</strong> <strong>College</strong>s April 2004<br />
Project No. CC-02-6188<br />
II-5
The Learning Resource Center at <strong>Windward</strong> <strong>Community</strong> <strong>College</strong><br />
PROJECT DEVELOPMENT REPORT<br />
• J Humanities<br />
• K Science Department<br />
• L Maintenance (demolish for new structure)<br />
• M Automotive Tech (demolish for new structure)<br />
• N Automotive Tech (demolish for new structure)<br />
• O Math/ Science<br />
• P Math/ Science<br />
• Q Health/ Physical Ed.<br />
Of the above building uses the Campus Center and Parking (Hale<br />
Akoakoa), the Arts and Humanities Building (Hale Palanakila), the<br />
Planetarium (Hale Hokulani) and the Science Building (Hale<br />
‘Imiloa) have been designed and constructed.<br />
b. Area uses<br />
• Parking is to be located near the entrance to the campus just<br />
adjacent to Kea‘ahala Road. Other parking is planned for the<br />
area across Banyan Drive near the Humanities Building J.<br />
Additional parking is planned for the mauka side of<br />
Honeysuckle Road.<br />
• Agricultural and Aquaculture Plots are anticipated near<br />
Building ‘P’.<br />
• Shade Houses ‘A’ and ‘B’ are anticipated in the agriculture<br />
plots.<br />
• Building I has an addition in the back of the facility.<br />
2. Vehicular Circulation and Parking<br />
The vehicular entrance to the campus is on Kea‘ahala Road. Banyan<br />
Drive intersects Kea‘ahala Road and continues around the major open<br />
space and campus building to define the perimeter of the campus. The<br />
parking for the campus is located in three primary areas: 1) to the right at<br />
the entrance along Kea‘ahala Road, 2) across Banyan Street in front of<br />
the Hale Palanakila (Humanities Building), and 3) to the southeast of the<br />
student center. There is also parking along Honeysuckle Road and Ilima<br />
Way and around Hale Alaka‘I, Hale Kuhina, and the automotive area.<br />
See Figure II.2 Existing Vehicular & Pedestrian Circulation.<br />
3. Pedestrian Circulation<br />
The pedestrian circulation is comprised of the existing network of<br />
walkways interior to the campus and along Banyan Drive on the east side<br />
on the campus. See Figure II.2 Existing Vehicular & Pedestrian<br />
Circulation.<br />
University of Hawaii <strong>Community</strong> <strong>College</strong>s April 2004<br />
Project No. CC-02-6188<br />
II-6
The Learning Resource Center at <strong>Windward</strong> <strong>Community</strong> <strong>College</strong><br />
PROJECT DEVELOPMENT REPORT<br />
The comprehensive network of curvilinear walkways is defined in the<br />
Master Plan of <strong>Windward</strong> <strong>Community</strong> <strong>College</strong>. This proposed network is<br />
being incrementally developed in conjunction with the implementation of<br />
individual facilities that are planned for the campus.<br />
4. Landscaping and Open Spaces<br />
5. Views<br />
a. Central Campus Landscaping<br />
Trees and Palms: The major open space consists of a sloped<br />
grass area with 20 banyan trees within the major open space.<br />
Two of the banyan trees are in need of special attention; these are<br />
the two just to the southeast of the site. There are a very limited<br />
number of palm trees within the major open space and these are<br />
located very close to the existing buildings, not in the major open<br />
space area.<br />
Ground Covers: The major open space area is entirely grassed<br />
with a small amount of different types of ground cover that tends<br />
to integrate the buildings into the landscape areas.<br />
Plant types and irrigation requirements are further discussed in<br />
Section IV, Item C Landscape.<br />
b. Open Space<br />
‘Ilima Way defines the major open space on the north and the<br />
buildings fronting Banyan Drive and Honeysuckle Drive define this<br />
space on the southeast and west. The master plan mandates the<br />
retention of this openness on the southeast sector of campus.<br />
The open space to the southeast is much more of a “passive open<br />
space” while the open space to the northwest is potentially more<br />
active due to the pedestrian activity generated by the classrooms<br />
in both the Humanities Building and the Science Center. See<br />
Figure II.3 Existing Vegetation & Open Spaces.<br />
The Koolau Mountains are viewed from most locations on the campus.<br />
The two views that are identified in the Urban Design Plan are the views<br />
to the south and to the west, page 11 Figure 2 Campus Views and Open<br />
Space; <strong>Windward</strong> <strong>Community</strong> <strong>College</strong> Urban Design Plan and Design<br />
Guidelines July 1994. The lower image views from the campus are<br />
limited to a certain degree by the campus buildings themselves on the<br />
north-north west, west, southwest, east, northeast, and north. The view<br />
to the south-southeast is open at grade level and to the mountains. See<br />
Figure II.3.<br />
University of Hawaii <strong>Community</strong> <strong>College</strong>s April 2004<br />
Project No. CC-02-6188<br />
II-7
The Learning Resource Center at <strong>Windward</strong> <strong>Community</strong> <strong>College</strong><br />
PROJECT DEVELOPMENT REPORT<br />
6. Site Utilities<br />
The existing Site Utilities are shown on Figure II.4, Underground Utilities<br />
as a general reference. The assessment and proposed improvements<br />
are discussed in Section IV Preliminary Engineering Design Criteria.<br />
University of Hawaii <strong>Community</strong> <strong>College</strong>s April 2004<br />
Project No. CC-02-6188<br />
II-8
The Learning Resource Center at <strong>Windward</strong> <strong>Community</strong> <strong>College</strong><br />
PROJECT DEVELOPMENT REPORT<br />
III.<br />
THE LEARNING RESOURCE CENTER<br />
A. Overview of the Planning and Design Process<br />
In the summer of 2003, the programming and design team began a pre-design<br />
analysis for the new Learning Resource Center at <strong>Windward</strong> <strong>Community</strong> <strong>College</strong>.<br />
The purpose of this report is to focus on the new Learning Resource Center<br />
building and define its future potential which will combine five currently separate<br />
campus functions: 1) <strong>Library</strong>; 2) The Learning Center; 3) Instructional Media<br />
Services; 4) Computing Services and Computer Laboratory; and 5) LRC<br />
Administration. This analysis includes a recommended final site selection, a final<br />
space needs program, a new building design concept, and a conceptual<br />
construction cost estimate.<br />
It is important to note that this is only a preliminary schematic design study and<br />
the related code analysis, engineering criteria and cost data are conceptual in<br />
nature.<br />
The design study team was comprised of University of Hawaii <strong>Community</strong><br />
<strong>College</strong> Facilities Planning Staff, <strong>Windward</strong> <strong>Community</strong> <strong>College</strong><br />
Staff/Administrators and the architectural firm of LEO A DALY. Through the<br />
summer and fall of 2003, a series of work sessions, tours and conference calls<br />
were conducted to address the vision and goals for the project. The current uses<br />
and organization of The Learning Resource Center components were toured and<br />
quantified. Proposed space needs were identified and summarized in a program<br />
matrix. The systems and infrastructure of the existing facilities were reviewed<br />
and a variety of issues identified. A site plan, floor plans, building sections,<br />
elevations study models, a perspective rendering, and cost models were<br />
developed to determine the overall budget.<br />
To help identify the vision of a 21 st century library/learning resource center,<br />
members of the <strong>Windward</strong> staff along with LEO A DALY design team members<br />
toured three libraries, all with Information Commons serving as the “living room<br />
for the campus.” Libraries visited were the new Lied <strong>Library</strong> at UNLV (University<br />
of Nevada at Las Vegas), the renovated campus <strong>Library</strong> at the University of<br />
Arizona (Tucson), and the new <strong>Library</strong> at Mesa <strong>Community</strong> <strong>College</strong> in Phoenix.<br />
These tours proved very valuable, providing both insight and confirmation of the<br />
emerging concept layout for the new Learning Resource Center.<br />
LEO A DALY would like to thank the University of Hawaii <strong>Community</strong> <strong>College</strong>s, the<br />
<strong>Windward</strong> <strong>Community</strong> <strong>College</strong> Administration and the entire <strong>Library</strong> staff for their<br />
valuable input, understanding, and willingness to explore and invest in the future.<br />
B. <strong>Library</strong> of the Future/Vision<br />
Academic libraries are known as leaders among their peers in the delivery of<br />
scholarly information services to a diverse and global community. These libraries<br />
University of Hawaii <strong>Community</strong> <strong>College</strong>s April 2004<br />
Project No. CC-02-6188<br />
III-1
The Learning Resource Center at <strong>Windward</strong> <strong>Community</strong> <strong>College</strong><br />
PROJECT DEVELOPMENT REPORT<br />
also are known for their efficient use of state-of-the-art information technologies,<br />
innovative management practices, and faculty focused on leading-edge<br />
professional directions. The libraries’ reputation for partnership-building and<br />
consortium leadership is widely recognized, and is known for its client-focused<br />
and learner-centered approach to librarianship. The challenge now is to create a<br />
new library/learning resource center paradigm within an aesthetically rich and<br />
dynamic physical environment. It is time to combine and transform these aging<br />
facilities to meet the challenges and expectations of a new, collaborative,<br />
learning environment, and to develop The Learning Resource Center at<br />
<strong>Windward</strong> into a facility that is the heart of the campus and a vibrant and inspiring<br />
“place” where students are welcomed and nourished.<br />
Recent developments in higher education have prompted a near revolution in<br />
teaching and learning, with libraries eagerly embracing such opportunities as: 1)<br />
the advent of web-enhanced instruction; 2) universal computer-access programs<br />
and the growing seamlessness of the worldwide community of libraries; 3) the<br />
rapid proliferation of full-text electronic research databases; and 4) necessary<br />
reconfiguration, plus growth of the internal geography of libraries and learning<br />
resource centers. These dynamic new campus resource centers are being<br />
realized through new construction or major reconceptualization and renovation of<br />
those structures built in the 1970s or earlier.<br />
Leadership at <strong>Windward</strong> <strong>Community</strong> <strong>College</strong> clearly has accepted these<br />
challenges. As innovators on the state, regional, and national stages, they have<br />
continued to engage their peers in conversations on the future of information<br />
services.<br />
As academic libraries move into the digital age, their role is constantly being<br />
challenged. Obviously, this is affecting library facilities, both existing and<br />
proposed. <strong>Library</strong> space must be designed to accommodate new approaches<br />
toward interaction between technology and fellow information seekers. Many new<br />
services, such as distance learning, are affecting library facility needs, and the<br />
role of the library as a campus cultural center and icon is becoming more<br />
prevalent on many college campuses.<br />
In the midst of these changes, many traditional library services will remain and<br />
continue to place demands on space. Facilities must be able to accommodate<br />
these traditional elements, which are associated with paper format resources, as<br />
this format will continue to play a significant role in library collections for the next<br />
several decades. The essential element in this transition to planning for the<br />
digital age is flexibility of space.<br />
It is incumbent upon the proposed new Learning Resource Center to<br />
architecturally express the importance of space in a learning society, the<br />
changing nature of collections, the effect on the library as a symbolic and<br />
physical place, and the library as a “community place” at the academic center of<br />
University of Hawaii <strong>Community</strong> <strong>College</strong>s April 2004<br />
Project No. CC-02-6188<br />
III-2
The Learning Resource Center at <strong>Windward</strong> <strong>Community</strong> <strong>College</strong><br />
PROJECT DEVELOPMENT REPORT<br />
the university. The new Learning Resource Center facility should be viewed as<br />
the most important, interesting, and popular building on campus.<br />
Even in a difficult economic period, library facility improvements and expansions<br />
appear to be at an all-time high, with many universities viewing their new and<br />
expanded libraries as signature campus buildings, critical to attracting and<br />
retaining excellent students and faculty.<br />
C. Project Success Criteria/Goals<br />
The vision for the new Learning Resource Center is to recognize the role of<br />
<strong>Library</strong> as Central Place on the <strong>Windward</strong> <strong>Community</strong> <strong>College</strong> campus. The<br />
Learning Resource Center building serves as a home for a community of<br />
learners and their materials, a refuge for commuting students, and a collaborative<br />
and scholarly environment for faculty, staff, students and members of the greater<br />
community.<br />
As a guide to the planning team the following goals/criteria were developed:<br />
1. Planning<br />
a. Create a memorable sense of place that welcomes users<br />
b. Enhance the library’s presence on campus, marking these newly<br />
combined Learning Resource Center functions with a distinguished<br />
“landmark” architectural image<br />
c. Creatively combine, under one roof, the five currently separated<br />
departments within open floor plans with visual clarity to the<br />
services provided, allowing users to navigate independently<br />
d. Arrange the collections in a climate-controlled, environmentally<br />
and physically secure, accessible, and space-efficient manner<br />
e. Increase the needed future collection growth space and reader<br />
seating programmed requirements within a flexible and rearrangeable<br />
environment<br />
f. Locate service points and departments in a readily understandable<br />
and functional pattern<br />
g. Provide barrier-free access, both inside and outside the building<br />
h. Incorporate principles of "green" architecture to create a healthy<br />
and forward-looking facility, while ensuring an appropriate.<br />
environment for the preservation of books and other materials by<br />
addressing issues of energy efficiency, recycled and replenishable<br />
resources, and flexible design<br />
i. Strive to achieve LEED® “Silver Certification” based on the U.S.<br />
Green Buildings Council criteria.<br />
j. Invite the <strong>College</strong> faculty to become a more accommodating<br />
presence in the library proper<br />
k. Encourage natural daylight and views to the surrounding natural<br />
beauty at every opportunity<br />
University of Hawaii <strong>Community</strong> <strong>College</strong>s April 2004<br />
Project No. CC-02-6188<br />
III-3
The Learning Resource Center at <strong>Windward</strong> <strong>Community</strong> <strong>College</strong><br />
PROJECT DEVELOPMENT REPORT<br />
l. Retain and emphasize the natural beauty of the <strong>Windward</strong><br />
campus site, paying special attention to the rural and pastoral<br />
ambiance unique to the campus<br />
m. Design the new building to “feel at home” in the campus context of<br />
arches, tile roofs, shaded lanais, and landscape.<br />
2. Technology<br />
a. Provide an Information Commons uniting technology, reference<br />
services, research assistance, instructional media, and The<br />
Learning Center assistance to create a collaborative learning<br />
environment – a campus living room<br />
b. Provide locations for technology-rich information services for<br />
students, faculty, and staff<br />
3. <strong>Library</strong> Environments<br />
a. Create collaborative work environments for both students and staff<br />
b. Improve staff work environments<br />
c. Create a variety of study environments<br />
d. Provide comfortable meeting and gathering spaces, within an<br />
“architecture of interaction”<br />
e. Create large and small group study rooms<br />
f. Create high-technology zones throughout the building, with power<br />
and data access convenient to all reader stations<br />
g. Provide quiet zones<br />
h. Provide a coffee shop cafe and outside covered lanai/patio<br />
i. Be a welcome center to the campus<br />
j. Have a strong exterior visual identity, with the library as landmark<br />
D. Facilities Program – Summary Of Spatial Requirements<br />
The Learning Resource Center (LRC) is envisioned as the center of scholarship<br />
and learning as well as the information and technology center of <strong>Windward</strong><br />
<strong>Community</strong> <strong>College</strong>. It seeks to provide an environment conducive to the<br />
advancement of learning by providing access to comprehensive learning<br />
resources, instructional services, computers, multimedia and high speed<br />
connections, facilitating the integration of new technologies into teaching and<br />
learning, and providing appropriate technological support to the campus.<br />
The Learning Resource Center provides a collection of print, non-print and<br />
electronic resources; maximum access to these resources regardless of location<br />
or format; information and multimedia hardware and software for the general<br />
student use and advanced faculty and student productions; and instruction and<br />
assistance in the use of the various resources and technologies.<br />
University of Hawaii <strong>Community</strong> <strong>College</strong>s April 2004<br />
Project No. CC-02-6188<br />
III-4
The Learning Resource Center at <strong>Windward</strong> <strong>Community</strong> <strong>College</strong><br />
PROJECT DEVELOPMENT REPORT<br />
The following facility program and design concept incorporates new and<br />
traditional functions of the <strong>Library</strong>, Media Production Center, The Learning<br />
Center, and Academic and Administrative Computing. It strives to meet the<br />
general information needs of and to promote lifelong learning among students,<br />
faculty, staff and community users.<br />
This section summarizes the spatial requirements of the facility program, site<br />
analysis, preliminary zoning and building code analyses, the architectural design<br />
concept and the environmental analysis for the development of The Learning<br />
Resource Center.<br />
The facilities program is a comprehensive document that defines the functional,<br />
operational and spatial requirements of the facility that is represented in detail in<br />
a companion document entitled Program Planning. Exhibit III.1 SUMMARY OF<br />
FUNCTIONS – ASSIGNABLE SQUARE FOOTAGE summarizes each function,<br />
the faculty and staff requirements and the assignable square footage.<br />
EXHIBIT III.1 SUMMARY OF FUNCTIONS - ASSIGNABLE SQUARE FOOTAGE<br />
Function<br />
Number Function Description Units<br />
Student<br />
Stations<br />
Fac/Staff<br />
Stations<br />
Initial<br />
ASF Final Difference<br />
I. Administration<br />
1 Director of Information<br />
Technology Services Office 1 1 200 200<br />
2 Institutional Researcher Office 1 1 200 200<br />
3 Secretary Office 1 2 200 175 -25<br />
4 Administrative Storage Room 1 150 0 -150<br />
5 Conference Room 1 700 600 -100<br />
5a Male Restroom 1 0 50 +50<br />
5b Female Restroom 1 0 50 +50<br />
Subtotal 0 4 1,450 1,275 -175<br />
II. <strong>Library</strong><br />
6 Vestibule 1 800 800<br />
7 Information Commons 1 48 2,400 2,700 +300<br />
8 Information Commons<br />
Manager's Office 1 1 150 150<br />
9 Information Reference Desk<br />
Area 1 4 325 425 +100<br />
10 Reference Collection Area 1 16 1,050 1,100 +50<br />
Reference Librarian's Office (4<br />
@ 115) 4 4 480 460 -20<br />
11<br />
12 Reference Librarians<br />
Conference Room 1 200 340 +140<br />
Function<br />
Number Function Description Units<br />
Student<br />
Stations<br />
Fac/Staff<br />
Stations<br />
Initial<br />
ASF Final Difference<br />
University of Hawaii <strong>Community</strong> <strong>College</strong>s April 2004<br />
Project No. CC-02-6188<br />
III-5
The Learning Resource Center at <strong>Windward</strong> <strong>Community</strong> <strong>College</strong><br />
PROJECT DEVELOPMENT REPORT<br />
13 Circulation Service Center 1 4 1,000 1,125 +125<br />
14 Circulation Workroom 1 3 600 735 +135<br />
15 Circulation Manager's Office 1 1 150 145 -5<br />
16 Circulation Storage Room 1 200 200<br />
16a Additional Circulation Storage 1 1 0 135 +135<br />
17 Current Periodicals Area 1 20 925 700 -225<br />
18 Periodicals Backfile Area 1 12 925 700 -225<br />
19 Microforms Area 1 5 540 550 +10<br />
20 Pamphlets Area 1 4 200 155 -45<br />
21 Maps/Art Prints Area 1 4 460 600 +140<br />
22 Listening/Viewing Area 1 8 400 480 +80<br />
23 Study Area A 1 22 720 1,000 +280<br />
24 Hawaiian Collection Room 1 24 1 2,000 1,800 -200<br />
25 Bookstacks Area 1 6,000 5,500 -500<br />
26<br />
Study Area B (shared w/<br />
Learning Center) inc. 6 study<br />
booths 1 110 3,300 4,100 +800<br />
27 Group Viewing Room (1 @ 300<br />
& 2 @ 170) 3 450 640 +190<br />
28 Group Study Room (6 @ 150 &<br />
2 @170) Area B 9 1,150 1,240 +90<br />
29 Technical Services Room 1 4 1,200 1,130 -70<br />
30 Technical Services Librarian's<br />
Office (Tech I) 1 1 150 140 -10<br />
31 <strong>Library</strong> Technician's Office<br />
(Tech II) 1 1 150 130 -20<br />
32 <strong>College</strong> Archives Room 1 600 600<br />
33 Head Librarian's Office 1 1 200 240 +40<br />
34 Secretary Office 1 1 200 195 -5<br />
35 Storage Room 1 200 200<br />
36 Staff Emergency Room and<br />
Lounge 1 800 800<br />
37 Meeting Room with 2 Closets<br />
@ 100 1 1,200 1,220 +20<br />
38 Electronic Classroom 1 24 1 1,200 875 -325<br />
39 Computer Laboratory 1 72 4 3,600 3,670 +70<br />
39a 24-hour Study/Coffee Shop 1 30 1,000 1,500 +500<br />
Subtotal 399 31 34,925 36,480 1,555<br />
III. The Learning Center (TLC)<br />
40 TLC Coordinator's Office 1 1 150 150<br />
41 TLC Manager 1 1 120 120<br />
42 Distribution Center 1 2 340 330 -10<br />
43 Work Room 1 2 320 385 +65<br />
Function<br />
Number Function Description Units<br />
Student<br />
Stations<br />
Fac/Staff<br />
Stations<br />
Initial<br />
ASF Final Difference<br />
University of Hawaii <strong>Community</strong> <strong>College</strong>s April 2004<br />
Project No. CC-02-6188<br />
III-6
The Learning Resource Center at <strong>Windward</strong> <strong>Community</strong> <strong>College</strong><br />
PROJECT DEVELOPMENT REPORT<br />
44 Testing Room 1 25 750 810 +60<br />
45 Quiet Study Area (Merged with<br />
Study Area ‘B’ - <strong>Library</strong> 1 0 5 400 0 -400<br />
46 Resource Teacher Room 2 2 220 220<br />
47 STAAR Reception Area 1 2 200 180 -20<br />
48 STAAR Counselor's Office 3 3 330 330<br />
49 STAAR Clerk-Typist Office 1 1 110 100 -10<br />
50 STAAR Tutors' Office 1 2 220 235 +15<br />
Subtotal 27 19 3,160 2,860 -300<br />
IV. Computing Services<br />
51 Computing Services<br />
Coordinator's Office 1 1 200 215 +15<br />
52 Computing Services Secretary<br />
Office 1 2 200 205 +5<br />
53 Help Desk Room 1 2 260 285 +25<br />
54<br />
Training and Demonstration<br />
Room 1 2 400 440 +40<br />
55 Staff Workroom 1 6 1,000 985 -15<br />
56 Computer Setup and Repair<br />
Room 1 4 800 800<br />
57 Server Area 1 0 200 355 +155<br />
58 Storage Room 1 300 200 -100<br />
58a Bathroom 0 50 +50<br />
Subtotal 0 17 3,360 3,535 +175<br />
V. Instructional Media Services<br />
Reception<br />
59 Area/Counter/Equipment<br />
Check-out 1 3 250 210 -40<br />
60 General Office, Job and<br />
Equipment Intake Room 1 6 450 450<br />
61 Clerk-Typist's Office 1 1 120 125 +5<br />
62 Media Coordinator’s Office 1 1 200 200<br />
63 Storage Room 1 0 230 190 -40<br />
64 Duplication and Copiers Room 1 1 830 610 -220<br />
65 Duplication Storage Room 1 0 220 160 -60<br />
66 Bindery Room 1 3 300 300<br />
67 Duplication Manager's Office 1 1 120 140 +20<br />
68 New Media Laboratory 1 20 1 700 620 -80<br />
69 Instructional <strong>Development</strong><br />
Specialist’s Office 1 1 120 110 -10<br />
70<br />
Media Production Specialist's<br />
Office 1 1 120 120<br />
Function<br />
Number Function Description Units<br />
Student<br />
Stations<br />
Fac/Staff<br />
Stations<br />
Initial<br />
ASF Final Difference<br />
University of Hawaii <strong>Community</strong> <strong>College</strong>s April 2004<br />
Project No. CC-02-6188<br />
III-7
The Learning Resource Center at <strong>Windward</strong> <strong>Community</strong> <strong>College</strong><br />
PROJECT DEVELOPMENT REPORT<br />
71 Web Master's Office 1 1 160 125 -35<br />
72 Studio Storage Room 1 0 100 110 +10<br />
73 Instructional Video Studio 1 5 750 715 -35<br />
74 Electronic Duplication and<br />
Distribution Room 1 3 500 450 -50<br />
75 Studio Control Room 1 6 300 210 -90<br />
76 Audio Recording Booth 1 2 125 125<br />
77 Electronic Maintenance and<br />
Repair Shop 1 3 745 745<br />
78 Electronic Technician I Office 1 1 120 145 +25<br />
79 Electronic Technician II Office 1 1 120 145 +25<br />
80 Equipment Storage Room 1 1 230 215 -15<br />
81 Graphic Materials Preparation<br />
Room 1 4 4 1,000 850 -150<br />
82 Graphic Artist’s Office 1 1 150 160 +10<br />
83 Graphics Storage Room 1 0 100 115 +15<br />
84 Spray Booth 0 60 70 +10<br />
85 Loading and Receiving/Storage<br />
Room 0 1300 900 -400<br />
85a Bathroom 1 0 0 50 +50<br />
Subtotal 29 42 9,420 8,365 -1,055<br />
Subtotal (Assignable Square<br />
Feet) 455 113 52,315 52,515 +200<br />
VI. Non-Assignable Square Feet/Building Support<br />
86. Atrium 1 3,000 3,500 500<br />
87. Delivery Area/Receiving<br />
1 600 -600<br />
(Merged with #85)<br />
88. Cart Parking Area 1 500 485 -15<br />
89. Trash Area 1 200 250 +50<br />
90. Wiring/Telecommunications 1 400 440 +40<br />
Room (1 @ 400)<br />
91. Wiring/Telecommunications 4 400 415 +15<br />
Subroom (1 @ 85, 1 @ 95, 1<br />
@ 100, 1 @ 135)<br />
92. Janitorial Rooms (1 @ 45, 1 4 200 240 +40<br />
@ 60, 1 @ 65, 1 @ 70)<br />
93. Central Housekeeping 1 200 160 -40<br />
94. Central Mechanical Room 1 3,500 3,090 -410<br />
95. Central Electrical Room 1 400 350 -50<br />
96. Electrical Floor Closets (4 @ 4 320 240 -80<br />
60)<br />
97. Public Toilets (2 @ 280, 2 @ 4 1,200 1,130 -70<br />
285)<br />
98. Student Lockers/Bag Niches 40 400 200 -200<br />
(20 ½ length lockers)<br />
Function<br />
Number Function Description Units<br />
Student<br />
Stations<br />
Fac/Staff<br />
Stations Initial Final Difference<br />
University of Hawaii <strong>Community</strong> <strong>College</strong>s April 2004<br />
Project No. CC-02-6188<br />
III-8
The Learning Resource Center at <strong>Windward</strong> <strong>Community</strong> <strong>College</strong><br />
PROJECT DEVELOPMENT REPORT<br />
Subtotal (Non-Assignable<br />
11,320 10,500 -820<br />
Square Feet) (VI)<br />
Subtotal Assignable<br />
52,315 52,515 +200<br />
Square<br />
Feet (I-V)<br />
Subtotal (I-VI) 63,635 63,015 -620<br />
VII. Horizontal & Vertical Circulation,<br />
Wall Thickness; Duct Shafts &<br />
Overhangs (+29.8%)<br />
15,909 18,778<br />
TOTAL GROSS SQUARE<br />
FEET<br />
79,544<br />
GSF<br />
81,793<br />
GSF<br />
+2,249<br />
E. City & County of Honolulu Land Use Ordinance: Preliminary Zoning<br />
Information<br />
The following data is a summary of the preliminary zoning information for The<br />
Learning Resource Center as defined by the Plan Review Use Application<br />
Resolution No. 94-87, CD-1, dated May 4, 1994.<br />
1. Preliminary Zoning Information<br />
Tax Map Area: 4-5-23:2<br />
Lot Area:<br />
64 Acres<br />
Zoning:<br />
AG-2<br />
Setbacks – Front Yard: Not Applicable<br />
Setbacks – Side & Rear Yards: Not Applicable<br />
Maximum Density:<br />
Not Applicable<br />
Maximum Building Area:<br />
Not Applicable<br />
Actual Building Area:<br />
81,793 Gross Square Feet<br />
Maximum Height:<br />
50 Feet<br />
Actual Height:<br />
Varies from 36.25 Feet to 51.25 Feet<br />
Flood Zone:<br />
Not Applicable<br />
Parking Loading:<br />
See Exhibit III.2<br />
2. Exhibit III.2 Parking Stall Summary<br />
Summary Floor Area L.U.O. Requirement No. of Stalls<br />
Accessory 38,960 0 0<br />
Classrooms 7,450 1 per 10 student @ 39<br />
20 s.f. per student<br />
Conference Rooms 2,100 1 per 75 s.f. 28<br />
Offices 5,020 1 per 400 s.f. 13<br />
Learning Resource 53,530 80<br />
Center Subtotal<br />
3. Exhibit III.3 Parking Stall Calculation<br />
University of Hawaii <strong>Community</strong> <strong>College</strong>s April 2004<br />
Project No. CC-02-6188<br />
III-9
The Learning Resource Center at <strong>Windward</strong> <strong>Community</strong> <strong>College</strong><br />
PROJECT DEVELOPMENT REPORT<br />
Functions Floor Area L.U.O. Requirement No. of Stalls<br />
Administration<br />
Accessory 150 0 0<br />
Meeting Rooms 700 1 per 75 s.f. 9<br />
Offices 600 1 per 400 s.f. 2<br />
Administration<br />
Subtotal<br />
1,450 11<br />
<strong>Library</strong><br />
Accessory 24,645 0 0<br />
Classrooms 6,300 1 per 10 student @ 20 32<br />
s.f. per student<br />
Conference Rooms 1,400 1 per 75 s.f. 19<br />
Offices 1,480 1 per 400 s.f. 4<br />
<strong>Library</strong> Subtotal 33,825 55<br />
The Learning Center<br />
Accessory 3,780 0 0<br />
Classrooms 750 1 per 10 student @ 20 4<br />
s.f. per student<br />
Offices 930 1 per 400 s.f. 2<br />
Learning Center<br />
Subtotal<br />
5,460 6<br />
Computing Services<br />
Accessory 2,560 0 0<br />
Training Room 400 1 per 10 student @ 20 3<br />
s.f. per student<br />
Offices 400 1 per 400 s.f. 1<br />
Computing<br />
Services Subtotal<br />
3,360 4<br />
Instructional<br />
Media Services<br />
Accessory 7,825 0 0<br />
Offices 1,610 1 per 400 s.f. 4<br />
Instructional Media<br />
Subtotal<br />
9,435 4<br />
Learning<br />
Resource Center<br />
Net Floor Area 53,530<br />
Required Parking<br />
Stalls 80<br />
University of Hawaii <strong>Community</strong> <strong>College</strong>s April 2004<br />
Project No. CC-02-6188<br />
III-10
The Learning Resource Center at <strong>Windward</strong> <strong>Community</strong> <strong>College</strong><br />
PROJECT DEVELOPMENT REPORT<br />
F. Preliminary Building Code Analysis<br />
The following data represents preliminary building code information for The<br />
Learning Resource Center:<br />
1. Applicable Building Code: 1997 Uniform Building Code with City &<br />
County of Honolulu Amendments<br />
2. Occupancy Groups: Reading Rooms: A-3<br />
Offices: B<br />
3. Type of Construction: Type II – F.R., Sprinklered<br />
4. Allowable Areas:<br />
Allowable Area – Group A-3<br />
Basic Allowable Area:<br />
3-Side Yard Separation:<br />
Fire Sprinkler:<br />
Total Allowable Area<br />
Actual Area:<br />
29,900 S.F.<br />
x2 Max.<br />
(2.5% x 40Ft,)<br />
x3<br />
179,400 S.F.<br />
10,020 S.F.<br />
Allowable Area – Group B<br />
Basic Allowable Area:<br />
3-Side Yard Separation:<br />
Fire sprinkler:<br />
Total Allowable Area:<br />
Actual Area:<br />
39,900 S.F.<br />
x2 Max.<br />
(2.55 x 40 Ft.)<br />
x3<br />
219,400 S.F.<br />
179,400 S.F.<br />
Total Allowable Area<br />
10,020sf/179,400sf + 43,510sf/219,400sf = 0.06 + 0.20 = 0.26 < 1 (OK)<br />
5. Allowable Building Height:<br />
In Stories:<br />
6. Occupancy Separation:<br />
Between A-3 & B:<br />
2 Stories per PRU/Master Plan<br />
None; No Requirements for Fire Resistance<br />
7. Fire Resistive Requirements for Building Elements:<br />
Bearing Walls – Exterior:<br />
Bearing Walls – Interior:<br />
4 Hrs<br />
2 Hrs<br />
University of Hawaii <strong>Community</strong> <strong>College</strong>s April 2004<br />
Project No. CC-02-6188<br />
III-11
The Learning Resource Center at <strong>Windward</strong> <strong>Community</strong> <strong>College</strong><br />
PROJECT DEVELOPMENT REPORT<br />
Non-Bearing Walls – Exterior:<br />
Structural Frame:<br />
Partitions – Permanent:<br />
Shaft Enclosures:<br />
Floor and Floor – Ceilings:<br />
Floor and Roof – Ceilings:<br />
4 Hrs<br />
2 Hrs<br />
1 Hr<br />
2 Hrs<br />
2 Hrs<br />
1 Hr<br />
G. Final <strong>Concept</strong> Design (Early Schematics)<br />
1. Site Analysis<br />
a. Topography and Existing Features<br />
The site for The Learning Resource Center (LRC) is located at the<br />
northwest corner of the major open space of the campus as<br />
established by the Plan Review Use resolution and the master<br />
plan documents. The site for The Learning Resource Center<br />
slopes from an approximate elevation of 250 on the southwest to<br />
an approximate elevation of 240 to the northeast, i.e., on the<br />
mauka side of the Hale Mana‘opono Building. The LRC site has<br />
three mature banyan trees on the west, two mature banyan trees<br />
to the south of the site and one monkey pod tree on the eastern<br />
portion of the site. There are two Hong Kong orchid trees mauka<br />
of the site, three Hong Kong orchid trees makai of the site and one<br />
palm tree makai of the site and one mauka of the site.<br />
The Hale Manaleo building is currently on the site and will be<br />
removed for the construction of the new facility. The topography<br />
is characterized by a drainage pattern that followed the old<br />
streambed in the area just to the north of the site. This drainage<br />
pattern now consists of catch basins that are connected to an<br />
underground storm water system.<br />
Ilima Way vehicular access to the south of the site will be partially<br />
removed facilitating a more contiguous open space pattern with<br />
the existing campus. This area will be integrated with the major<br />
open space and The Learning Resource Center. The accessible<br />
parking associated with Ilima Way will be relocated toward the<br />
entrance of the building. The vehicular handicap access to the<br />
site will be via the fire access lane that is adjacent to the Hale<br />
Na‘auao and Hale Mana‘opono.<br />
b. Site Amenities<br />
The site has several significant amenities, which include the<br />
expansive open space, dramatic views to the Koolau’s and<br />
prominent banyan trees. There are potentially a few strategic<br />
University of Hawaii <strong>Community</strong> <strong>College</strong>s April 2004<br />
Project No. CC-02-6188<br />
III-12
The Learning Resource Center at <strong>Windward</strong> <strong>Community</strong> <strong>College</strong><br />
PROJECT DEVELOPMENT REPORT<br />
views and vistas that need to be considered to take full advantage<br />
for the beauty of the mountain views. Another significant site<br />
amenity is the mature banyan trees on site with specific attention<br />
to approximately 20 banyan trees within the major open space.<br />
The large expansive open space is a very unique site amenity.<br />
The general aggregation of Spanish Mediterranean architecture<br />
provides a unity to the campus that is a site amenity. The similar<br />
materials of stucco and red tile roofs are a dominant and unifying<br />
feature of the campus.<br />
Additional campus amenities that increase the quality of<br />
environment are: ocean breezes, dense area vegetation,<br />
abundant sunshine, abundant light rain, looped campus vehicular<br />
circulation and pedestrian zones without vehicles.<br />
c. Building Placement<br />
The Learning Resource Center Facility site was established in the<br />
PRU resolution and Master Plan documents. The placement of<br />
the building is constrained by the existing banyan tree canopies to<br />
the south and west and a monkey pod tree to the east. In the<br />
interest of saving these trees and as many Hong Kong orchid<br />
trees as possible, the building was placed on both the north south<br />
axis and the east west axis. The building is also placed vertically<br />
at an elevation that is equidistant as possible between the grades<br />
of the Hale La‘akea and the Hale Mana‘opono building to facilitate<br />
the handicap access to the proposed facility.<br />
After comparative analysis of several locations, the best site is a<br />
highly used central location at the north end of the Central Green.<br />
This site optimally places the new Learning Resource Center<br />
(LRC) at a convenient crossroads/hub for campus pedestrian<br />
traffic moving between the Student Center, Humanities Building,<br />
Science Complex, classroom buildings and parking. By using a 2-<br />
story rectangular form, the new building fits between the major<br />
trees on the site, saving all the banyan trees, the monkey pod,<br />
and most of the Hong Kong orchid trees in this area. The actual<br />
preservation of the monkey pod and orchids requires further<br />
evaluation due to the proximity of the building. The existing onestory<br />
Hale Manaleo classroom building will be demolished.<br />
This site is intended to provide great student convenience and<br />
potentially create an exciting outside lanai/plaza/amphitheater to<br />
the north to generate new prominence, energy and exposure to<br />
the spaces between the Humanities, Theater, and Science<br />
facilities. An exciting new “sense of place” is anticipated for<br />
<strong>Windward</strong> <strong>Community</strong> <strong>College</strong>.<br />
University of Hawaii <strong>Community</strong> <strong>College</strong>s April 2004<br />
Project No. CC-02-6188<br />
III-13
The Learning Resource Center at <strong>Windward</strong> <strong>Community</strong> <strong>College</strong><br />
PROJECT DEVELOPMENT REPORT<br />
d. Site Related <strong>Concept</strong> Plans<br />
The “site-fit” of The Learning Resource Center with respect to<br />
existing topography, site utilities, and amenities and constraints<br />
are represented in Figures III.1.1 – III.1.5, inclusive.<br />
2. Architectural Design <strong>Concept</strong><br />
Critical to fulfilling the vision and goals for the new Learning Resource<br />
Center (LRC) is the creation of a one-stop shop with a warm and<br />
welcoming building exterior, prominently located, and at-home within the<br />
existing architectural language of <strong>Windward</strong> <strong>Community</strong> <strong>College</strong> campus.<br />
The interior environment of the new combined-use facility housing the five<br />
relocated functions of the <strong>Library</strong>, The Learning Center (TLC),<br />
Instructional Media Services, Computing Services and LRC<br />
Administration will be spatially united as one facility, yet with each of<br />
these functions being visually identified and land marked within.<br />
The combining volume and heart will be a central, open, vertical atrium<br />
space over the Information Commons that unites the first and second<br />
levels. Located on a sloping site, the building entries are placed to invite<br />
convenient access to the lower level from the east and north, and access<br />
to the upper level from the higher grades to the west. As one enters the<br />
new building, way finding will be visually clear, with the pathways obvious<br />
and easy to see destinations.<br />
The open, invitational stairways, located at the edge of the oval-shaped<br />
atrium, are designed to encourage frequent use, thereby minimizing the<br />
use of the public elevators. Thus, all of the primary functions within this<br />
new LRC facility will be easily accessible and spatially connected.<br />
Key to the successful library is a dynamic, central and open hightechnology<br />
Information Commons surrounded and energized by<br />
collaborative study and learning opportunities, and within easy access to<br />
books, technology and staff assistance. Furniture will be comfortable,<br />
and a coffee cafe will provide friendly amenities designed to invite and<br />
encourage lingering in the LRC. The objective of this architecture of<br />
interaction is to embrace research, collaborative study (for student and<br />
faculty) and individual quiet study as well.<br />
Staff workstations and offices are efficiently and flexibly laid out close to<br />
the service points. Key resource-staffed service points will be placed to<br />
optimize the dual function of user assistance as well as building security.<br />
Electronic security gates will be placed at each of the three exterior<br />
entries.<br />
University of Hawaii <strong>Community</strong> <strong>College</strong>s April 2004<br />
Project No. CC-02-6188<br />
III-14
The Learning Resource Center at <strong>Windward</strong> <strong>Community</strong> <strong>College</strong><br />
PROJECT DEVELOPMENT REPORT<br />
The vertical zoning of key functions within the new LRC is as follows:<br />
Level One:<br />
Level Two:<br />
Level Three:<br />
East Entry (Main Entry) and North Entry (Coffee Cafe<br />
Entry) <strong>Library</strong> Information Commons<br />
New Periodicals<br />
Reference Area<br />
<strong>Library</strong> Technical Services<br />
Coffee Shop<br />
Group Study Rooms<br />
<strong>Library</strong> Collection and Study Area A<br />
Computer Lab<br />
Computing Services<br />
<strong>College</strong> Archives<br />
Hawaiian Room<br />
West Entry (upper level grade access to the west)<br />
Primary <strong>Library</strong> Collection Area<br />
<strong>Library</strong> Study Area B<br />
The Learning Center (TLC)<br />
Large Conference Room<br />
Instructional Media Services<br />
Electronic Classroom<br />
Duplicating and Copy Center<br />
Group Study Room<br />
Service Entry and Dock to the west<br />
LRC Administration<br />
Mechanical space<br />
An important vertical volume and visual connector will<br />
be the two-story atrium. A stonewall that begins at the<br />
north entry and continues through the facility to the<br />
south end is located to the west of the atrium. This<br />
wall provides key way finding by emphasis of the northsouth<br />
axis within the building. This warm-toned and<br />
textured wall, perhaps built of local stone, provides<br />
opportunities for art display and locally rich historic<br />
symbolism, as well as a great setting for the Hawaiian<br />
Room.<br />
Friendly, indirect natural lighting minimizes the need for<br />
artificial light. Natural light will enter the building<br />
through large energy-conscious glass windows utilizing<br />
light deflecting mullions and automatic shades.<br />
Translucent gabled-skylights, placed along the top roof<br />
ridge, and clerestory windows along and under the<br />
eaves of the east-west raised roof will provide diffused,<br />
University of Hawaii <strong>Community</strong> <strong>College</strong>s April 2004<br />
Project No. CC-02-6188<br />
III-15
The Learning Resource Center at <strong>Windward</strong> <strong>Community</strong> <strong>College</strong><br />
PROJECT DEVELOPMENT REPORT<br />
natural light throughout. Photosensitive controls on<br />
artificial lights will turn off electric lights when not<br />
needed, thereby reducing heat gain. Mechanical<br />
spaces are strategically located within the facility floor<br />
plan for efficient and easy airflow access to all spaces.<br />
The exterior building form and massing for <strong>Windward</strong><br />
<strong>Community</strong> <strong>College</strong> is designed to be a pleasant<br />
human scale, a friendly neighborhood image, and a<br />
contextual tropical architectural vocabulary. Matching<br />
clay tile roofs, off-white stucco walls, and sloped-roof<br />
arcades will be the primary design components that<br />
define the architecture of the new building.<br />
Under the protective banyan trees, the LRC will bring<br />
dynamic new life and architectural dignity to the<br />
campus.<br />
a. Building Massing and Form<br />
The Learning Resource Center facility building massing is an<br />
outgrowth of the function of the building as well as a response to<br />
the site parameters and spatial requirements. As mentioned<br />
above, the building form responds to the major and minor axes as<br />
well as the grades between Hale La’akea and the Hale<br />
Mana’opono. The architectural functions within the building are<br />
expressed in the building massing. The western portion of the<br />
building houses the “back of the house” functions used by the staff<br />
of The Learning Resource Center while the eastern portion relates<br />
to the stack areas and other areas used by the students on a daily<br />
basis.<br />
Roof Design shall conform to hip or gable styles currently used on<br />
campus. Roof slopes shall be 3:12 to 6:12 using S-shape clay tile<br />
system. The design concept uses varying roof and wall planes to<br />
optimize scale and massing with respect to the site.<br />
Balconies/arcades are selectively integrated to further address<br />
scale and massing.<br />
b. Architectural Elements<br />
View Corridors:<br />
The exterior view corridors that were taken into consideration in<br />
the design were: 1) the view down the major mall axis. The<br />
building responds to this view corridor by aligning the wall<br />
separating the two major building functions along that line. The<br />
University of Hawaii <strong>Community</strong> <strong>College</strong>s April 2004<br />
Project No. CC-02-6188<br />
III-16
The Learning Resource Center at <strong>Windward</strong> <strong>Community</strong> <strong>College</strong><br />
PROJECT DEVELOPMENT REPORT<br />
view corridor along that axis is emphasized by the structural and<br />
sculptural wall that runs the full length of the building and<br />
continues past the outer walls. The entry of the building to the<br />
north is along this wall. The users entering the building will be<br />
able to see down this view corridor to the sculpture in the center of<br />
the mall. They will also “feel” the axis of the entire mall. 2) The<br />
view to the Koolau Mountains from the west entry point. The<br />
building takes advantage of the view to the Koolau Mountains<br />
between the two banyan trees just west of the west entrance at<br />
the Second Floor. 3) The view of the existing historic architecture<br />
to the east. The view of Hale Mana‘opono to the east is in direct<br />
alignment with The Learning Resource Center entrance. This<br />
view is along the previously mentioned minor axis.<br />
Architectural Style:<br />
The architectural style from the exterior blends with the existing<br />
campus architecture and could be considered Spanish<br />
Mediterranean in character. The arched openings, hip roofs with<br />
clay tile and the covered arcades or colonnaded walkways are<br />
detail elements of the existing architecture that is integrated into<br />
The Learning Resource Center. The two-story profile from each<br />
of the facades also creates a unity with the existing architecture.<br />
The building massing emphasizes horizontal elements instead of<br />
vertical elements as established by the <strong>Windward</strong> <strong>Community</strong><br />
<strong>College</strong> Urban Design Plan and Design Guidelines 1994. The<br />
building elevations are articulated with changes in planes and<br />
vertical elements, again as requested by the aforementioned<br />
guidelines. The roof design generally conforms to the hip or gable<br />
styles currently found on campus. The main east and west<br />
entrances were emphasized as requested in the design<br />
guidelines.<br />
Building Materials:<br />
The stucco walls and clay tile roofs create a strong sense of visual<br />
unity for the campus. The metal roofing, flashing, gutters and<br />
downspouts will be developed in later design phases. The flat<br />
roofing materials shall be non-reflective and non-glare producing<br />
earth tone colors as requested. The main entrances are<br />
anticipated to be aluminum and glass systems similar to the newer<br />
buildings on campus.<br />
University of Hawaii <strong>Community</strong> <strong>College</strong>s April 2004<br />
Project No. CC-02-6188<br />
III-17
The Learning Resource Center at <strong>Windward</strong> <strong>Community</strong> <strong>College</strong><br />
PROJECT DEVELOPMENT REPORT<br />
Fenestration:<br />
The arched openings, hip roofs with clay tile and the covered<br />
arcades or colonnaded walkways are detail elements of the<br />
existing architecture that are incorporated in The Learning<br />
Resource Center.<br />
Colors:<br />
The exterior wall colors shall be off-white/beige to match the<br />
existing buildings. The paint finishes will conform to the design<br />
guidelines.<br />
The glass on the exterior shall be the blue/green tinted glass as<br />
specified in the Design Guidelines.<br />
The flat roofing materials shall be non-reflective and non-glare<br />
producing earth tone colors as requested<br />
Sense of Place:<br />
The sense of place for the building will be captured by its strategic<br />
location within the campus mall location. The facility will act as a<br />
focal building within the campus master plan yet will blend with the<br />
existing massing, fenestration, materials, and color of the existing<br />
architecture.<br />
The interior will also provide a sense of place with the central<br />
atrium at the juncture of the main entrance and the linear open<br />
space within the building. This space will house the Information<br />
Commons and define the hub of activity of the complex. The<br />
social sense of place will be further defined by the strategic<br />
placement of the coffee shop at the north end of the facility<br />
overlooking the proposed amphitheater area to the north.<br />
c. Architectural <strong>Concept</strong> Plans<br />
H. Environmental Analysis<br />
The architectural concept for The Learning Resource Center is<br />
represented by Figures III.2.1 – III.2.11, inclusive.<br />
1. Description of technical, economic, social and environmental<br />
characteristics of the new facility.<br />
The building location for The Learning Resource Center works well within<br />
the campus master plan because the proposed building site is centrally<br />
University of Hawaii <strong>Community</strong> <strong>College</strong>s April 2004<br />
Project No. CC-02-6188<br />
III-18
The Learning Resource Center at <strong>Windward</strong> <strong>Community</strong> <strong>College</strong><br />
PROJECT DEVELOPMENT REPORT<br />
located within the most active area of the campus. Students will be able<br />
to quickly get to the facility for studying between classes.<br />
This northwest end of the major open space could potentially function as<br />
the center of activity for the campus. The facility just fits within the large<br />
banyan and monkey pod tree canopies. The large open space to the<br />
northwest of the facility between the Humanities Building (Hale<br />
Palanakila) and the Science Building (Hale ‘Imiloa) acts as one of the<br />
main entrances to the facility. The proposed walkway system has been<br />
integrated with the site development of The Learning Resource Center<br />
and is intended to conform to the campus master plan.<br />
The scale of the facility, articulation of the façade, and the choice of<br />
materials are intended to reflect the Spanish-Mediterranean architecture<br />
and respect the rural and pastoral feeling unique to the campus.<br />
Even in difficult economic periods, many universities commit to library<br />
facilities improvements and expansions and view their new and expanded<br />
libraries as “signature” campus buildings, critical to attracting and<br />
retaining excellent students and facility.<br />
The 81,793 gross square foot new Learning Resource Center for<br />
<strong>Windward</strong> <strong>Community</strong> <strong>College</strong> will be a state-of-the-art library with<br />
learning center, instructional media services, and computing services that<br />
are inspiring, functional and cost effective. The focus will be to provide<br />
the appropriate technology for a community college that will inspire the<br />
students and still be cost sensitive.<br />
2. Summarization of the affected environment, including suitable and<br />
adequate location and site maps.<br />
Every effort has been made to integrate the facility with its environment.<br />
The use of tile roofs, arches, and stucco finish will help to make the<br />
facility more congruous within its campus environment. The facility will<br />
make good use of the ocean breezes, natural day lighting and selected<br />
views of the Koolau’s. The facility is positioned within the large Banyan<br />
tree canopies and will act as a transitional element between the<br />
Humanities Building (Hale Palanakila) and the Science Facility (Hale<br />
‘Imiloa).<br />
The minor open space that is defined by these three buildings has the<br />
potential to be a focal activity area and to create the social synergy<br />
between activities and uses associated with Hale Palanakila, Hale ‘Imiloa<br />
and The Learning Resource Center.<br />
University of Hawaii <strong>Community</strong> <strong>College</strong>s April 2004<br />
Project No. CC-02-6188<br />
III-19
The Learning Resource Center at <strong>Windward</strong> <strong>Community</strong> <strong>College</strong><br />
PROJECT DEVELOPMENT REPORT<br />
3. Identification and summarization of major impacts and alternatives<br />
considered, if any.<br />
The site analysis for the facility defined critical site considerations that<br />
were integrated into the final site solution. Two site location alternatives<br />
were studied: 1) at the southeast of the major open space and 2) at the<br />
northwest of the major open space. The northwest site was designated in<br />
the master plan and selected as the site for the following reasons: a) it<br />
conformed to the original site proposed in the master plan, b) it is close to<br />
the concentration of student activity and could potentially provide an<br />
activity node for the north end of campus, and c) the other site was<br />
considered too remote for ease of circulation and access.<br />
<strong>Development</strong> of proposed mitigation measures, if any. Two (2) other site<br />
factors were important and required mitigation: 1) the fact of having to<br />
remove the existing building (Hale Manaleo) on the site. After conferring<br />
with the State Historical Society, the appropriate mitigation for this<br />
building removal from the point of view of the state Historical Society was<br />
the desire to renovate the three existing facilities around Hale Manaleo:<br />
A) Hale Mana‘opono, B) Hale La‘akea, and C) Hale No‘eau. 2) The<br />
second stakeholder issue was related to the trees that fall within the<br />
proposed building footprint. These trees within the footprint of the<br />
proposed Learning Resource Center will be removed: two palm trees, and<br />
two clusters of Hong Kong orchids (three on the makai side and two on<br />
the mauka side).<br />
4. The following major site factors were analyzed with respect to the<br />
Learning Resource Center: 1) open space, 2) pedestrian circulation,<br />
3) vehicular circulation, 4) and vegetation.<br />
a. Open Space<br />
The major open space in conjunction with the existing and<br />
planned location of buildings around the mall establishes a strong<br />
visual identity for the campus. The location of The Learning<br />
Resource Center acknowledges the suggested major and minor<br />
axes with respect to the open space and the existing buildings and<br />
conforms to the site designated in the Plan Review Use/Master<br />
Plan documents for <strong>Windward</strong> <strong>Community</strong> <strong>College</strong>.<br />
b. Pedestrian Circulation<br />
Important to any master plan are the pedestrian, vehicular and<br />
service circulation systems. The design team continues to work<br />
with the development of pedestrian circulation consistent with the<br />
master plan.<br />
University of Hawaii <strong>Community</strong> <strong>College</strong>s April 2004<br />
Project No. CC-02-6188<br />
III-20
The Learning Resource Center at <strong>Windward</strong> <strong>Community</strong> <strong>College</strong><br />
PROJECT DEVELOPMENT REPORT<br />
c. Vehicular Circulation<br />
The vehicular master plan centers on the loop road system.<br />
Vehicles, service and fire access come off of the loop system and<br />
penetrates only a short way in towards the major open space and<br />
typically adjacent to a building. The vehicular, service, and fire<br />
access functions would be integrated to minimize the impact on<br />
the campus. The access for vehicles, service and fire access will<br />
be short cul-de-sacs, specific, and adjacent to a building.<br />
d. Vegetation<br />
The placement, massing and building form respects the existing<br />
banyan trees to the south and west and the monkey pod tree to<br />
the south east of The Learning Resource Center. The<br />
development of the design concept will continue to respect the<br />
preservation of banyan trees as prescribed in the PRU resolution<br />
and the master plan documents. Any need to remove other trees,<br />
or landscaping will be supplemented either by relocation/<br />
replanting or with the inclusion of new trees.<br />
5. The preparation and determination of findings and reasons<br />
supporting determination.<br />
The facility is located in the prescribed location shown in the existing<br />
master plan and the approved PRU resolution by the City and County of<br />
Honolulu. The primary site factor regarding the placement of the facility<br />
was the close proximity to the greatest pedestrian need – the northwest<br />
portion of the mall. The Humanities Building (Hale Palanakila) and the<br />
Science Building (Hale ‘Imiloa) generate the most pedestrian traffic. The<br />
students can quickly go from their classrooms to the library all close<br />
together in the northwest portion of the mall.<br />
The architectural character will conform to the Spanish-Mediterranean<br />
architecture that is well established for the campus with the inclusion of<br />
the prescribed roof tiles, exterior wall finishes, colors and textures. Also<br />
incorporated are exterior arcades, variation in roof planes and articulated<br />
facades to optimize the scale and massing of the building.<br />
The Environmental Analysis was prepared to consolidate related data into<br />
a comprehensive document that clearly defines the analysis, constraints,<br />
assets and outcomes related to the development of The Learning<br />
Resource Center.<br />
University of Hawaii <strong>Community</strong> <strong>College</strong>s April 2004<br />
Project No. CC-02-6188<br />
III-21
The Learning Resource Center at <strong>Windward</strong> <strong>Community</strong> <strong>College</strong><br />
PROJECT DEVELOPMENT REPORT<br />
IV.<br />
PRELIMINARY ENGINEERING DESIGN CRITERIA<br />
A. Introduction<br />
The preliminary engineering design criteria is intended to integrate site and utility<br />
systems improvements on a conceptual basis. Similarly, design criteria is<br />
introduced for structural, landscape, mechanical and electrical engineering to<br />
supplement the proposed architectural design concept for the Learning Resource<br />
Center.<br />
B. Summary Of Existing Site Conditions And Utilities<br />
1. Overview<br />
This section covers civil engineering criteria related to parking, circulation,<br />
handicap accessibility, site grading, water service, sewer service, and<br />
storm drainage. The sustainable attributes for the civil engineering are<br />
described under Section V.<br />
a. Parking: (4) handicap spaces and (75) regular spaces are<br />
provided plus (18) relocated handicapped parking spaces.<br />
b. Circulation: Access to parking is provided from the Banyan Drive<br />
loop road system. The fire access is provided from the vehicular<br />
access south of the Humanities Building, the west portion of Ilima<br />
Way (reconfigured), and the east portion of Ilima Way<br />
(reconfigured).<br />
c. Accessibility: Handicap accessibility is provided from the parking<br />
to the building. An accessible route is also provided to the front of<br />
the building for drop off and entrance into the building via the fire<br />
access area to the southeast. Accessible routes from the green<br />
mall area walkway system are also provided.<br />
d. Site Grading: The First Floor of the Learning Resource Center is<br />
approximately at elevation 228; the Second Floor at elevation 242.<br />
The grading will provide for access from the west at the Second<br />
Floor and from the east at the First Floor. The grading around the<br />
building will be adjusted to meet the aforementioned criteria and<br />
accommodate handicap access to both entry points as well as the<br />
entrance to the north. The north portion of the site is stepped to<br />
provide amphitheater seating to create a public area that would be<br />
contiguous with the Planetarium and the Arts/Humanities Building.<br />
e. Geotechnical Survey: To be furnished by the owner.<br />
University of Hawaii <strong>Community</strong> <strong>College</strong>s April 2004<br />
Project No. CC-02-6188<br />
IV-1
The Learning Resource Center at <strong>Windward</strong> <strong>Community</strong> <strong>College</strong><br />
PROJECT DEVELOPMENT REPORT<br />
f. Water Service: The water system will service the proposed<br />
Learning Resource Center from the 6” water main located near<br />
Ilima Way. The new facility will contain a fire sprinkler system<br />
similar to other buildings on campus since the water pressure is<br />
not 2000 psi. A sustainable water service system approach will<br />
reduce the potable water demand.<br />
g. Sewer System: The sewer system is in the process of being<br />
upgraded building by building. The existing sewer system needs<br />
maintenance due to settlement and root problems. The<br />
Department of Planning and Permitting (DPP), Site <strong>Development</strong><br />
Division, confirmed that the moratorium on plumbing fixture units<br />
imposed by 92 / PRU-3, condition 4, limiting development to a<br />
one-to-one replacement until the Kaneohe Sewage Treatment<br />
Plant is expanded, was lifted in the mid 1990s. DPP, Site<br />
<strong>Development</strong> Division will determine if the number of plumbing<br />
fixtures is within the sewer system capacity for each project on a<br />
case-by-case basis. A sustainable storm sewer system approach<br />
will reduce the flow rate.<br />
h. Storm Drainage System: The drainage anticipated for the<br />
Learning Resource Center will utilize drainage lines on either side<br />
of the site. There is a 36” drainage main to the north-northwest<br />
and a 24” drainage main to the south and southeast. Both of<br />
these mains flow to the east where they both have outlet<br />
structures that flow into an open drainage ditch. A sustainable<br />
storm drainage approach will reduce the storm drainage off of the<br />
site.<br />
2. Parking, Circulation and Accessibility<br />
a. Parking:<br />
1) Handicap Parking: There are four (4) handicap parking<br />
spaces provided for the facility. The proposed design will<br />
meet the current state and federal requirements related to<br />
the Americans with Disabilities Act (ADA) Accessibility<br />
Guidelines for Buildings and Facilities and the Architectural<br />
Barriers Act (ABA).<br />
2) Regular Parking: A new parking lot to include 80 parking<br />
spaces will be located directly across Hale Mana‘opono<br />
with access from Banyan Drive. The spaces will be 8’ – 6”<br />
x 22’ – 0”.<br />
3) Loading Areas: The loading area for the facility is located<br />
in the southwest portion of the facility. There are two (2)<br />
University of Hawaii <strong>Community</strong> <strong>College</strong>s April 2004<br />
Project No. CC-02-6188<br />
IV-2
The Learning Resource Center at <strong>Windward</strong> <strong>Community</strong> <strong>College</strong><br />
PROJECT DEVELOPMENT REPORT<br />
b. Circulation:<br />
loading areas for the facility. One space needs to be 12’<br />
wide by x 35’ long with a vertical clearance of at least 14’.<br />
The second loading area shall have minimum dimensions<br />
of 8’-6” wide by 19’ long with a vertical clearance of at least<br />
10 feet.<br />
1) Pedestrian Circulation: Pedestrian circulation to the site is<br />
from the parking via the sidewalk that is parallel to Banyan<br />
Drive and will be integrated with the overall campus<br />
walkway system.<br />
2) Vehicular Circulation: The vehicular circulation is primarily<br />
via the loop roadway system (Banyan Drive, Honeysuckle<br />
Road, and Maile Way). Vehicular access to the parking<br />
will be via the loop road network.<br />
3) Service Circulation: The service circulation to the building<br />
is via the west end of the modified Ilima Way. This access<br />
also doubles as a fire access approach to the building.<br />
4) Fire Access Circulation: The fire access to the building is<br />
via the (a) existing fire access south of the Humanities<br />
Building, (b) modified west portion of Ilima Way, and (c)<br />
modified east portion of Ilima Way.<br />
c. Accessibility:<br />
1) Handicap Accessibility from Parking: There are four (4)<br />
handicap accessible spaces for the Learning Resource<br />
Center located in the parking area east of Banyan Drive.<br />
There are (8) existing Handicap Accessible parking spaces<br />
that have been relocated from Ilima Way.<br />
2) Handicap Accessibility between Buildings: The following<br />
are handicap accessible routes adjacent to the Learning<br />
Resource Center: a) the sidewalk from the Student Center<br />
that is located east of Hale No‘eau and Hale La‘akea, b)<br />
the sidewalk that connects Hale La‘akea and the proposed<br />
Learning Resource Center, c) the sidewalk connecting<br />
Hale Palanakila and The Learning Resource Center, d) the<br />
sidewalk west of Hale Na‘auao and Hale Mana‘opono, e)<br />
The Learning Resource Center entrance walkway to the<br />
east of the building, f) the walkway running east and west<br />
between Hale Mana‘opono and Hale ‘Imiloa, and the<br />
University of Hawaii <strong>Community</strong> <strong>College</strong>s April 2004<br />
Project No. CC-02-6188<br />
IV-3
The Learning Resource Center at <strong>Windward</strong> <strong>Community</strong> <strong>College</strong><br />
PROJECT DEVELOPMENT REPORT<br />
3. Site Grading<br />
covered walkway from the vehicle dropoff area to the north<br />
of Hale Hokulani to Hale ‘Imiloa.<br />
3) See Figure IV-2.<br />
a. Existing Grading:<br />
The existing grading of the western portion of the proposed<br />
Learning Resource Center slopes from a high point near the Hale<br />
La‘akea building at the elevation of approximately 250 to the<br />
Existing Hale Manaleo building elevation of approximately 236.<br />
The existing grading continues to slope downward from the Hale<br />
Manaleo to both the Hale Mana‘opono and the Science Facility<br />
(Hale ‘Imiloa) at approximately 220. The site also slopes down to<br />
the Hale Hokulani elevation of approximately 226.<br />
b. Proposed Grading:<br />
The proposed first floor of The Learning Resource Center is at<br />
approximately 228. The second floor elevation is at approximately<br />
elevation 242. The western face of the building would have the<br />
exterior grade at approximately 241. This would facilitate the<br />
removal of ground water from the area around the building. This<br />
configuration would reduce the potential adverse affects of water<br />
against the west wall of the lowest floor. The grading of the<br />
southeastern side of the facility needs to accommodate the<br />
pedestrian walkway as well as the banyan tree root structure.<br />
Due to the extensive change in grade, the handicap accessibility<br />
will need to be handled in the eastern, western and northern<br />
portions of the facility.<br />
The northwestern portion of the site has been configured to<br />
accommodate an outdoor seating area/amphitheater between The<br />
Learning Resource Center and the Planetarium (Hale Hokulani).<br />
The stepped seating area permits the transition from the grade of<br />
the north entrance to The Learning Resource Center at<br />
approximately elevation 228 to the grade southeast outside of the<br />
Planetarium (Hale Hokulani) at approximately elevation 224.<br />
4. Geotechnical Survey<br />
A geotechnical survey of the site is typically furnished by the Owner and<br />
is required to define the subsurface conditions associated with The<br />
Learning Resource Center. The structural engineer should be consulted<br />
University of Hawaii <strong>Community</strong> <strong>College</strong>s April 2004<br />
Project No. CC-02-6188<br />
IV-4
The Learning Resource Center at <strong>Windward</strong> <strong>Community</strong> <strong>College</strong><br />
PROJECT DEVELOPMENT REPORT<br />
regarding the quantity and location of soil borings required for the<br />
proposed structural system. The geotechnical data should be available at<br />
the start of the design process.<br />
5. Water System<br />
a. Existing Water System:<br />
1) Current Water System Description: Due to the age and<br />
high maintenance of the system, the applicant proposes to<br />
develop a new system for installation throughout the<br />
campus. Water is supplied by the Board of Water Supply<br />
(BWS). The applicant has obtained approval from the State<br />
Department of Land and Natural Resources for a water<br />
allocation of 120,000 gallons per day (gpd).<br />
Director’s Report, PRU WCC 1994<br />
2) Existing Condition: The existing water distribution system<br />
to the campus buildings for the most part has been up<br />
graded. The piping within the buildings is older and has<br />
not been replaced.<br />
3) Design Rate of Use: 4,000 gallons per acre = 285,000<br />
gallons per day<br />
WCC MPR 1989 Page 72<br />
4) Calculated Use by Function: 2000 students x 60 gallons<br />
per day = 120,000 gallons per day. WCC has received<br />
approval to use 120,000 gallons per day (gpd) based on<br />
projected demand. WCC submitted a water master plan in<br />
August 1993.<br />
WCC MPR 1989 Page 71<br />
5) Fire Department Water Flow Rate: The Fire Department of<br />
the City and County of Honolulu requires a flow rate of<br />
2000 gallons per minute (gpm) with a 20 pounds per<br />
square inch (psi) residual pressure. The present system is<br />
only capable of providing 1,100 gallons per minute (gpm).<br />
The Fire Department responded to the applicant’s proposal<br />
to install sprinklers in combination with fire hydrants by<br />
stating “…we have no objections to the proposal providing<br />
that the existing 1,100 gallons per day (gpd) water<br />
availability is supplemented with a combined building<br />
sprinkler and hydrant system that is in compliance with<br />
University of Hawaii <strong>Community</strong> <strong>College</strong>s April 2004<br />
Project No. CC-02-6188<br />
IV-5
The Learning Resource Center at <strong>Windward</strong> <strong>Community</strong> <strong>College</strong><br />
PROJECT DEVELOPMENT REPORT<br />
National Fire Protection Association13, Uniform Fire Code<br />
Article 10 and Board of Water Supply Standards.”<br />
Directors Report PRU WCC 1994 page 22<br />
6) Water System Construction (Science Facility):<br />
The water service that was part of the Science Facility<br />
(Hale ‘Imiloa) project consisted of 8” service in the adjacent<br />
Banyan Drive and the roadway to the Banyan Drive portion<br />
northwest of the Science Facility. The construction also<br />
included an 8” service to the new facility. The water<br />
service construction included a connection to Board of<br />
Water Supply (BWS) 16” main. The connection also<br />
included a pressure-reducing valve near the connection to<br />
the BWS main.<br />
7) Water System Construction (Humanities Building): In 1996<br />
the water service was extended from the 8” service that<br />
was constructed prior to the juncture of Banyan Drive and<br />
Honeysuckle Road and prior to the Science Facility.<br />
8) Water System Construction (Student Center): The water<br />
main construction in the area of the Student Center (Hale<br />
Akoakoa) was completed in the 2002 time frame. The 8”<br />
water main was constructed along Honeysuckle Road,<br />
Maile Way, and Banyan Drive (near Hale Kuhina and Hale<br />
Alakai). This work included the abandonment of a 4” water<br />
line near Hale Kuhina, a 6” water line near Hale Alakai, 4”<br />
water line along Maile Way, a 4” water line parallel to<br />
Honeysuckle, a 3” water line near Hale La‘Akea, a 4” water<br />
line in Ilima Way, and a 2” water line Hale Mana‘opono.<br />
9) Water System Upgrade (Campus-wide 2002 - 2003): The<br />
water service between buildings has been upgraded.<br />
Currently the water piping between buildings is newer<br />
system piping. The older system that was in need of repair<br />
has been abandoned or replaced.<br />
Refer to Engineering Solutions Inc. drawings T-1 to T-4<br />
and C-1 to C-12 dated 4-19-2002 for the extensive system<br />
upgrades.<br />
b. Proposed Water System (The Learning Resource Center)<br />
1) Proposed Water System Demand<br />
The demand is projected for the campus by using the<br />
number of students at the facility.<br />
University of Hawaii <strong>Community</strong> <strong>College</strong>s April 2004<br />
Project No. CC-02-6188<br />
IV-6
The Learning Resource Center at <strong>Windward</strong> <strong>Community</strong> <strong>College</strong><br />
PROJECT DEVELOPMENT REPORT<br />
2,000 students x 60 gallons per day = 120,000 gallons per<br />
day.<br />
WCC has received approval to use 120,000 gallons per<br />
day (gpd) based on projected demand. Existing<br />
Reservoirs: 100,000 gallons. *<br />
Water Demand for The Learning Resource Center<br />
calculation is as follows:<br />
4,000 gallons per acre or 60 gallons per person.**<br />
Site 1.63 acres x 4,000 gal per acre = 6,520 gallons per<br />
day. 60 gallons per person x 968 people = 34,048 gallons<br />
Say 34,000.<br />
It is anticipated that the actual water demand for The<br />
Learning Resource Center may be reduced by using<br />
LEED® sustainable design techniques. Refer to LEED®<br />
Water Efficiency Credit 3 Water Use Reduction, Section V.<br />
Demand Factor: 1.5 x Average day*<br />
1.5 x 34,000 gallons per day = 51,000 gallons per day =<br />
0.590 gps<br />
Impact to the Existing System: 8” diameter minimum for<br />
the fire loop. Service lateral to the building will likely be 3”<br />
or 4”.<br />
* Water System Design Criteria 2002<br />
** Information from WCC Master Plan 1989<br />
2) Proposed Water System<br />
The water system will service The Learning Resource<br />
Center from the 6” water main located near Ilima Way.<br />
The new facility will contain a fire sprinkler system similar<br />
to other buildings on campus since the water pressure is<br />
below 2000 psi. This provision has been acceptable to the<br />
approving agencies. Since the proposed Learning<br />
Resource Center footprint will be over the existing water<br />
lines, the water lines need to be rerouted. It is<br />
recommended that the new water service be a 3” to 4”<br />
lateral. Any existing older water lines that are outside of<br />
the building and will feed The Learning Resource Center<br />
should be replaced with new lines. See Figure IV.3.<br />
University of Hawaii <strong>Community</strong> <strong>College</strong>s April 2004<br />
Project No. CC-02-6188<br />
IV-7
The Learning Resource Center at <strong>Windward</strong> <strong>Community</strong> <strong>College</strong><br />
PROJECT DEVELOPMENT REPORT<br />
6. Wastewater System<br />
a. Existing Sewer System:<br />
1) Current Sewer System Description: The sewer system is<br />
in the process of being upgraded building by building. The<br />
existing sewer system needs maintenance due to<br />
settlement and root problems.<br />
2) Capacity: Mr. Nishimura, Department of Planning and<br />
Permitting (DPP), Site <strong>Development</strong> Division, confirmed<br />
that the moratorium on plumbing fixture units imposed by<br />
92 / PRU-3, condition 4, i.e. limiting development to a oneto-one<br />
replacement until the Kaneohe Sewage Treatment<br />
Plant is expanded, was lifted in the mid 1990s. DPP, Site<br />
<strong>Development</strong> Division will determine if the number of<br />
plumbing fixtures is within the sewer system capacity for<br />
each project on a case-by-case basis.<br />
DPP confirmed that the master application form may be<br />
downloaded from their website, i.e., Site <strong>Development</strong><br />
Division, Master Application form, sewer portion. If the<br />
proposed project’s plumbing fixture unit count exceeds the<br />
sewer system’s capacity, DPP will work with the applicant<br />
on a solution to meet capacity.<br />
3) Existing Condition: “The applicant proposes to phase the<br />
installation of a new system of sewer lines throughout the<br />
campus for connection to the City sewer system.”<br />
Director’s Report, PRU WCC 1994, page 22.<br />
“The current system maintenance staff has indicated that<br />
the existing system must be constantly maintained, with<br />
settlement and root problems being common. Based on<br />
the high maintenance requirements and age of the system,<br />
installation of new sewer lines and laterals throughout the<br />
campus is recommended. The existing lines can be<br />
abandoned in-place, except where they interfere with new<br />
construction. The existing sanitary manholes should be<br />
removed to approximately two feet below grade and<br />
backfilled, with complete removal in new facility locations.”<br />
Plan Review Use for a Five Year Master Plan for the University of<br />
Hawaii, <strong>Windward</strong> <strong>Community</strong> <strong>College</strong> 1992<br />
University of Hawaii <strong>Community</strong> <strong>College</strong>s April 2004<br />
Project No. CC-02-6188<br />
IV-8
The Learning Resource Center at <strong>Windward</strong> <strong>Community</strong> <strong>College</strong><br />
PROJECT DEVELOPMENT REPORT<br />
4) Master Plan <strong>Concept</strong>: The plan is to have minimum sewer<br />
size of 6” for all lines other than building laterals.<br />
5) Sewer Construction (Science Facility): At the Science<br />
Facility (Hale ‘Imiloa) a 4” lateral was connected to a new<br />
6” which connects to sewer lines leading to the main sewer<br />
line in Kea‘ahala Road<br />
6) Sewer Construction (Humanities Building): At the<br />
Humanities Building (Hale Palanakila) a 6” lateral sewer<br />
service that turns into an 8” line connecting to another 8”<br />
main along Ilima Way. The 8” main flows makai and<br />
eventually to the sewer mains in Kea‘ahala Road.<br />
7) Sewer Construction (Student Center): At the Student<br />
Center (Hale Akoakoa) a number of 6” laterals were<br />
connected to an 8” sewer line that flows toward the<br />
Humanities Building (Hale Palanakila). The 8” sewer main<br />
located in the green mall area is flowing toward Diamond<br />
Head.<br />
b. Proposed Sewer System (Learning Resource Center):<br />
1) Sewer System Demand:<br />
Average Wastewater Flow: 25 gal per capita per day<br />
(3)*for schools 25 gpcd x 568 pcd = 14,200 gallons per<br />
day.<br />
Maximum Wastewater Flow: Flow factor = 5 (3)*<br />
5 x 14,200 = 71,000 gal per day<br />
Dry Weather Infiltration: 5 gpcd for above water table (3)*<br />
5 gpcd x 568 p = 2,840 gpd<br />
Design Average Flow: 14,200 gpd + 2,840 gpd = 17,040 gpd<br />
71,000 gpd + 2840 gpd = 73,840 say 74,000 gpd<br />
University of Hawaii <strong>Community</strong> <strong>College</strong>s April 2004<br />
Project No. CC-02-6188<br />
IV-9
The Learning Resource Center at <strong>Windward</strong> <strong>Community</strong> <strong>College</strong><br />
PROJECT DEVELOPMENT REPORT<br />
Wet Weather Infiltration: 1290 gal per acre per day<br />
1290 gad x 1.630 acre = 2,103 gpd<br />
Design Peak Flow: 73,840 gpd + 2038 gpd = 75,878 gpd<br />
Say 76,000 gpd Q=0.88 gals /sec<br />
It is anticipated that the actual sewer system demand for<br />
The Learning Resource Center may be reduced by using<br />
LEED® sustainable design techniques. Refer to LEED®<br />
Water Efficiency Credit 2, Innovative Waste Water<br />
Technologies, Section V.<br />
2) Proposed Sewer Construction (Learning Resource<br />
Center): The sewer connection for The Learning Resource<br />
Center will connect to the existing 8” sewer located<br />
adjacent to Ilima Way. The 8” main flows makai and<br />
eventually to the sewer mains in Kea‘ahala Road.<br />
7. Storm Drainage Sytem<br />
Since a portion of the existing 8” sewer is would be within<br />
the footprint of the proposed Learning Resource Center, a<br />
portion the lines located in Ilima Way proposed for<br />
rerouting to the southeast around the existing Banyan<br />
trees. A portion of the existing 6” sewer serving the<br />
Humanities Building (Hale Palanakila) will need to be<br />
relocated since the existing line falls within the footprint of<br />
the proposed Learning Resource Center. See Figure<br />
IV.4.<br />
a. Existing Storm Drainage System:<br />
1) Current Storm Drainage System Description: “The existing<br />
storm drainage system is composed of a combination of<br />
open ditches and underground drain lines. Most of the<br />
Campus is drained by numerous inlets which intercept runoff<br />
along the roadway area. This runoff is then piped through<br />
the drainage system and outlet along the outskirts of the<br />
Campus property. Toward the northeastern side of the<br />
campus, there is an open drainage ditch which serves as the<br />
main drainage system for that side of the campus. All of the<br />
drainage from WCC eventually goes into two well-defined<br />
natural drainage ditches. These drainage ditches run along<br />
both sides of Kea‘ahala Road.”<br />
Plan Review Use for a Five Year Master Plan for the University of Hawaii,<br />
<strong>Windward</strong> <strong>Community</strong> <strong>College</strong> 1992 page 37.<br />
University of Hawaii <strong>Community</strong> <strong>College</strong>s April 2004<br />
Project No. CC-02-6188<br />
IV-10
The Learning Resource Center at <strong>Windward</strong> <strong>Community</strong> <strong>College</strong><br />
PROJECT DEVELOPMENT REPORT<br />
2) Capacity: “No changes to the existing storm water drainage<br />
system are proposed. Runoff will be intercepted through<br />
inlets within paved areas, piped to the outskirts of the<br />
property for discharge into the City storm drainage system.”<br />
“Renovation and development of WCC will increase peak<br />
runoff produced on the campus. The increased peak runoff<br />
can be detained on-site in open areas located around the<br />
campus and outlet during off-peak times.”<br />
Plan Review Use for a Five Year Master Plan for the University of Hawaii,<br />
<strong>Windward</strong> <strong>Community</strong> <strong>College</strong> 1992, page 37.<br />
3) Master Plan <strong>Concept</strong>: “The proposed storm drainage system<br />
will continue the same concept, which services the existing<br />
campus. Runoff will be intercepted thru inlets within paved<br />
areas, piped to the outskirts of the property and outlet to<br />
match the existing drainage outlet locations. “<br />
Plan Review Use for a FiveYear Master Plan for the University of Hawaii,<br />
<strong>Windward</strong> <strong>Community</strong> <strong>College</strong> 1992 page 37<br />
4) Storm Drainage Construction (Science Facility): During the<br />
construction of the Science Building (Hale ‘Imiloa) the open<br />
drainage ditch was developed into drain inlets and 12” to 36”<br />
drainage-lines on the mauka and Diamond Head sides of the<br />
Science Center. There were 11 area drainage catch basins<br />
installed as well as a drainage inlet and an outlet structures.<br />
5) Storm Drainage Construction (Humanities Building): The<br />
storm drainage system to the southeast of the Humanities<br />
Building (Hale Palanakila) consists of 24”, 30” and 36” storm<br />
drainage lines connecting to the 36” Storm Drainage Main<br />
that crosses Banyan Drive. There are also storm drainage<br />
lines that cross Banyan Drive adjacent to the Humanities<br />
Building and proceed to the north-northwest to a drainage<br />
outlet structure located beyond the parking structure.<br />
6) Storm Drainage Construction (Student Center): The storm<br />
drainage system for the Student Center (Hale Akoakoa)<br />
consists of 8”, 18”, 24”, and 30” drainage lines connecting to<br />
the 30” main that crosses the Maile Way and proceeds in the<br />
Diamond Head direction.<br />
University of Hawaii <strong>Community</strong> <strong>College</strong>s April 2004<br />
Project No. CC-02-6188<br />
IV-11
The Learning Resource Center at <strong>Windward</strong> <strong>Community</strong> <strong>College</strong><br />
PROJECT DEVELOPMENT REPORT<br />
b. Proposed Storm Drainage System (The Learning Resource<br />
Center)<br />
1) Storm Drainage Demand:<br />
The proposed Learning Resource Center has a roof area of<br />
approximately 56,000 square feet that will contribute to<br />
storm systems. Additional hardscape maybe created with<br />
introduction of the amphitheater/Plaza area to the north of<br />
The Learning Resource Center and with the inclusion of the<br />
fire access and turnarounds that are located along the<br />
existing Ilima Way to the southwest and southeast of The<br />
Learning Resource Center.<br />
It is anticipated that the actual storm drainage system<br />
demand for The Learning Resource Center may be reduced<br />
by using LEED® sustainable design techniques. (Refer to<br />
LEED® Sustainable Sites, Credit 6, Storm Water<br />
Management, Section V.)<br />
2) Storm Drainage Construction: The drainage anticipated for<br />
The Learning Resource Center will utilize drainage lines on<br />
either side of the site. There is a 36” drainage main to the<br />
north-northwest and a 24” drainage main to the south and<br />
southeast. Both of these mains flow to the east where they<br />
both have outlet structures that flow into an open drainage<br />
ditch. See Figure IV.5.<br />
The Learning Resource Center site is in the Storm Drain<br />
Basin B5 which has 9.48 acres and 18.5 cubic feet per<br />
second (CFS) Runoff Flow. The proposed parking<br />
associated with the new facility is anticipated for Storm Drain<br />
Basin B8 which has 9.74 acres and 18.3 cubic feet per<br />
second (CFS) Runoff Flow.*<br />
* Plan Review Use for a Five-Year Master Plan for the University of<br />
Hawaii, <strong>Windward</strong> <strong>Community</strong> <strong>College</strong> 1992, Figure 20 Storm Drain<br />
Basins.7<br />
8. Sustainable Design (Refer to Section V)<br />
C. Landscape<br />
1. Overview<br />
The landscaping concept for The Learning Resource Center shall be in<br />
conformance with the Ultimate Landscape Plan that is part of the Plan<br />
University of Hawaii <strong>Community</strong> <strong>College</strong>s April 2004<br />
Project No. CC-02-6188<br />
IV-12
The Learning Resource Center at <strong>Windward</strong> <strong>Community</strong> <strong>College</strong><br />
PROJECT DEVELOPMENT REPORT<br />
Review Use resolution and the Master Plan for <strong>Windward</strong> <strong>Community</strong><br />
<strong>College</strong>. The landscape plans will be developed in the course of the final<br />
Schematics, Design <strong>Development</strong> and Construction Documents phases.<br />
For purposes of the Project <strong>Development</strong> Report, the Design Parameters<br />
and Plant List are summarized as follows:<br />
2. Design Parameters<br />
a. The landscape plan shall retain the character of the existing<br />
campus.<br />
b. Retain existing banyan trees and remove mango and monkey pod<br />
trees.<br />
c. Pedestrian circulation walks shall generally conform to the<br />
concept established in the master plan.<br />
d. Provide enhanced landscaping adjacent to buildings as defined in<br />
the master plan.<br />
e. Provide one species of flowering tree for parking lot landscaping<br />
and in accordance with the City and County of Honolulu Land Use<br />
Ordinance (recommend matching trees in existing parking lots for<br />
consistency and unity).<br />
3. Plant List<br />
a. Trees<br />
Scientific Name<br />
Acacia confusa<br />
Aleurites moluccana<br />
Bauhinia blakeana<br />
Bauhinia monandra<br />
Fagraea retusa<br />
Ficus Retusa<br />
Lagestroemia speciosa<br />
Lassia J x F ‘Wilhemina Tenny’<br />
Michelia alba<br />
Plumeria sp.<br />
Samanea saman<br />
Tabeuia pentaphylla<br />
Common Name<br />
Formosan Koa<br />
Kukui<br />
Hong Kong Orchid Tree<br />
St. Thomas tree<br />
Pua Kenikeni<br />
Chinese Banyan<br />
Giant Crape Myrtle<br />
Rainbow Shower<br />
Pak Lan<br />
Plumeria<br />
Monkeypod<br />
Pink Tecoma<br />
b. Palms<br />
Archotonophoenix alexandrae<br />
Chrysalipocarpus lutescens<br />
Pritchardia sp.<br />
Ptychosperma macarthurii<br />
Roystonea regia<br />
Alexander Palm<br />
Areca Palm<br />
Lolu Palm<br />
Macarthur Palm<br />
Royal Palm<br />
University of Hawaii <strong>Community</strong> <strong>College</strong>s April 2004<br />
Project No. CC-02-6188<br />
IV-13
The Learning Resource Center at <strong>Windward</strong> <strong>Community</strong> <strong>College</strong><br />
PROJECT DEVELOPMENT REPORT<br />
c. Shrubs<br />
Acalpha w. var. macafeana<br />
Alpina purpurata<br />
Bixa orellana<br />
Breynia nivosa roseo-picta<br />
Brunfelsia latifolia<br />
Cordyline terminalis<br />
Heliconia sp.<br />
Ixoria sp.<br />
Monstera deliciosa<br />
Musseanda sp.<br />
Philodendron<br />
Beefsteak Plant<br />
Red Ginger<br />
Lipstick Plant<br />
Snow Bush<br />
Yesterday-Today-Tomorrow<br />
Ti<br />
Heliconia<br />
Ixoria<br />
Monstera<br />
Musseanda<br />
Philodendron<br />
d. Ground Covers<br />
Asparagus sprengeri<br />
Gardenia radicans<br />
Microsorium scolopendria<br />
Ophiopogon japonicus<br />
Scindapsus<br />
Syngoium sp.<br />
Asperagus Fern<br />
Creeping Gardenia<br />
Laua’e Fern<br />
Mondo Grass<br />
Taro Vine<br />
Syngoium<br />
e. Grasses<br />
Paspalum congugatum<br />
Stenotaphrum secundatum<br />
Hilo Grass<br />
St. Augustine Grass<br />
4. Irrigation<br />
The Master Plan recommends the inclusion of “enhanced landscaping”<br />
adjacent to and surrounding each building. Permanent underground<br />
irrigation will be provided for this area only and integrated with a system<br />
of hose bibs to facilitate hand watering at selected times. The extent of<br />
landscaping will be developed during the subsequent design phases.<br />
D. Structural Engineering<br />
1. Overview<br />
At the time of this writing the code adopted for use in the City and County<br />
of Honolulu is the 1997 Uniform Building Code. The 2000 edition is<br />
pending review and adoption by the City.<br />
University of Hawaii <strong>Community</strong> <strong>College</strong>s April 2004<br />
Project No. CC-02-6188<br />
IV-14
The Learning Resource Center at <strong>Windward</strong> <strong>Community</strong> <strong>College</strong><br />
PROJECT DEVELOPMENT REPORT<br />
2. Design Criteria<br />
For purposes of this report, it is recommended that, as a minimum, the<br />
structural design be consistent with the following criteria:<br />
a. Design Assumptions: Assume concrete shear walls and<br />
concrete frame system, i.e. concrete columns and beams. Walls<br />
may be masonry in place of concrete walls. The structural system<br />
is subject to further evaluation during the design phases.<br />
b. Codes and Standards: Uniform Building Code 1997 edition<br />
c. Design Live Loads:<br />
Roof<br />
Ground Floor<br />
20 psf (reducible)<br />
100 psf (reducible)<br />
d. Design Dead Loads (additional to self-weight):<br />
Roof<br />
Ground Floor<br />
Roof-Mounted Equipment<br />
e. Wind:<br />
10 psf<br />
20 psf partition load<br />
Weight as provided by<br />
equipment manufacturer<br />
Basic Wind Speed<br />
80 mph<br />
Exposure Category<br />
B<br />
Primary Frame Design Method Method 1 (Normal Force<br />
Method)<br />
Building Classification<br />
Enclosed/Unenclosed<br />
Importance Factor 1.0<br />
f. Seismic<br />
E. MECHANICAL ENGINEERING<br />
1. Overview<br />
Lateral Force Procedure<br />
Equivalent Static<br />
Zone<br />
2a<br />
C t<br />
Rw 6.5<br />
Importance Factor 1.0<br />
The following sections summarize the design criteria for heating,<br />
ventilation, air conditioning (HVAC), plumbing and fire protection systems.<br />
University of Hawaii <strong>Community</strong> <strong>College</strong>s April 2004<br />
Project No. CC-02-6188<br />
IV-15
The Learning Resource Center at <strong>Windward</strong> <strong>Community</strong> <strong>College</strong><br />
PROJECT DEVELOPMENT REPORT<br />
2. HVAC<br />
Design Criteria<br />
a. Codes and Standards<br />
Current editions with City and County of Honolulu Amendments<br />
where applicable:<br />
Uniform Building Codes<br />
Uniform Fire Codes<br />
Uniform Mechanical Code<br />
State of Hawaii Elevator and Boiler Safety Code<br />
State of Hawaii Department of Health Title 39<br />
NFPA 90 A and B<br />
NFPA 96<br />
ASHRAE Fundamentals<br />
ASHRAE Standard 55<br />
ASHRAE Standard 62-2001<br />
ASHRAE Standard 90.1<br />
SMACNA Guidelines for Duct Construction<br />
Design Conditions<br />
Indoor Design for all occupied spaces:<br />
75 degrees Fahrenheit dry bulb<br />
Maximum 60 percent relative humidity<br />
Outdoor Design<br />
Per ASHRAE recommendations, use peak moisture conditions for<br />
design of outside air systems.<br />
b. Systems<br />
Descriptions<br />
Condenser water air conditioning systems using packaged air<br />
handling units with integral compressors, condensers and<br />
refrigerant coils. Constant temperature variable air volume air<br />
distribution systems serving all occupied spaces.<br />
Temperature Control Zoning<br />
Temperature control zones based on occupancy, usage and<br />
exposure. Separate zones for corner exposures. Maximum depth<br />
University of Hawaii <strong>Community</strong> <strong>College</strong>s April 2004<br />
Project No. CC-02-6188<br />
IV-16
The Learning Resource Center at <strong>Windward</strong> <strong>Community</strong> <strong>College</strong><br />
PROJECT DEVELOPMENT REPORT<br />
of perimeter zones in open plan areas to be 12 feet. Maximum<br />
size VAV box based on maximum noise criteria (NC) of 30.<br />
Air Handling Units<br />
Size of air handling equipment based on expected occupancy,<br />
hours of operation and usage. Maximum size of air handling unit<br />
to be 14,000 cubic feet per minute (CFM) of air supply. Air<br />
handling units above 2,000 CFM to have variable volume controls.<br />
Air handling units above 5,000 CFM to have variable frequency<br />
drive for fans with mixed-flow characteristic fan wheels.<br />
All air handling units to be located in sound attenuated mechanical<br />
equipment rooms, maximum NC of 35 immediately outside of fan<br />
rooms.<br />
Outside Air Systems<br />
Separate, dedicated outside air systems will serve the entire<br />
building and be sized to provide dehumidification for all air<br />
conditioned spaces and positive building pressurization under all<br />
anticipated exhaust and normal ambient wind conditions.<br />
Units to be all stainless steel construction with all copper coils.<br />
Units to employ refrigerant heat recovery to provide 100 percent of<br />
reheat required to supply neutral air at a temperature of 75<br />
degrees and dew point suitable to maintain a maximum of 60<br />
percent relative humidity in all air conditioned spaces at peak<br />
loads.<br />
Condenser Water System<br />
Distribution to all air handling units will be handled via variable<br />
flow piping system using copper and welded steel piping. Buried<br />
schedule piping from building to remote site cooling tower<br />
location. Two primary and two secondary condenser water pumps<br />
with variable frequency drives, each pump sized for a minimum of<br />
70 percent of full load.<br />
Stainless steel plate-frame heat exchangers between building<br />
distribution system and open tower cooling system. Minimum two<br />
heat exchangers, each sized for 100 percent of full load.<br />
Cooling towers shall be open, induced draft counter flow towers<br />
with all stainless steel construction. Two separate fan motors, one<br />
for full load and one for approximately 40 percent full load.<br />
Minimum of two cells, each sized for 70 percent of full load.<br />
University of Hawaii <strong>Community</strong> <strong>College</strong>s April 2004<br />
Project No. CC-02-6188<br />
IV-17
The Learning Resource Center at <strong>Windward</strong> <strong>Community</strong> <strong>College</strong><br />
PROJECT DEVELOPMENT REPORT<br />
3. Plumbing<br />
a. Design Criteria<br />
Codes and Standards<br />
Current editions with City and County of Honolulu Amendments<br />
Where applicable:<br />
Uniform Building Code<br />
Uniform Plumbing Code<br />
State of Hawaii Elevator and Boiler Safety Code<br />
NFPA Standards<br />
b. Systems Description<br />
Domestic Water<br />
Furnished at street pressure through a pressure reducing valve<br />
stations.<br />
Domestic Hot Water<br />
Domestic hot water generated by air-to-water heat pumps with<br />
electric backup at the storage tanks. Hot water at 140 degrees F<br />
and distributed at 120 degrees F through automatic mixing valve.<br />
Temperature maintenance for domestic hot water systems<br />
provided by re-circulating piping and pumps.<br />
Sanitary Sewer<br />
Waste lines for plumbing fixtures collected and piped by gravity to<br />
site sanitary sewer mains. Provide maximum 1,500 gallon precast<br />
concrete grease interceptor for food service operation.<br />
Confirm final sizing with City and County of Honolulu Division of<br />
Environmental Services.<br />
Roof Drainage<br />
4. Fire Protection<br />
Roof drainage provided by internal, cast iron rain leaders piped to<br />
site mains. Separate overflow rood drains piped to grade.<br />
a. Design Criteria<br />
University of Hawaii <strong>Community</strong> <strong>College</strong>s April 2004<br />
Project No. CC-02-6188<br />
IV-18
The Learning Resource Center at <strong>Windward</strong> <strong>Community</strong> <strong>College</strong><br />
PROJECT DEVELOPMENT REPORT<br />
Codes and Standards<br />
Current editions with City and County of Honolulu Amendments<br />
where applicable:<br />
Uniform Building Code<br />
Uniform Fire Code<br />
State of Hawaii Elevator and Boiler Safety Code<br />
NFPA 13<br />
NFPA 14<br />
NFPA 25<br />
Sprinklers<br />
All areas of the new buildings to be fully protected by wet-type fire<br />
extinguishing systems.<br />
Standpipes<br />
Manual standpipes with hose valve located in all exit stairwell and<br />
interconnected at the base of the building. Standpipe will be precharged<br />
with domestic water.<br />
5. Sustainable Design (Refer to Section V)<br />
F. Electrical Engineering<br />
1. Overview<br />
a. The information below defines a preliminary electrical<br />
infrastructure to The Learning Resource Center, parts of which are<br />
not included at this time; however, the quality level is defined.<br />
2. HECO Requirements<br />
a. Per as-built construction documents of WCC, electric utility service<br />
is provided by Hawaiian Electric Company (HECO) overhead<br />
service at 12,470 volts, 3 phase through two underground service<br />
circuits. The power is primarily metered and controlled in the main<br />
electrical metering and switching vault located at the northeast<br />
corner of the student/public parking lot on Kea‘ahala Road.<br />
Distribution to the various campus electrical distribution handholes<br />
is provided at 12.47 kV through loop underground feeder circuits.<br />
Building utilization voltages shall be 208Y/ 120 volts, 3 phase and<br />
480Y / 277 volts, 3 phase. Secondary feeders from the electrical<br />
University of Hawaii <strong>Community</strong> <strong>College</strong>s April 2004<br />
Project No. CC-02-6188<br />
IV-19
The Learning Resource Center at <strong>Windward</strong> <strong>Community</strong> <strong>College</strong><br />
PROJECT DEVELOPMENT REPORT<br />
distribution handholes to the respective building panels shall be<br />
via underground feeder circuits.<br />
b. Per discussions with HECO, the primary electrical service capacity<br />
is sufficient to support the additional electrical load of The<br />
Learning Resource Center.<br />
3. Existing Site Conditions<br />
a. Hale Manaleo presently occupies the campus site on which The<br />
Learning Resource Center will be built. An electrical improvement<br />
project was recently completed to provide underground electrical<br />
feeders to the building and to disconnect it from the adjacent<br />
overhead electrical service. This new underground electrical<br />
service also feeds Hale Mana‘opono and Hale Na‘auao to the<br />
north.<br />
b. A portion of the original overhead service (electrical, night lighting<br />
circuits, telephone, data, fire alarm, and security) along Ilima Way<br />
remains, which presently feeds Hale Manaleo, Hale La‘akea, and<br />
Hale No‘eau, and crosses Honeysuckle Road to feed the Haloa<br />
and ‘Iolani buildings on the State Hospital site. This overhead<br />
service will be removed to avoid conflict with The Learning<br />
Resource Center. Reconnection of electrical, telephone, data, fire<br />
alarm, and security services to the above listed buildings to<br />
remain shall be considered prior to termination of the overhead<br />
service along Ilima Way.<br />
c. Similar to the electrical utility distribution loop, an underground<br />
communications duct loop distributes night lighting circuits,<br />
telephone, data, fire alarm, and security services to the various<br />
buildings on the campus via communication distribution<br />
handholes, with exception to the above buildings still connected to<br />
overhead services. On-campus telephone, data, fire alarm and<br />
security systems are centrally located in [building(s)]. New<br />
telephone, data, fire alarm, and security cabling shall be provided<br />
from the central distribution location to The Learning Resource<br />
Center within the existing communications duct.<br />
4. On-Site Power & Communications<br />
a. Electrical service to The Learning Resource Center shall be<br />
obtained from existing EHH #12A located at the turnaround on the<br />
east side of Hale Palanakila (Arts & Humanities Building). The<br />
12.47 kV primary electrical service shall be tapped and extended<br />
via underground feeders to a new pad-mounted dry-type<br />
transformer to step down the primary voltage to 480Y/277V, 3-<br />
University of Hawaii <strong>Community</strong> <strong>College</strong>s April 2004<br />
Project No. CC-02-6188<br />
IV-20
The Learning Resource Center at <strong>Windward</strong> <strong>Community</strong> <strong>College</strong><br />
PROJECT DEVELOPMENT REPORT<br />
phase utilization voltage. The transformer shall be located on the<br />
southwest side of the building, preferably adjacent to the<br />
turnaround for maintenance considerations. Secondary electrical<br />
service shall be via underground feeders to a 480Y/277V<br />
switchboard/distribution panel located in the first floor Central<br />
Electrical Room of The Learning Resource Center. The 480/277<br />
voltages shall be primarily utilized for mechanical and lighting<br />
systems. Step-down transformers shall be utilized for 208Y/120<br />
voltages for general power distribution throughout The Learning<br />
Resource Center.<br />
b. Communications services (telephone, data, fire alarm, and<br />
security) shall be obtained from existing CMH #9 adjacent to EHH<br />
#12A. New telephone, data, fire alarm, and security cabling shall<br />
be pulled within the existing communications duct from the central<br />
distribution center located in [building(s)] to existing CMH #9 and<br />
extended to the Central Data Room of The Learning Resource<br />
Center via underground communications conduits. Night lighting<br />
circuits shall also be extended to provide power to site lighting<br />
poles in the area of The Learning Resource Center.<br />
5. Design Criteria<br />
a. Electrical Codes and Standards:<br />
1) NFPA 70 National Electrical Code (NEC)<br />
2) NFPA 101 Life Safety Code<br />
3) IES Lighting Illuminating Engineering Society<br />
Handbook<br />
4) 1997 UBC Uniform Building Code<br />
5) 1997 UFC Uniform Fire Code<br />
b. Power Service<br />
1) Primary power will be extended from the primary circuits(s)<br />
electrical handhole EHH #12A. 15 kV rated primary cables<br />
will tap into the existing circuit(s) and extend via a new<br />
underground primary duct to a new pad mounted<br />
transformer with integral switch. The utilization voltage of<br />
the transformer shall be 480Y/277 volts, 3 phase, 4-wire.<br />
2) An underground secondary duct with secondary cables will<br />
be run from the new transformer to the Main Switchboard.<br />
University of Hawaii <strong>Community</strong> <strong>College</strong>s April 2004<br />
Project No. CC-02-6188<br />
IV-21
The Learning Resource Center at <strong>Windward</strong> <strong>Community</strong> <strong>College</strong><br />
PROJECT DEVELOPMENT REPORT<br />
3) The Main Switchboard will be rated as required and shall<br />
consist of a pull section, check meter section and a main<br />
breaker section and distribution section with breakers for<br />
sub-feeders. Voltage and ampere meters will be provided.<br />
4) Utilization Panels will be located within the Central<br />
Electrical Room and Electrical Closets within the building.<br />
c. Communications Services<br />
1) Communications (telephone, data, fire alarm and security)<br />
services shall be extended from CMH #9 to respective<br />
backboards, enclosures, or panels in the Central Data<br />
Room via an underground duct.<br />
2) All necessary system cabling to connect The Learning<br />
Resource Center to the campus communications<br />
distribution center for the listed systems shall be inclusive<br />
to the project.<br />
3) Cabling within the building shall be distributed via panels,<br />
backboards, and raceways dedicated to each system as<br />
coordinated with the appropriate WCC department.<br />
d. Lighting<br />
1) General illumination shall be provided by fluorescent<br />
luminaires with electronic ballast and T8 (or T5) lamps.<br />
2) Fluorescent lamps shall be low-mercury, TCLP-compliant.<br />
3) Indirect / direct pendant-mounted luminaires shall be<br />
utilized for computer / circulation areas.<br />
4) Parabolic louvers or prismatic lens will be provided as<br />
determined.<br />
5) Recessed downlights, where required, shall have compact<br />
fluorescent lamps with electronic ballast. Lamps shall be<br />
provided with color temperature of 3500K.<br />
6) Zone light switches will be provided for conference/<br />
teaching / learning areas to provide multiple illumination<br />
levels.<br />
University of Hawaii <strong>Community</strong> <strong>College</strong>s April 2004<br />
Project No. CC-02-6188<br />
IV-22
The Learning Resource Center at <strong>Windward</strong> <strong>Community</strong> <strong>College</strong><br />
PROJECT DEVELOPMENT REPORT<br />
7) Corridor illumination shall be pendant, surface, or recessed<br />
mounted luminaires as determined.<br />
8) Photocell switching shall be utilized in areas where<br />
daylighting will be incorporated to minimize energy usage.<br />
9) Emergency exit and egress illumination shall be provided<br />
by integral battery and charger at selected locations in<br />
ceiling luminaires within all areas.<br />
10) EXIT signs will be provided with integral batteries and<br />
chargers for emergency backup. LED lamps selected for<br />
long life.<br />
11) Luminaires for exterior building illumination shall have<br />
compact fluorescent lamps with electronic ballast.<br />
Luminaires shall be wall-mounted for maintenance<br />
considerations. Lamps shall be provided with color<br />
temperature of 3500K.<br />
12) Site (walkway) luminaires shall be provided to match<br />
existing pole lighting with metal-halide lamps.<br />
e. Power Utilization Systems<br />
1) Duplex convenience outlets with isolated ground and<br />
duplex convenience outlets with ground fault interrupt<br />
(GFI) will be installed accordance with the NEC.<br />
2) Faceplates shall be stainless steel for durability.<br />
3) Single/double gang junction boxes, with future circuits will<br />
be provided as required.<br />
4) Special outlets as will be determined, shall be provided.<br />
f. Communications Systems<br />
1) Telephone and data outlets shall be provided where<br />
required.<br />
2) Approximately 300 data outlets will be required in the first<br />
floor circulation and computer areas. Majority of outlets<br />
will be located in floor slab or raised floor, and shall be<br />
recessed, covers shall be flush to floor.<br />
University of Hawaii <strong>Community</strong> <strong>College</strong>s April 2004<br />
Project No. CC-02-6188<br />
IV-23
The Learning Resource Center at <strong>Windward</strong> <strong>Community</strong> <strong>College</strong><br />
PROJECT DEVELOPMENT REPORT<br />
3) Telephone outlets to have individual 1” conduit homerun to<br />
nearest Tech Closet on each floor. Each Telephone outlet<br />
location will be provided with a 4-11/ 16” x 2-1/8” deep<br />
square junction box, double gang collar with blank cover<br />
plate. Outlets and cables shall be furnished and installed<br />
complete.<br />
4) DATA outlets shall include 1” conduit homerun to<br />
backboards within the Tech Closets. System shall include<br />
distribution frame (backboards), as required for connecting<br />
circuits including all cabling. Equipment for an operating<br />
local area network system to be furnished by others. Each<br />
DATA outlet location will be provided a 4-11/ 16” x 2-1/8”<br />
deep square junction box, double gang collar with blank<br />
cover plate. Outlets and cables shall be furnished and<br />
installed complete.<br />
5) Video outlets, if required, will have an individual 1” conduit<br />
homerun to backboards within the Tech Closets. Each<br />
video outlet location will be provided a 4-11/ 16” x 2-1/8”<br />
deep square junction box, double gang collar with blank<br />
cover plate. Outlets and cables shall be furnished and<br />
installed complete. Video distribution shall originate from<br />
the Studio Control room or as determined.<br />
g. Fire Alarm System<br />
1) An addressable type system matching or compatible to the<br />
campus central system, which is compliant to the Life<br />
Safety Code (NFPA 101) and the current Uniform Fire<br />
Code, shall be specified.<br />
2) An annunciator panel shall be provided. Location to be<br />
determined.<br />
3) Devices shall include manual pull stations, audio and<br />
visual devices per ADA criteria, supervision of sprinkler<br />
flow and tamper switches, smoke detectors and automatic<br />
duct smoke detectors.<br />
4) Interface will be provided for remote annunciation and<br />
supervision to the central campus system.<br />
University of Hawaii <strong>Community</strong> <strong>College</strong>s April 2004<br />
Project No. CC-02-6188<br />
IV-24
The Learning Resource Center at <strong>Windward</strong> <strong>Community</strong> <strong>College</strong><br />
PROJECT DEVELOPMENT REPORT<br />
h. Security System<br />
1) A system matching or compatible to the central campus<br />
system shall be specified.<br />
2) An annunciator panel will be provided. Location to be<br />
determined.<br />
3) Devices shall include magnetic door switches, infrared and<br />
ultrasonic motion detectors as determined by the Security<br />
Consultant.<br />
6. Sustainable Design (Refer to Section V)<br />
University of Hawaii <strong>Community</strong> <strong>College</strong>s April 2004<br />
Project No. CC-02-6188<br />
IV-25
The Learning Resource Center at <strong>Windward</strong> <strong>Community</strong> <strong>College</strong><br />
PROJECT DEVELOPMENT REPORT<br />
V. SUSTAINABLE DESIGN GUIDELINES<br />
A. Overview of Sustainability<br />
The pursuit of sustainable building design encompasses a comprehensive set of<br />
design and construction considerations that typically involve owner, architect and<br />
engineers, contractors, manufacturers, maintenance personnel and building<br />
occupants, etc.; i.e., the entire project team from design inception through post<br />
occupancy. The U.S. Green Building Council developed and sponsors the<br />
LEED® (Leadership in Energy and Environmental <strong>Development</strong>) Green Building<br />
Rating System® to evaluate, measure and assign credits for environmental and<br />
system performance of a facility. LEED® addresses the following environmental<br />
categories with prescriptive requirements for each category:<br />
1. Sustainable Sites<br />
2. Water Efficiency<br />
3. Energy & Atmosphere<br />
4. Material & Resources<br />
5. Indoor Environmental Quality<br />
6. Innovation & Design Process<br />
These categories and requirements are summarized in Exhibit V.1 and are<br />
intended for further evaluation for The Learning Resource Center during the<br />
course of design and the preparation of construction documents. The attached<br />
exhibit summarizes the credits that are attainable based on meeting prescriptive<br />
prerequisites and requirements for the above categories. The exhibit identifies<br />
credits that are “reasonably certain” (achievable); credits that are “possible” to<br />
achieve; and additionally, credits that are deemed “not possible” to achieve.<br />
The (33) credits indicated in the Exhibit V.1 represent an initial assessment and<br />
point of departure toward achieving LEED® Certification for The Learning<br />
Resource Center at <strong>Windward</strong> <strong>Community</strong> <strong>College</strong>. The suggested credits<br />
should be evaluated in greater depth with the design team and the University of<br />
Hawaii/<strong>Windward</strong> <strong>Community</strong> <strong>College</strong>.<br />
University of Hawaii <strong>Community</strong> <strong>College</strong>s April 2004<br />
Project No. CC-02-6188 V-1
The Learning Resource Center at <strong>Windward</strong> <strong>Community</strong> <strong>College</strong><br />
PROJECT DEVELOPMENT REPORT<br />
EXHIBIT V.1 LEED® CERTIFICATION SUMMARY<br />
Reference: LEED® Rating System,<br />
Version 2.1<br />
Reasonably<br />
Certain<br />
Possible<br />
Not Possible<br />
Points<br />
Sustainable Sites 14 Possible Points<br />
Prereq 1 Erosion & Sedimentation Control Required<br />
Credit 1 Site Selection 1 1 0 0<br />
Credit 2 Urban Redevelopment 1 0 0 1<br />
Credit 3 Brownfield Redevelopment 1 0 0 1<br />
Credit 4.1 Alternative Transportation, Public Transportation Access 1 0 0 1<br />
Credit 4.2 Alternative Transportation, Bicycle Storage & Changing Rooms 1 1 0 0<br />
Credit 4.3 Alternative Transportation, Alternative Fuel Vehicles 1 1 0 0<br />
Credit 4.4 Alternative Transportation, Parking Capacity 1 1 0 0<br />
Credit 5.1 Reduced Site Disturbance, Protect or Restore Open Space 1 0 0 1<br />
Credit 5.2 Reduced Site Disturbance, <strong>Development</strong> Footprint 1 1 0 0<br />
Credit 6.1 Stormwater Management, Rate and Quantity 1 1 0 0<br />
Credit 6.2 Stormwater Management, Treatment 1 0 0 1<br />
Credit 7.1 Heat Island Effect, Non-Roof 1 1 0 0<br />
Credit 7.2 Heat Island Effect, Roof 1 0 0 1<br />
Credit 8 Light Pollution Reduction 1 1 0 0<br />
Subtotal 8 0 6 14<br />
Water Efficiency 5 Possible Points<br />
Credit 1.1 Water Efficient Landscaping, Reduce by 50% 1 1 0 0<br />
Credit 1.2 Water Efficient Landscaping, No Potable Use or No Irrigation 1 1 0 0<br />
Credit 2 Innovative Wastewater Technologies 1 1 0 0<br />
Credit 3.1 Water Use Reduction, 20% Reduction 1 1 0 0<br />
Credit 3.2 Water Use Reduction, 30% Reduction 1 0 0 1<br />
Subtotal 4 0 1 5<br />
Energy & Atmosphere 17 Possible Points<br />
Prereq 1 Fundamental Building Systems Commissioning Required<br />
Prereq 2 Minimum Energy Performance Required<br />
Prereq 3 CFC Reduction in HVAC&R Equipment Required<br />
Credit 1 Optimize Energy Performance 1–10<br />
15% 1 0 0<br />
20% 1 0 0<br />
25% 0 0 1<br />
30% 0 0 1<br />
35% 0 0 1<br />
40% 0 0 1<br />
45% 0 0 1<br />
50% 0 0 1<br />
University of Hawaii <strong>Community</strong> <strong>College</strong>s April 2004<br />
Project No. CC-02-6188 V-2
The Learning Resource Center at <strong>Windward</strong> <strong>Community</strong> <strong>College</strong><br />
PROJECT DEVELOPMENT REPORT<br />
55% 0 0 1<br />
60% 0 0 1<br />
Credit 2.1 Renewable Energy, 5% 1 0 0 1<br />
Credit 2.2 Renewable Energy, 10% 1 0 0 1<br />
Credit 2.3 Renewable Energy, 20% 1 0 0 1<br />
Credit 3 Additional Commissioning 1 1 0 0<br />
Credit 4 Ozone Depletion 1 0 0 1<br />
Credit 5 Measurement & Verification 1 1 0 0<br />
Credit 6 Green Power 1 0 0 1<br />
Subtotal 4 0 13 17<br />
Materials & Resources 13 Possible Points<br />
Prereq 1 Storage & Collection of Recyclables Required<br />
Credit 1.1 Building Reuse, Maintain 75% of Existing Shell 1 0 0 1<br />
Credit 1.2 Building Reuse, Maintain 100% of Shell 1 0 0 1<br />
Credit 1.3 Building Reuse, Maintain 100% Shell & 50% Non-Shell 1 0 0 1<br />
Credit 2.1 Construction Waste Management, Divert 50% 1 1 0 0<br />
Credit 2.2 Construction Waste Management, Divert 75% 1 0 0 1<br />
Credit 3.1 Resource Reuse, Specify 5% 1 0 0 1<br />
Credit 3.2 Resource Reuse, Specify 10% 1 0 0 1<br />
Credit 4.1 Recycled Content, Specify 5% (p.c. + 1/2 p.i.) 1 1 0 0<br />
Credit 4.2 Recycled Content, Specify 10% (p.c. + 1/2 p.i.) 1 0 0 1<br />
Credit 5.1 Local/Regional Materials, 20% Manufactured Locally 1 0 0 1<br />
Credit 5.2 Local/Regional Materials, of 20% in MRc5.1, 50% Harvested Locally 0 0 1<br />
1 Credit 6 Rapidly Renewable Materials 1 1 0 0<br />
Credit 7 Certified Wood 1 0 0 1<br />
Subtotal 3 0 10 13<br />
Indoor Environmental Quality 15 Possible Points<br />
Prereq 1 Minimum IAQ Performance Required<br />
Prereq 2 Environmental Tobacco Smoke (ETS) Control Required<br />
Credit 1 Carbon Dioxide (CO2 ) Monitoring 1 1 0 0<br />
Credit 2 Ventilation Effectiveness 1 0 0 1<br />
Credit 3.1 Construction IAQ Management Plan, During Construction 1 1 0 0<br />
Credit 3.2 Construction IAQ Management Plan, Before Occupancy 1 1 0 0<br />
Credit 4.1 Low-Emitting Materials, Adhesives & Sealants 1 1 0 0<br />
Credit 4.2 Low-Emitting Materials, Paints 1 1 0 0<br />
Credit 4.3 Low-Emitting Materials, Carpet 1 1 0 0<br />
Credit 4.4 Low-Emitting Materials, Composite Wood 1 1 0 0<br />
Credit 5 Indoor Chemical & Pollutant Source Control 1 1 0 0<br />
Credit 6.1 Controllability of Systems, Perimeter 1 0 0 1<br />
Credit 6.2 Controllability of Systems, Non-Perimeter 1 0 0 1<br />
Credit 7.1 Thermal Comfort, Comply with ASHRAE 55-1992 1 1 0 0<br />
Credit 7.2 Thermal Comfort, Permanent Monitoring System 1 1 0 0<br />
Credit 8.1 Daylight & Views, Daylight 75% of Spaces 1 0 0 1<br />
Credit 8.2 Daylight & Views, Views for 90% of Spaces 1 0 0 1<br />
University of Hawaii <strong>Community</strong> <strong>College</strong>s April 2004<br />
Project No. CC-02-6188 V-3
The Learning Resource Center at <strong>Windward</strong> <strong>Community</strong> <strong>College</strong><br />
PROJECT DEVELOPMENT REPORT<br />
Subtotal 10 0 5 15<br />
Innovation & Design Process 5 Possible Points<br />
Credit 1.1 Innovation in Design 1 1 0 0<br />
Credit 1.2 Innovation in Design 1 1 0 0<br />
Credit 1.3 Innovation in Design 1 1 0 0<br />
Credit 1.4 Innovation in Design 1 0 0 1<br />
Credit 2 LEED® Accredited Professional 1 1 0 0<br />
Subtotal 4 0 1 5<br />
LEED® Certification for WCC Learning Resource Center 33<br />
LEED® Possible Additional Credits 0<br />
LEED® Not Possible 36<br />
LEED® Rating System Total Available Credits 69<br />
University of Hawaii <strong>Community</strong> <strong>College</strong>s April 2004<br />
Project No. CC-02-6188 V-4
The Learning Resource Center at <strong>Windward</strong> <strong>Community</strong> <strong>College</strong><br />
PROJECT DEVELOPMENT REPORT<br />
VI.<br />
IMPLEMENTATION AND PROBABLE COST OF CONSTRUCTION<br />
The proposed implementation plan and the probable cost of construction for The<br />
Learning Resource Center comprises three (3) components, i.e., The Learning Resource<br />
Center, Banyan Drive (Loop Road) Improvements and the Hazardous Pipe Removal and<br />
Remediation. The following timeframe represents the projected design and construction<br />
schedule and assumes that these components will be implemented in parallel.<br />
A. Projected Schedule for Planning Purposes<br />
1. Design Phase 10 – 14 months<br />
(Schematic Completion)<br />
(Design <strong>Development</strong>)<br />
(Construction Documents)<br />
2. Building Permit Allow 3 – 4 months<br />
3. Bid Period/Negotiations/Award 3 – 4 months<br />
4. Construction Phase + Fit Out 20 – 24 months<br />
5. Close Out Allow 3 – 4 months<br />
B. The Statement of Probable Construction Cost is conceptually summarized in<br />
Exhibit VI.1 for The Learning Resource Center and related work and assumes a<br />
5 percent escalation beginning January 2005.<br />
EXHIBIT VI.1: STATEMENT OF PROBABLE CONSTRUCTION COST<br />
THE LEARNING RESOURCE CENTER<br />
1 Site Costs<br />
Parking Spaces<br />
(80) <strong>Library</strong> and Learning Center parking spaces @ $2800 $224,000<br />
(18) Ilima Way relocated parking spaces @ $2800 $50,400<br />
Utilities, utility relocation, site lighting $325,000<br />
Landscaping, walks & plazas $450,000<br />
Retaining walls $100,000<br />
Amphitheater $200,000<br />
Service and Fire Drives $300,000<br />
Demolition of Hale Manaleo $125,000<br />
Subtotal $1,774,400<br />
2 Building Construction Cost $24,528,935<br />
81,793 GSF & 2000 GSF of canopy overhang @ $300 / GSF<br />
3 Furniture and Equipment $2,452,894<br />
10% of Item 2<br />
4 Computers / Technology $1,839,670<br />
7.5% of Item 2<br />
University of Hawaii <strong>Community</strong> <strong>College</strong>s April 2004<br />
Project No. CC-02-6188<br />
VI-1
The Learning Resource Center at <strong>Windward</strong> <strong>Community</strong> <strong>College</strong><br />
PROJECT DEVELOPMENT REPORT<br />
5 Construction Contingency $2,630,334<br />
10% of Items 1 & 2<br />
Subtotal Project Cost $33,226,232<br />
6 A / E Fees (Assume 10% of Project Cost) $3,322,623<br />
Total Project Cost $36,548,855<br />
BANYAN DRIVE - LOOP ROAD DESIGN & CONSTRUCTION<br />
1 Site Costs<br />
Roadway $180,000<br />
Fill Material $100,000<br />
Retaining Wall $100,000<br />
Utility Pole Relocation & Related Work $150,000<br />
Fence Relocation $20,000<br />
Subtotal $550,000<br />
2 Construction Contingency $55,000<br />
10% of Item 1<br />
3 A / E Fees (Assume 10% of 1+2) $60,500<br />
Subtotal Project Cost $665,500<br />
HAZARDOUS PIPE REMOVAL AND REMEDIATION<br />
1 Scope Not Determine (Allowance) $150,000<br />
2 Construction Contingency $15,000<br />
10% of Item 1.<br />
3 A / E Fees (Assume 10% of 1+2) $16,500<br />
Subtotal Project Cost $181,500<br />
SUSTAINABLE DESIGN STRATEGIES (LEED)®<br />
1 Additional Costs (Assume 6% of LRC Cost) $1,461,954<br />
2 Construction Contingency $146,195<br />
10% of Item 1.<br />
3 A/E Fee (Assume 10% of Items 1+2) $160,815<br />
Subtotal Project Cost $1,768,965<br />
Grand Total $39,164,820<br />
Notes:<br />
1. The Grand Total cost is in current dollars. Escalation to the midpoint of<br />
the future construction is required. Escalation is "assumed" @ 5% per year.<br />
University of Hawaii <strong>Community</strong> <strong>College</strong>s April 2004<br />
Project No. CC-02-6188<br />
VI-2
The Learning Resource Center at <strong>Windward</strong> <strong>Community</strong> <strong>College</strong><br />
PROJECT DEVELOPMENT REPORT<br />
ESCALATION<br />
Grand Total escalated to January of 2005 @ 5% $41,123,061<br />
Grand Total escalated to January of 2006 @ 5% $43,179,214<br />
Grand Total escalated to January of 2007 @ 5% $45,338,175<br />
Grand Total escalated to January of 2008 @ 5% $47,605,083<br />
Grand Total escalated to January of 2009 @ 5% $49,985,338<br />
Grand Total escalated to January of 2010 @ 5% $52,484,604<br />
Grand Total escalated to January of 2011 @ 5% $55,108,835<br />
University of Hawaii <strong>Community</strong> <strong>College</strong>s April 2004<br />
Project No. CC-02-6188<br />
VI-3
The Learning Resource Center at <strong>Windward</strong> <strong>Community</strong> <strong>College</strong><br />
PROJECT DEVELOPMENT REPORT<br />
VII.<br />
REFERENCES<br />
1. City and County of Honolulu, Resolution No. 94-87, CD-I, May 4, 1994<br />
2. Joint Venture/Okita Kunimitsu & Associates, Inc./Ernest Hara and Associates,<br />
Inc., <strong>Windward</strong> <strong>Community</strong> <strong>College</strong> Master Plan Report, April 22, 1989.<br />
3. Okita Kunimitsu & Associates, Inc., Plan Review Use for a Five Year Master Plan<br />
for the University of Hawaii <strong>Windward</strong> <strong>Community</strong> <strong>College</strong>, Volumes 1 & 2, May<br />
1992<br />
4. Okita Kunimitsu & Associates, Inc., <strong>Windward</strong> <strong>Community</strong> <strong>College</strong> Urban Design<br />
Plan and Design Guidelines, July 15, 1994, Revised November 30, 1995.<br />
5. Wilson Okamoto & Associates, Inc., Environmental Assessment for <strong>Windward</strong><br />
<strong>Community</strong> <strong>College</strong> Master Plan, October 28, 1987.<br />
6. City and County of Honolulu, Dept. of Planning & Permitting, Land Use<br />
Ordinance, April 1995.<br />
7. 1997 Uniform Building Code<br />
8. Drawings<br />
Description Job Number Date Project<br />
Water lines<br />
Accessible ramps,<br />
Minor storm drains<br />
at Hale Manaleo<br />
Site Utilities<br />
Storm sewer<br />
DAGS<br />
CC-00-6152<br />
DAGS<br />
12-31-4135<br />
DAGS<br />
12-31-6180<br />
01-18-02 WCC – Connect Existing<br />
buildings to new main campus<br />
water distribution system<br />
3-4-02 Architectural Barrier<br />
Removal<br />
2-7-04 Building K<br />
Natural Sciences C-13<br />
Site Utilities DAGS 12-31-<br />
4100<br />
Utility Plan DAGS 12-31-<br />
4056<br />
April 2001<br />
April 2000<br />
Fire Safety Improvements<br />
E-1, E-2, E-3, E-4<br />
Building D<br />
Campus Center C-5, C-6<br />
Exterior<br />
Elevations<br />
Storm Drains,<br />
Lines and Roads<br />
12-31-4027 9-15-98 Building J<br />
12-31-4002 4-22-96 New Campus <strong>Development</strong>,<br />
Phase I<br />
University of Hawaii <strong>Community</strong> <strong>College</strong>s April 2004<br />
Project No. CC-02-6188<br />
VII-1
The Learning Resource Center at <strong>Windward</strong> <strong>Community</strong> <strong>College</strong><br />
PROJECT DEVELOPMENT REPORT<br />
9. Federal Register<br />
Architectural and Transportation Barriers Compliance Board<br />
36 CFR Parts 1190 and 1191<br />
Americans with Disabilities Act (ADA)<br />
Accessibility Guidelines for Buildings and Facilities;<br />
Architectural Barriers Act (ABA) Accessibility Guidelines for Proposed Rule.<br />
10. LEED® Reference Guide and Rating System Version 2.0, June 2001<br />
University of Hawaii <strong>Community</strong> <strong>College</strong>s April 2004<br />
Project No. CC-02-6188<br />
VII-2
PROJECT DEVELOPMENT REPORT<br />
VOLUME I: PLANNING & CONCEPT DEVELOPMENT<br />
APPENDIX A<br />
PLAN REVIEW USE (PRU) ASSESSMENT AND CITY<br />
AND COUNTY OF HONOLULU REVIEW COMMENTS<br />
PROJECT NO. CC-02-6188<br />
APRIL 2004<br />
1357 KAPIOLANI BOULEVARD<br />
HONOLULU, HAWAII 96814
<strong>Windward</strong> <strong>Community</strong> <strong>College</strong><br />
Hale Manaleo
<strong>Windward</strong> <strong>Community</strong> <strong>College</strong><br />
Hale Manaleo
The Learning Resource Center at <strong>Windward</strong> <strong>Community</strong> <strong>College</strong><br />
PROGRAM PLANNING<br />
SUMMARY OF FUNCTIONS - ASSIGNABLE SQUARE FOOTAGE<br />
Function<br />
Number Function Description Units<br />
Student<br />
Stations<br />
Fac/Staff<br />
Stations<br />
Pre-Final<br />
I. Administration<br />
1 Director of Information Technology Services<br />
Office 1 1 200<br />
2 Institutional Researcher Office 1 1 200<br />
3 Secretary Office 1 2 175<br />
4 Administrative Storage Room 1 0<br />
5 Conference Room 1 600<br />
5a Male Restroom 1 50<br />
5b Female Restroom 1 50<br />
Subtotal 0 4 1,275<br />
II. <strong>Library</strong><br />
6 Vestibule 1 800<br />
7 Information Commons 1 48 2,700<br />
8 Information Commons Manager's Office 1 1 150<br />
9 Information Reference Desk Area 1 4 425<br />
10 Reference Collection Area 1 16 1,100<br />
11 Reference Librarian's Office (4 @ 115) 4 4 460<br />
12 Reference Librarians Conference Room 1 340<br />
13 Circulation Service Center 1 4 1,125<br />
14 Circulation Workroom 1 3 735<br />
15 Circulation Manager's Office 1 1 145<br />
16 Circulation Storage Room 1 200<br />
17 Current Periodicals Area 1 20 700<br />
18 Periodicals Backfile Area 1 12 700<br />
19 Microforms Area 1 5 550<br />
20 Pamphlets Area 1 4 155<br />
21 Maps/Art Prints Area 1 4 600<br />
22 Listening/Viewing Area 1 8 480<br />
23 Study Area A 1 22 1,000<br />
24 Hawaiian Collection Room 1 24 1 1,800<br />
25 Bookstacks Area 1 5,500<br />
26 Study Area B (shared w/ Learning Center) inc.<br />
6 study booths 1 110 4,100<br />
27 Group Viewing Room (1 @ 300 & 2 @ 170) 3 640<br />
28 Group Study Room (6 @ 150 & 2 @170) Area<br />
B 9 1,240<br />
29 Technical Services Room 1 4 1,130<br />
30 Technical Services Librarian's Office (Tech I) 1 1 140<br />
31 <strong>Library</strong> Technician's Office (Tech II) 1 1 130<br />
32 <strong>College</strong> Archives Room 1 600<br />
32a Circulation Storage Room 1 135<br />
33 Head Librarian's Office 1 1 240<br />
34 Secretary Office 1 1 195<br />
University of Hawaii <strong>Community</strong> <strong>College</strong>s December 2003<br />
Project No. CC-02-6188 1 PRE-FINAL
The Learning Resource Center at <strong>Windward</strong> <strong>Community</strong> <strong>College</strong><br />
PROGRAM PLANNING<br />
SUMMARY OF FUNCTIONS - ASSIGNABLE SQUARE FOOTAGE<br />
Function<br />
Number Function Description Units<br />
Student<br />
Stations<br />
Fac/Staff<br />
Stations<br />
Pre-Final<br />
35 Storage Room 1 200<br />
36 Staff Emergency Room and Lounge 1 800<br />
37 Meeting Room with 2 Closets @ 100 1 1,220<br />
38 Electronic Classroom 1 24 1 875<br />
39 Computer Laboratory 1 72 4 3,670<br />
39a 24-hour Study/Coffee Shop 1 30 1,500<br />
Subtotal 399 31 36,480<br />
III. The Learning Center (TLC)<br />
40 TLC Coordinator's Office 1 1 150<br />
41 TLC Manager 1 1 120<br />
42 Distribution Center 1 2 330<br />
43 Work Room 1 2 385<br />
44 Testing Room 1 25 810<br />
45 Quiet Study Area (Merged with Study Area ‘B’ -<br />
<strong>Library</strong> 1 0 5 0<br />
46 Resource Teacher Room 2 2 220<br />
47 STAAR Reception Area 1 2 180<br />
48 STAAR Counselor's Office 3 3 330<br />
49 STAAR Clerk-Typist Office 1 1 100<br />
50 STAAR Tutors' Office 1 2 235<br />
Subtotal 27 19 2,860<br />
IV. Computing Services<br />
51 Computing Services Coordinator's Office 1 1 215<br />
52 Computing Services Secretary Office 1 2 205<br />
53 Help Desk Room 1 2 285<br />
54 Training and Demonstration Room 1 2 440<br />
55 Staff Workroom 1 6 985<br />
56 Computer Setup and Repair Room 1 4 800<br />
57 Server Area 1 0 355<br />
58 Storage Room 1 200<br />
58a Bathroom 50<br />
Subtotal 0 17 3,535<br />
V. Instructional Media Services<br />
59 Reception Area/Counter/Equipment Check-out 1 3 210<br />
60 General Office, Job and Equipment Intake<br />
Room 1 6 450<br />
61 Clerk-Typist's Office 1 1 125<br />
62 Media Coordinator’s Office 1 1 200<br />
63 Storage Room 1 0 190<br />
64 Duplication and Copiers Room 1 1 610<br />
65 Duplication Storage Room 1 0 160<br />
66 Bindery Room 1 3 300<br />
University of Hawaii <strong>Community</strong> <strong>College</strong>s December 2003<br />
Project No. CC-02-6188 2 PRE-FINAL
The Learning Resource Center at <strong>Windward</strong> <strong>Community</strong> <strong>College</strong><br />
PROGRAM PLANNING<br />
SUMMARY OF FUNCTIONS - ASSIGNABLE SQUARE FOOTAGE<br />
Function<br />
Number Function Description Units<br />
Student<br />
Stations<br />
Fac/Staff<br />
Stations<br />
Pre-Final<br />
67 Duplication Manager's Office 1 1 140<br />
68 New Media Laboratory 1 20 1 620<br />
69 Instructional <strong>Development</strong> Specialist’s Office 1 1 110<br />
70 Media Production Specialist's Office 1 1 120<br />
71 Web Master's Office 1 1 125<br />
72 Studio Storage Room 1 0 110<br />
73 Instructional Video Studio 1 5 715<br />
74 Electronic Duplication and Distribution Room 1 3 450<br />
75 Studio Control Room 1 6 210<br />
76 Audio Recording Booth 1 2 125<br />
77 Electronic Maintenance and Repair Shop 1 3 745<br />
78 Electronic Technician I Office 1 1 145<br />
79 Electronic Technician II Office 1 1 145<br />
80 Equipment Storage Room 1 1 215<br />
81 Graphic Materials Preparation Room 1 4 4 850<br />
82 Graphic Artist’s Office 1 1 160<br />
83 Graphics Storage Room 1 0 115<br />
84 Spray Booth 0 70<br />
85 Loading and Receiving/Storage Room 0 900<br />
85a Bathroom 1 0 50<br />
Subtotal 29 42 8.365<br />
Subtotal (Assignable Square Feet) 455 113 52,515<br />
VI. Non-Assignable Square Feet/Building Support<br />
86. Atrium 1 3,500<br />
87. Delivery Area/Receiving (Merged with #85) 1<br />
88. Cart Parking Area 1 485<br />
89. Trash Area 1 250<br />
90. Wiring/Telecommunications Room (1 @ 1 440<br />
400)<br />
91. Wiring/Telecommunications Subroom (1 @ 4 415<br />
85, 1 @ 95, 1 @ 100, 1 @ 135)<br />
92. Janitorial Rooms (1 @ 45, 1 @ 60, 1 @ 65, 4 240<br />
1 @ 70)<br />
93. Central Housekeeping 1 160<br />
94. Central Mechanical Room 1 3,090<br />
95. Central Electrical Room 1 350<br />
96. Electrical Floor Closets (4 @ 60) 4 240<br />
97. Public Toilets (2 @ 280, 2 @ 285) 4 1,130<br />
98. Student Lockers/Bag Nitches (20 ½ length<br />
lockers)<br />
40 200<br />
University of Hawaii <strong>Community</strong> <strong>College</strong>s December 2003<br />
Project No. CC-02-6188 3 PRE-FINAL
The Learning Resource Center at <strong>Windward</strong> <strong>Community</strong> <strong>College</strong><br />
PROGRAM PLANNING<br />
SUMMARY OF FUNCTIONS - ASSIGNABLE SQUARE FOOTAGE<br />
Function<br />
Number Function Description Units<br />
Student<br />
Stations<br />
Fac/Staff<br />
Stations<br />
Pre-Final<br />
Subtotal (Non-Assignable Square Feet)<br />
10,500<br />
(VI)<br />
Subtotal Assignable Square<br />
52,515<br />
Feet (I-V)<br />
Subtotal (I-VI) 63,015<br />
VII. Horizontal & Vertical Circulation, Wall<br />
Thickness; Duct Shafts & Overhangs (+29.8%)<br />
18,778<br />
TOTAL GROSS SQUARE FEET 81,793<br />
GSF<br />
University of Hawaii <strong>Community</strong> <strong>College</strong>s December 2003<br />
Project No. CC-02-6188 4 PRE-FINAL
PROJECT DEVELOPMENT REPORT<br />
VOLUME I: PLANNING & CONCEPT DEVELOPMENT<br />
APPENDIX B<br />
INTERACTIVE WORKSHOP NOTES AND DOCUMENTS<br />
PROJECT NO. CC-02-6188<br />
APRIL 2004<br />
1357 KAPIOLANI BOULEVARD<br />
HONOLULU, HAWAII 96814
University of Hawaii <strong>Community</strong> <strong>College</strong>s<br />
Plan <strong>Development</strong> Report for<br />
The Learning Resource Center<br />
At <strong>Windward</strong> <strong>Community</strong> <strong>College</strong><br />
Subject: Roundtable #1 (Interactive Workshop) – Facility Programming<br />
Location: <strong>Windward</strong> <strong>Community</strong> <strong>College</strong><br />
Date: July 29, 2003<br />
Participants: See Attached Sign-up Sheet<br />
WORKSHOP NOTES:<br />
1. Summary of New Learning Resource Center by T. Findley<br />
• The Learning Resource Center is intended for social interaction<br />
• WCC confirmed that the users of the <strong>Library</strong> need a “physical” document<br />
to “hold” vs. reading everything electronically<br />
• House books and reference material and plan for expansion<br />
• Integrate computer-based data system<br />
• Provide “raised floor” system, or similar system for functional flexibility;<br />
the Learning Resource Center (<strong>Library</strong>) needs “pathways” for<br />
power, communication and/or data.<br />
• UH/WCC to confirm the budget for the facility.<br />
• Need a topographic survey to site the facility.<br />
2. Significance of the Learning Resource Center<br />
• WCC envisions the Learning Resource Center/<strong>Library</strong> as the Intellectual<br />
Center, and the Technology Center of campus<br />
• Visual identity and presence is important; architectural prominence; a<br />
memorable “sense of place”<br />
• A place for “gathering” and “socializing”<br />
• Impart a friendly and inviting atmosphere<br />
• Need to encourage “group” work; collaboration<br />
• Provide different venues for grouping, i.e., breakout niches, booths, other<br />
interactive spaces, etc.<br />
• Quiet areas for study; high energy areas for collaboration and group<br />
interaction<br />
3. Facility Program<br />
• WCC confirmed that the facility program is for current and future needs<br />
and should be viewed as “realistic” rather than “ideal”<br />
• UH/State will independently review the staffing requirements associated<br />
with the facility program<br />
1
<strong>Library</strong> Program<br />
• N. Heu confirmed that a security system is required for the Hawaiian<br />
Collection Room; need a service/check out counter<br />
Learning Center Functions (Glynnis Kinoshita)<br />
• Handwritten Testing<br />
• Placement Testing<br />
• Distant Educations (from other campuses)<br />
• General Study<br />
• Computer Center for Testing<br />
• Occasional Workshops<br />
• Computer Lab<br />
• Video Tapes for Language Arts (Math faculty not part of this facility)<br />
Computer Center (Michael Tom)<br />
• May need a “shared” computer facility since WCC has experienced<br />
difficulty with the upkeep and/or replacement of computers, i.e., a<br />
“shared” facility would reduce the total number of computers<br />
Staff Offices<br />
• Comment: “built-in furniture is not working”<br />
Instructional Media/Media Center (Elizabeth Ratliff)<br />
• Need “walk-up” counter for “drop-off” service<br />
• Shares staff with Duplication Room (usually students)<br />
• Audio Recording Room<br />
• Studio with Audio Booth<br />
• Multi-media<br />
• Uses specialized, high-end equipment<br />
Audio-Visual (Mike Bowles)<br />
• Computer area needs a “self-help” counter<br />
• A-V staff “troubleshoots” and assists the entire campus<br />
• Close-off computer room<br />
• Need a work area in the delivery dock for a compressor<br />
Site Meeting with the Outdoor Circle<br />
• Confirmed that the banyans are not listed as “exceptional trees,” but<br />
should be preserved; the example at the Campus Center is “acceptable”<br />
with the proper set backs for the retaining wall<br />
2
• Confirmed that the Hong Kong Orchid trees were “old,” however, the<br />
Outdoor Circle did not make any commitments with respect to removal, or<br />
relocation; similarly for the monkey pod<br />
• The Outdoor Circle recommended that we provide proposed plans prior to<br />
any proposed removal or relocation of trees.<br />
3
University of Hawaii <strong>Community</strong> <strong>College</strong>s<br />
Plan <strong>Development</strong> Report for<br />
The Learning Resource Center<br />
At <strong>Windward</strong> <strong>Community</strong> <strong>College</strong><br />
Subject: Roundtable #1 (Interactive Workshop) – Facility Programming<br />
Location: <strong>Windward</strong> <strong>Community</strong> <strong>College</strong><br />
Date: July 30, 2003<br />
Participants: See Attached Sign-up Sheet<br />
WORKSHOP NOTES:<br />
1. Existing Learning Center – Current Functions<br />
• Make-up Testing by subject (non-scheduled; at random)<br />
• Placement testing (Upward Bound)<br />
• Distant Education (some are non-students)<br />
• Quiet Area (as part of larger area) for overflow testing<br />
• Testing area: 25-30 seats for written testing (not computer)<br />
• Lab monitors typically observe testing<br />
• Tutoring: 1-5 concurrent sessions<br />
2. Construction Costs<br />
• UH/WCC directive: LAD to focus on cost of building only and “disregard”<br />
costs for the roadway, parking, infrastructure, renovation of existing<br />
building, etc. UH/WCC will further assess other costs that may be<br />
associated with the facility<br />
3. Other Costs<br />
• WCC anticipates need to relocate classrooms from Hale Manaleo to Hale<br />
No’eau or Hale La’akea. May need to account for these other costs<br />
associated with the development of the Learning Resource Center, if this<br />
is a negotiated point with State Historic Preservation.<br />
4. Facility Program Evaluation<br />
• See attached Block Diagrams<br />
5. Site Assessment<br />
• Participants evaluated the site at Hale Manaleo (north) and also another<br />
site at the south end of the “open space/quad”<br />
• Participants selected the site at the north end for the following reasons:<br />
- The north site is the designated location of the Learning<br />
Resource Center in the Plan Review Use Application and<br />
the Master Plan<br />
1
- The site at the south end “infringes” on the established<br />
open space and may require modification and re-approval<br />
of the PRU by the City<br />
- This location is closest to the existing and future<br />
classrooms<br />
- In proximity to the major parking areas<br />
- Has the potential to “synergize” the north end of the<br />
campus with the Theatre and Science facilities.<br />
2
University of Hawaii <strong>Community</strong> <strong>College</strong>s<br />
Plan <strong>Development</strong> Report for<br />
The Learning Resource Center<br />
At <strong>Windward</strong> <strong>Community</strong> <strong>College</strong><br />
Subject: Roundtable #2 (Interactive Workshop)<br />
Location: <strong>Windward</strong> <strong>Community</strong> <strong>College</strong> – Hale Akoakoa Rooms 107-109<br />
Date: October 22, 2003, 1:30 PM – 4:30 PM<br />
Participants: See Attached Sign-up Sheet<br />
WORKSHOP NOTES:<br />
1. Core Group Discussion: First Level Floor Plan<br />
• Locate Reference <strong>Library</strong> on outside wall<br />
• Add more seating around Reference Desk<br />
• Tech Services requested a location with exterior wall/daylight<br />
• Combine Computer Services Set-up Room, CS Staff Workroom and CS<br />
Storage; provide entry at each end with direct entry into Data Closet<br />
2. Core Group Discussion: Second Level Floor Plan<br />
• Discussed location of Listening & Viewing at the south end (outside wall<br />
location)<br />
• Instructional Media Service: flip Receptionist Desk to other side of entry<br />
next to Work Room and Copy Room<br />
• Instructional Media Service: locate Control Room adjacent to both<br />
Instructional Video Studio and Audio Recording Studio<br />
• Instructional Media Service: provide double doors for Electric<br />
Maintenance & Repair<br />
• Instructional Media Service: provide door from IDS to Media Lab<br />
• Relocate Hawaiian Room (Second Level) closer to Reference <strong>Library</strong> (on<br />
the First Level)<br />
• Show Service Entry on the Second Level Floor Plan (adjacent to Loading<br />
& Receiving)<br />
• Electronic Classroom location is good, i.e., accessible by IMS and TLC on<br />
the Second Level<br />
3. Engineering - Mechanical<br />
• Confirmed concept for HVAC system with Beall & Associates: a central<br />
plant with chillers; high ceiling; provision of four (4) air handling<br />
equipment/fan rooms.<br />
• Rule of thumb: (1) fan room per 9,000 – 10,000 square feet<br />
• 10,000 sf requires about 25 sf of ductwork<br />
• Prefer water-cooled central plant for chilled water system<br />
• Heat pump system – does not have chilled water piping; the air handling<br />
units would be the heat pump<br />
1
• Use a separate ducted system for outside air<br />
• Need a cooling tower outside<br />
• Discussed raised floor concept with under floor ducting for HVAC: the<br />
entire floor is a plenum – considered more experimental<br />
• Discouraged the use of skylights that produce direct radiation and<br />
increased heat gain<br />
• Discussed need for locating a transformer pad to bring in primary power<br />
2
University of Hawaii <strong>Community</strong> <strong>College</strong>s<br />
Plan <strong>Development</strong> Report for<br />
The Learning Resource Center<br />
At <strong>Windward</strong> <strong>Community</strong> <strong>College</strong><br />
Subject: Roundtable #2 (Interactive Workshop)<br />
Location: <strong>Windward</strong> <strong>Community</strong> <strong>College</strong> – Hale Akoakoa Rooms 107-109<br />
Date: October 23, 2003, 9:00 AM – 4:30 PM<br />
Participants: See Attached Sign-up Sheet<br />
WORKSHOP NOTES:<br />
1. Meeting #1: Computer Services Group (Dave Maxson)<br />
• Provide air conditioning for Server Room<br />
• Raised floor system is acceptable although prefers concrete floor for<br />
static free area<br />
2. Meeting #2: Instructional Media Services (Elizabeth Ratliff)<br />
• Don’t need a wall between the Copy Room and Work Room<br />
• Provide public access to New Media Lab, Instructional Video Lab and<br />
Audio Lab<br />
• Provide compressed air at Service Area<br />
• Provide secured area for two (2) gas-powered service carts<br />
• Related elements near Service Area: trash (dumpster); cooling tower;<br />
transformer<br />
3. Meeting #3: <strong>Library</strong> (Nancy Heu)<br />
• Confirmed provision of windows for Tech Services; relocate group to<br />
Ground Level southeast corner<br />
• Include office spaces for Head Librarian, Reference Librarians, Secretary<br />
and Conference Room<br />
• Fill-in area over Coffee Shop for 60,000 sf Collections<br />
• Move electronic Classroom closer to center of floor plan<br />
3. Commentary Meeting Input<br />
• Discussion regarding large meeting room<br />
• School newspaper requested jpeg image of color rendering<br />
(libby@hawaii.edu)<br />
1
4. Exit Meeting Summary<br />
Confirmed the following with UH CC (Maynard Young):<br />
• Pursue LEED Silver Certification for WCC Learning Resource Center<br />
• Include costs associated with LEED Certification<br />
• Design team may need to include a “sustainability” consultant for the<br />
LEED requirements<br />
• Include the following work in the project cost estimate: 1) Loop Road<br />
improvements at the north end of campus, i.e., clearing, retaining walls,<br />
paving/widening, street lighting, etc. 2) the plaza/amphitheater at the<br />
north end of the site; 3) the proposed parking area at the northeast end of<br />
campus has some old asbestos pipes; include cost of removal and<br />
disposal<br />
• As a reference the earliest availability for design funds is June 2005; the<br />
earliest UH can begin construction is June 2006<br />
• Provide cost estimate for base year June 2004 and assume a 4%<br />
escalation.<br />
Other Comments:<br />
• Science professor likes the amphitheater for viewing of the night-time<br />
activities associated with the Planetarium; project should ensure<br />
minimizing “light pollution” from the <strong>Library</strong>/Learning Resource Center<br />
onto the Planetarium<br />
2
University of Hawaii <strong>Community</strong> <strong>College</strong>s<br />
Plan <strong>Development</strong> Report for<br />
The Learning Resource Center<br />
At <strong>Windward</strong> <strong>Community</strong> <strong>College</strong><br />
Subject: Roundtable #3 (Interactive Workshop)<br />
Location: <strong>Windward</strong> <strong>Community</strong> <strong>College</strong> – Hale Akoakoa Rooms 107-109<br />
Date: November 19, 2003, 1:30 PM – 4:30 PM<br />
Participants: See Attached Sign-up Sheet<br />
WORKSHOP NOTES:<br />
1. Overview<br />
• LAD presented a PowerPoint overview of the revised concept plans<br />
• Presentation included Site Plan, Floor Plans, Site/Building Sections,<br />
Exterior Building Elevations and an Aerial Perspective<br />
• Incorporated input from Roundtable #2<br />
• Latest concept includes a 3 rd Floor for mechanical rooms, staff lounge<br />
and Director’s Office<br />
• Tech Services located on southeast corner of First Level<br />
• Hawaiian Room located adjacent to Circ Desk at First Level<br />
• Consolidated Group Study Rooms eastside of Second Level<br />
• TLC located on northeast quadrant of Second Level<br />
• Electronic Classroom centrally located on Second Level along major entry<br />
way<br />
TLC Comments:<br />
• Add door to patio from Staff Room (Third Level Floor Plan)<br />
• Flip Coordinator’s and Manager’s Offices<br />
IMS Comments:<br />
• Add back doors into New Media Lab and Electronic Classroom<br />
• Flip-flop location of Graphics, etc. with General Office, Intake, Media<br />
Coordinator, Clerk and Reception Desk<br />
• Incorporate vestibules at each entry, i.e, air locks<br />
2. Tomorrow’s (11/20/03) Meeting Schedule<br />
• 9:00 – 9:45 Computer Services<br />
• 9:45 – 10:30 <strong>Library</strong><br />
• 10:30 – 11:15 IMS<br />
• 11:15 – 12:00 Open<br />
• 1:00 - 1:45 TLC<br />
• 2:00 Core Group Exit Meeting<br />
1
University of Hawaii <strong>Community</strong> <strong>College</strong>s<br />
Plan <strong>Development</strong> Report for<br />
The Learning Resource Center<br />
At <strong>Windward</strong> <strong>Community</strong> <strong>College</strong><br />
Subject: Roundtable #3 (Interactive Workshop)<br />
Location: <strong>Windward</strong> <strong>Community</strong> <strong>College</strong> – Hale Akoakoa Room 201<br />
Date: November 20, 2003, 9:30 AM – 4:30 PM<br />
Participants: See Attached Sign-up Sheet<br />
WORKSHOP NOTES:<br />
1. 9:00 – 9:45 Computer Services Group (Dave Maxson, Brian Tokuda)<br />
• Combine Computer Set-up & Repair/Staff Room/Storage Room all into<br />
one room<br />
• Move Sec Room to C.S. Coordinator location and move C.S. Coordinator<br />
to Storage location; provide niche/access in the back of the Help Desk,<br />
i.e., at the former Sec Room location<br />
2. 9:45 – 10:30 <strong>Library</strong> Staff (Nancy Heu, Tara Severns)<br />
• Rotate four (4) functions at the Reference area, i.e., New Periodicals,<br />
Back File Periodicals, Listen/View and Reference Collection.<br />
• The solid north-south wall feature could incorporate see-through displays,<br />
windows or petroglyphs<br />
• Some discussion about State of Hawaii provision for artwork that is<br />
equivalent to 1% of the construction budget<br />
3. 10:30 – 11:15 Instructional Media Service (Elizabeth Ratliff, Michael<br />
Bowles)<br />
• Second Level layout is OK<br />
• Requested a sink in the Electronic Repair Shop<br />
3. 1:00 – 1:45 TLC (Aileen Yim, Jerry Levinson)<br />
• Discussion regarding testing room<br />
• Preliminary confirmation for (15) computers and (2) test seats<br />
4. 2:00 Exit Meeting<br />
• Comment made to revise plans to indicate “deeper” stairwells to include<br />
refuge area and out-swing doors<br />
• LAD to verify number of toilets and fixture count; add toilet (unisex) at<br />
southwest quadrant on First Level<br />
• Delete cooling tower designation at the Service Area and address remote<br />
location in the PDR narrative<br />
1
• Discuss raised floor system and locations in the narrative<br />
• Re-evaluate/relocate public elevator for better access by Circ Staff and<br />
acoustics (machine room noise)<br />
• Include following in cost estimate: 1) base building; 2) north end -<br />
perimeter road; 3) asbestos pipe clean-up; 4) LEED Certification<br />
(sustainable design); 4) demolition of Hale Manaleo<br />
• UH CC (M. Young) confirmed NOT to include any costs associated with<br />
Hale Noe’au or Hale La’akea<br />
• UH CC requested documentation of any meetings with State Historic<br />
Preservation regarding demolition of Hale Manaleo<br />
• UH CC indicated need for EA for this project and requested a fee<br />
proposal (LAD indicated that a preliminary meeting with OEQC confirmed<br />
that an EA is NOT required for the Learning Resource Center)<br />
• LAD anticipates DRAFT of Project <strong>Development</strong> Report on, or about<br />
December 15, 2003<br />
2
PROJECT DEVELOPMENT REPORT<br />
VOLUME I: PLANNING & CONCEPT DEVELOPMENT<br />
APPENDIX C<br />
MEETING NOTES<br />
PROJECT NO. CC-02-6188<br />
APRIL 2004<br />
1357 KAPIOLANI BOULEVARD<br />
HONOLULU, HAWAII 96814
M E M O R A N D U M<br />
PLANNING<br />
ARCHITECTURE<br />
ENGINEERING<br />
INTERIORS<br />
DATE<br />
TO<br />
FROM<br />
September 24, 2003<br />
Project File<br />
Sam Ustare<br />
PROJECT NO.<br />
810802-00<br />
EST. 1915<br />
ATLANTA<br />
AUSTIN<br />
BERLIN<br />
DALLAS<br />
HONG KONG<br />
HONOLULU<br />
HOUSTON<br />
LAS VEGAS<br />
LOS ANGELES<br />
MADRID<br />
OMAHA<br />
ORLANDO<br />
PHOENIX<br />
SAN ANTONIO<br />
WASHINGTON, DC<br />
PROJECT<br />
SUBJECT<br />
<strong>Windward</strong> <strong>Community</strong> <strong>College</strong><br />
Learning Resource Center<br />
Sewer System - Confirmation<br />
of Moratorium<br />
Telecom with Dennis Nishimura (ph: 527-6064) - Planner at DPP, Site <strong>Development</strong><br />
Division:<br />
1. Was referred to by Mr. Kevin Nakamura, District Engineer at Kaneohe Sewage<br />
Treatment Plant, ph: 254-4063.<br />
2. Mr. Nishimura confirmed that the moratorium on plumbing fixture units imposed by 92<br />
/ PRU-3, condition 4, limiting development to a one-to-one replacement until the<br />
Kaneohe Sewage Treatment Plant is expanded, was lifted in the mid 1990s.<br />
3. DPP, Site <strong>Development</strong> Division will determine if the number of plumbing fixtures is<br />
within the sewer system capacity for each project on a case-by-case basis.<br />
4. Applicant can download application on DPP website, Site <strong>Development</strong> Division,<br />
Master Application form, sewer portion.<br />
5. Send application to:<br />
City & County of Honolulu<br />
Department of Planning and Permitting<br />
Site <strong>Development</strong> Division<br />
650 South King Street, Honolulu<br />
Hawaii, HI 96814<br />
Attention Mr. Dennis Nishimura.<br />
6. A response will be provided within 2 working days. If the proposed project’s plumbing<br />
fixture unit count exceeds the sewer system’s capacity, DPP will work with the<br />
applicant on a solution to meet capacity.<br />
AMERICAN SAVINGS BUILDING<br />
SUITE 1230<br />
1357 KAPIOLANI BOULEVARD<br />
HONOLULU, HI 96814-4537<br />
TEL 808.521.8889<br />
FAX 808.521.3757<br />
www.leoadaly.com
PROJECT DEVELOPMENT REPORT<br />
VOLUME I: PLANNING & CONCEPT DEVELOPMENT<br />
APPENDIX D<br />
COPY OF ENVIRONMENTAL ASSESSMENT FOR<br />
WINDWARD COMMUNITY COLLEGE MASTER PLAN<br />
PROJECT NO. CC-02-6188<br />
APRIL 2004<br />
1357 KAPIOLANI BOULEVARD<br />
HONOLULU, HAWAII 96814
PROJECT DEVELOPMENT REPORT<br />
VOLUME I: PLANNING & CONCEPT DEVELOPMENT<br />
APPENDIX E<br />
CORRESPONDENCE – STATE HISTORIC PRESERVATION<br />
PROJECT NO. CC-02-6188<br />
APRIL 2004<br />
1357 KAPIOLANI BOULEVARD<br />
HONOLULU, HAWAII 96814
The Learning Resource Center at <strong>Windward</strong> <strong>Community</strong> <strong>College</strong><br />
PROGRAM PLANNING<br />
SUMMARY OF FUNCTIONS - ASSIGNABLE SQUARE FOOTAGE<br />
Function<br />
Number Function Description Units<br />
Student<br />
Stations<br />
Fac/Staff<br />
Stations<br />
Pre-Final<br />
I. Administration<br />
1 Director of Information Technology Services<br />
Office 1 1 200<br />
2 Institutional Researcher Office 1 1 200<br />
3 Secretary Office 1 2 175<br />
4 Administrative Storage Room 1 0<br />
5 Conference Room 1 600<br />
5a Male Restroom 1 50<br />
5b Female Restroom 1 50<br />
Subtotal 0 4 1,275<br />
II. <strong>Library</strong><br />
6 Vestibule 1 800<br />
7 Information Commons 1 48 2,700<br />
8 Information Commons Manager's Office 1 1 150<br />
9 Information Reference Desk Area 1 4 425<br />
10 Reference Collection Area 1 16 1,100<br />
11 Reference Librarian's Office (4 @ 115) 4 4 460<br />
12 Reference Librarians Conference Room 1 340<br />
13 Circulation Service Center 1 4 1,125<br />
14 Circulation Workroom 1 3 735<br />
15 Circulation Manager's Office 1 1 145<br />
16 Circulation Storage Room 1 200<br />
17 Current Periodicals Area 1 20 700<br />
18 Periodicals Backfile Area 1 12 700<br />
19 Microforms Area 1 5 550<br />
20 Pamphlets Area 1 4 155<br />
21 Maps/Art Prints Area 1 4 600<br />
22 Listening/Viewing Area 1 8 480<br />
23 Study Area A 1 22 1,000<br />
24 Hawaiian Collection Room 1 24 1 1,800<br />
25 Bookstacks Area 1 5,500<br />
26 Study Area B (shared w/ Learning Center) inc.<br />
6 study booths 1 110 4,100<br />
27 Group Viewing Room (1 @ 300 & 2 @ 170) 3 640<br />
28 Group Study Room (6 @ 150 & 2 @170) Area<br />
B 9 1,240<br />
29 Technical Services Room 1 4 1,130<br />
30 Technical Services Librarian's Office (Tech I) 1 1 140<br />
31 <strong>Library</strong> Technician's Office (Tech II) 1 1 130<br />
32 <strong>College</strong> Archives Room 1 600<br />
32a Circulation Storage Room 1 135<br />
33 Head Librarian's Office 1 1 240<br />
34 Secretary Office 1 1 195<br />
University of Hawaii <strong>Community</strong> <strong>College</strong>s December 2003<br />
Project No. CC-02-6188 1 PRE-FINAL
The Learning Resource Center at <strong>Windward</strong> <strong>Community</strong> <strong>College</strong><br />
PROGRAM PLANNING<br />
SUMMARY OF FUNCTIONS - ASSIGNABLE SQUARE FOOTAGE<br />
Function<br />
Number Function Description Units<br />
Student<br />
Stations<br />
Fac/Staff<br />
Stations<br />
Pre-Final<br />
35 Storage Room 1 200<br />
36 Staff Emergency Room and Lounge 1 800<br />
37 Meeting Room with 2 Closets @ 100 1 1,220<br />
38 Electronic Classroom 1 24 1 875<br />
39 Computer Laboratory 1 72 4 3,670<br />
39a 24-hour Study/Coffee Shop 1 30 1,500<br />
Subtotal 399 31 36,480<br />
III. The Learning Center (TLC)<br />
40 TLC Coordinator's Office 1 1 150<br />
41 TLC Manager 1 1 120<br />
42 Distribution Center 1 2 330<br />
43 Work Room 1 2 385<br />
44 Testing Room 1 25 810<br />
45 Quiet Study Area (Merged with Study Area ‘B’ -<br />
<strong>Library</strong> 1 0 5 0<br />
46 Resource Teacher Room 2 2 220<br />
47 STAAR Reception Area 1 2 180<br />
48 STAAR Counselor's Office 3 3 330<br />
49 STAAR Clerk-Typist Office 1 1 100<br />
50 STAAR Tutors' Office 1 2 235<br />
Subtotal 27 19 2,860<br />
IV. Computing Services<br />
51 Computing Services Coordinator's Office 1 1 215<br />
52 Computing Services Secretary Office 1 2 205<br />
53 Help Desk Room 1 2 285<br />
54 Training and Demonstration Room 1 2 440<br />
55 Staff Workroom 1 6 985<br />
56 Computer Setup and Repair Room 1 4 800<br />
57 Server Area 1 0 355<br />
58 Storage Room 1 200<br />
58a Bathroom 50<br />
Subtotal 0 17 3,535<br />
V. Instructional Media Services<br />
59 Reception Area/Counter/Equipment Check-out 1 3 210<br />
60 General Office, Job and Equipment Intake<br />
Room 1 6 450<br />
61 Clerk-Typist's Office 1 1 125<br />
62 Media Coordinator’s Office 1 1 200<br />
63 Storage Room 1 0 190<br />
64 Duplication and Copiers Room 1 1 610<br />
65 Duplication Storage Room 1 0 160<br />
66 Bindery Room 1 3 300<br />
University of Hawaii <strong>Community</strong> <strong>College</strong>s December 2003<br />
Project No. CC-02-6188 2 PRE-FINAL
The Learning Resource Center at <strong>Windward</strong> <strong>Community</strong> <strong>College</strong><br />
PROGRAM PLANNING<br />
SUMMARY OF FUNCTIONS - ASSIGNABLE SQUARE FOOTAGE<br />
Function<br />
Number Function Description Units<br />
Student<br />
Stations<br />
Fac/Staff<br />
Stations<br />
Pre-Final<br />
67 Duplication Manager's Office 1 1 140<br />
68 New Media Laboratory 1 20 1 620<br />
69 Instructional <strong>Development</strong> Specialist’s Office 1 1 110<br />
70 Media Production Specialist's Office 1 1 120<br />
71 Web Master's Office 1 1 125<br />
72 Studio Storage Room 1 0 110<br />
73 Instructional Video Studio 1 5 715<br />
74 Electronic Duplication and Distribution Room 1 3 450<br />
75 Studio Control Room 1 6 210<br />
76 Audio Recording Booth 1 2 125<br />
77 Electronic Maintenance and Repair Shop 1 3 745<br />
78 Electronic Technician I Office 1 1 145<br />
79 Electronic Technician II Office 1 1 145<br />
80 Equipment Storage Room 1 1 215<br />
81 Graphic Materials Preparation Room 1 4 4 850<br />
82 Graphic Artist’s Office 1 1 160<br />
83 Graphics Storage Room 1 0 115<br />
84 Spray Booth 0 70<br />
85 Loading and Receiving/Storage Room 0 900<br />
85a Bathroom 1 0 50<br />
Subtotal 29 42 8.365<br />
Subtotal (Assignable Square Feet) 455 113 52,515<br />
VI. Non-Assignable Square Feet/Building Support<br />
86. Atrium 1 3,500<br />
87. Delivery Area/Receiving (Merged with #85) 1<br />
88. Cart Parking Area 1 485<br />
89. Trash Area 1 250<br />
90. Wiring/Telecommunications Room (1 @ 1 440<br />
400)<br />
91. Wiring/Telecommunications Subroom (1 @ 4 415<br />
85, 1 @ 95, 1 @ 100, 1 @ 135)<br />
92. Janitorial Rooms (1 @ 45, 1 @ 60, 1 @ 65, 4 240<br />
1 @ 70)<br />
93. Central Housekeeping 1 160<br />
94. Central Mechanical Room 1 3,090<br />
95. Central Electrical Room 1 350<br />
96. Electrical Floor Closets (4 @ 60) 4 240<br />
97. Public Toilets (2 @ 280, 2 @ 285) 4 1,130<br />
98. Student Lockers/Bag Nitches (20 ½ length<br />
lockers)<br />
40 200<br />
University of Hawaii <strong>Community</strong> <strong>College</strong>s December 2003<br />
Project No. CC-02-6188 3 PRE-FINAL
The Learning Resource Center at <strong>Windward</strong> <strong>Community</strong> <strong>College</strong><br />
PROGRAM PLANNING<br />
SUMMARY OF FUNCTIONS - ASSIGNABLE SQUARE FOOTAGE<br />
Function<br />
Number Function Description Units<br />
Student<br />
Stations<br />
Fac/Staff<br />
Stations<br />
Pre-Final<br />
Subtotal (Non-Assignable Square Feet)<br />
10,500<br />
(VI)<br />
Subtotal Assignable Square<br />
52,515<br />
Feet (I-V)<br />
Subtotal (I-VI) 63,015<br />
VII. Horizontal & Vertical Circulation, Wall<br />
Thickness; Duct Shafts & Overhangs (+29.8%)<br />
18,778<br />
TOTAL GROSS SQUARE FEET 81,793<br />
GSF<br />
University of Hawaii <strong>Community</strong> <strong>College</strong>s December 2003<br />
Project No. CC-02-6188 4 PRE-FINAL
<strong>Windward</strong> <strong>Community</strong> <strong>College</strong><br />
Hale Manaleo
<strong>Windward</strong> <strong>Community</strong> <strong>College</strong><br />
Hale Manaleo